Completed

Aurangabad (M Corp.), Aurangabad 431005 |Promoter: Ankit Dharam Pahade

Residential / Group HousingRERAP51500025482
6 Jun 2020Registered with MahaRERA
1 Oct 2022Promised completion
1Building
12Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
2BHK12 units in all
Land area for this project
465 sq m (5,005 sq ft)
Permissible built-up area
759 sq m (8,172 sq ft)
Sanctioned built-up area
759 sq m (8,172 sq ft)
Address
Plot No 20 And 21 S.no.17 P Shahnoorwadi, S.no.17p, ShhnoorwadiPIN 431005
Designated bank account
Saraswat Cooperative Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 1 Oct 2022

The latest completion date on record passed 4 years ago.

Registered
6 Jun 2020
Promised
1 Oct 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P515000254826 Jun 20201 Oct 2022—Ankit Dharam PahadeProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Pahade Housing612

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

12 units registered

2BHK · 12 units
TypeCarpet areaUnits
2BHK38.56 sq m · 415 sq ft4
2BHK38.66 sq m · 416 sq ft4
2BHK39.03 sq m · 420 sq ft4

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Pahade Housing

  • Excavation0%
  • Basement (if any)1%
  • Podiums (if any)0%
  • Plinth1%
  • Stilt Floor1%
  • Slabs of Super Structure5%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyAS PER PERMISSION0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)AS PER PERMISSION0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingAS PER PERMISSION0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable
  • COMPOUND WALL AND ENTRANCE GATEAS PER PERMISSION0%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

14 documents held by Deedo, 16 filings listed on MahaRERA's project page

Allotment letters

Others

Registration certificate

Document library

  • Copy of the legal title reportSearch Report_compressed.pdf · uploaded 19 Mar 2020View
  • Building Plan Approval / NA Order for plotted developmentBuilding Plan_compressed.pdf · uploaded 19 Mar 2020View
  • Commencement Certificates / NA Order for plotted developmentCommencement Cert.pdf · uploaded 19 Mar 2020View
  • Proforma of Allotment letterAgreement_for_Sale_Format.pdf · uploaded 19 Mar 2020View
  • Proforma of Allotment letterproforma_allotment_letter.pdf · uploaded 19 Mar 2020View
  • Copy of Layout Approval (in case of layout)Layout_compressed.pdf · uploaded 19 Mar 2020View
  • Details of encumbrancesEncumbrances Certificate.pdf · uploaded 1 Jun 2020View
  • Declaration in FORM BAnkit Form B.pdf · uploaded 1 Jun 2020View
  • Disclosure of sold/ booked inventoryRera updation for Pahade Housing.pdf · uploaded 17 Dec 2021View
  • Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 1 Feb 2023View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentForm 4.pdf · uploaded 1 Feb 2023View

Promoter documents

  • Legal Title reportSearch Report_compressed.pdf · uploaded 19 Mar 2020View
  • Declaration Form BAnkit Form B.pdf · uploaded 1 Jun 2020View

Technical documents

  • Building Plan ApprovalBuilding Plan_compressed.pdfView
  • Layout ApprovalLayout_compressed.pdfView

Proforma allotment letter

  • Proforma allotment letterproforma_allotment_letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (M Corp.), Aurangabad taluka

Survey, CTS, gat or plot numbers

202121 S.NO.17 P SHAHNOORWADIPLOT NO 20

As published on MahaRERA's project page

PLOT NO 20 AND 21 S.NO.17 P SHAHNOORWADI

Boundaries

North
6m Road
South
6m Road
East
Rear Magine Plot 19
West
9m Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSaurabh Mirkute—
Chartered accountantYash Nagar—
EngineerSunil Katariya—
OtherSunil Katariya—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology