Completed

Aurangabad (M Corp.), Aurangabad 431001 |Promoter: Vision Ventures

Residential / Group HousingRERAP51500001044
25 Jul 2017Registered with MahaRERA
31 Dec 2019Promised completion
1Building
24Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
101, 102, 103, 104, 105, 106, 201, 202, 203, 204, 205, 206, 301, 302, 303, 304, 305, 306, 401, 402, 403, 404, 405, 40624 units in all
Land area for this project
881 sq m (9,479 sq ft)
Permissible built-up area
1,226 sq m (13,191 sq ft)
Sanctioned built-up area
1,226 sq m (13,191 sq ft)
Address
Plot No. 30, 31, 15840/90, 15840/91PIN 431001
Designated bank account
Saraswat Cooperative Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.62778, 74.17244
Orchid is at latitude 18.62778, longitude 74.17244.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2019

The latest completion date on record passed 6 years and 10 months ago.

Registered
25 Jul 2017
Promised
31 Dec 2019

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150000104425 Jul 201731 Dec 2019—Vision VenturesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Orchid624

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

24 units registered

101 · 1 unit102 · 1 unit103 · 1 unit104 · 1 unit105 · 1 unit106 · 1 unit201 · 1 unit202 · 1 unit203 · 1 unit204 · 1 unit205 · 1 unit206 · 1 unit301 · 1 unit302 · 1 unit303 · 1 unit304 · 1 unit305 · 1 unit306 · 1 unit401 · 1 unit402 · 1 unit403 · 1 unit404 · 1 unit405 · 1 unit406 · 1 unit
TypeCarpet areaUnits
10142.92 sq m · 462 sq ft1
10242.92 sq m · 462 sq ft1
10348.35 sq m · 520 sq ft1
10442.92 sq m · 462 sq ft1
10551.9 sq m · 559 sq ft1
10651.9 sq m · 559 sq ft1
20142.92 sq m · 462 sq ft1
20242.92 sq m · 462 sq ft1
20348.35 sq m · 520 sq ft1
20442.92 sq m · 462 sq ft1
20551.9 sq m · 559 sq ft1
20651.9 sq m · 559 sq ft1
30142.92 sq m · 462 sq ft1
30242.92 sq m · 462 sq ft1
30348.35 sq m · 520 sq ft1
30442.92 sq m · 462 sq ft1
30551.9 sq m · 559 sq ft1
30651.9 sq m · 559 sq ft1
40142.92 sq m · 462 sq ft1
40242.92 sq m · 462 sq ft1
40348.35 sq m · 520 sq ft1
40442.92 sq m · 462 sq ft1
40551.9 sq m · 559 sq ft1
40651.9 sq m · 559 sq ft1

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00001

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Orchid

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
  • Sanitary Fittings within the flats / premises50%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.35%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyBY AMC0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)BY AMC0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingBY COMPLETION50%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationBY COMPLETION70%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

24 documents held by Deedo, 31 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Proforma of Allotment letterAGREEMENT of Sale Flat-Orchid-RERA.pdf · uploaded 19 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE.pdf · uploaded 19 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 19 Jul 2017View
  • Building Plan Approval (IOD)BUILDING PLAN APPROVAL-PDF.pdf · uploaded 19 Jul 2017View
  • Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 19 Jul 2017View
  • Copy of the legal title reportLEGAL TITLE.pdf · uploaded 19 Jul 2017View
  • Details of encumbrancescertificate encumbrances.pdf · uploaded 20 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER.pdf · uploaded 21 Jul 2017View
  • OtherDEED.pdf · uploaded 24 Jul 2017View
  • Declaration in FORM BFORM B.pdf · uploaded 24 Jul 2017View
  • OtherCORRECTION_TO_THE_DOD_2323.pdf · uploaded 24 Jul 2017View
  • Certificates of CA (Form 5)RERA AUDIT.pdf · uploaded 15 Oct 2018View
  • Certificates of Architect (Form 4)VISION VENTURES CC.pdf · uploaded 14 Jan 2019View
  • OtherCOMPLETION CERTIFICATE.pdf · uploaded 14 Jan 2019View
  • OtherCOMPLETION CERTIFICATE MAP.pdf · uploaded 14 Jan 2019View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLETION CERTIFICATE.pdf · uploaded 18 Dec 2019View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)VISION VENTURE.pdf · uploaded 23 Dec 2019View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)VISION.pdf · uploaded 30 Jan 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)VISION VENTURE (ORCHID).pdf · uploaded 12 Apr 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)VISION VENTURE 2021-2022.pdf · uploaded 24 Apr 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)VISION VENTURE 2022-2023.pdf · uploaded 24 Apr 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)vision venture.pdf · uploaded 6 Mar 2025View

Promoter documents

  • Legal Title reportLEGAL TITLE.pdf · uploaded 19 Jul 2017View
  • Declaration Form BFORM B.pdf · uploaded 24 Jul 2017View

Technical documents

  • Building Plan ApprovalBUILDING PLAN APPROVAL-PDF.pdfView
  • Layout ApprovalLAYOUT.pdfView

Other legal documents

  • OtherDEED.pdfView
  • OtherCORRECTION_TO_THE_DOD_2323.pdfView
  • OtherCOMPLETION CERTIFICATE.pdfView
  • OtherCOMPLETION CERTIFICATE MAP.pdfView

Proforma allotment letter

  • Proforma allotment letterAGREEMENT of Sale Flat-Orchid-RERA.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (M Corp.), Aurangabad taluka

Survey, CTS, gat or plot numbers

15840/9015840/9015840/9115840/91303131PLOT NO. 30

As published on MahaRERA's project page

PLOT NO. 30 ,31, 15840/90 , 15840/91

Boundaries

North
Open Space
South
Plots 27 28 29
East
Road
West
Open Space

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDeepesh Suresh Parkar—
EngineerRajesh Baliram Vargantwar—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology