CompletedAurangabad (M Corp.), Aurangabad 431001 |Promoter: Tapadia Constructions Limited
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Completed
- Buildings
- 2
- Unit types
- 2BHK18 units in all
- Land area for this project
- 1,177 sq m (12,672 sq ft)
- Permissible built-up area
- 1,078 sq m (11,607 sq ft)
- Sanctioned built-up area
- 1,078 sq m (11,607 sq ft)
- Address
- Plot No. 8 To 16, Gut No. 155 Part, Near Daulatabad Road, MitmitaPIN 431001
- Designated bank account
- State Bank Of India
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Location
Coordinates as published by MahaRERA
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Mar 2026
The latest completion date on record passed 7 months ago.
- Registered
- 23 Mar 2020
- Promised
- 30 Mar 2026
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51500025226 | 23 Mar 2020 | 30 Mar 2026 | — | Tapadia Constructions Limited | Project page |
2 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Nath Park - Type A | 2 | 9 |
| Nath Park - Type B | 2 | 9 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
18 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Nath Park - Type A | 2BHK | 59.63 sq m · 642 sq ft | 9 |
| Nath Park - Type B | 2BHK | 59.63 sq m · 642 sq ft | 9 |
Parking
| Building | Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|---|
| Nath Park - Type A | Closed/Covered | 0 | 0 | 0 | 0 | 0 |
| Nath Park - Type A | Open Space | 0 | 0 | 0 | 0 | 0 |
| Nath Park - Type B | Closed/Covered | 0 | 0 | 0 | 0 | 0 |
| Nath Park - Type B | Open Space | 0 | 0 | 0 | 0 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress
Work completed, as the promoter reported it to MahaRERA (Form 1)
Nath Park - Type A
Nath Park - Type B
Common areas and amenities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Documents
18 documents held by Deedo, 21 filings listed on MahaRERA's project page
Others
- Other19 Mar 2020ViewSource
- Other19 Mar 2020ViewSource
- Other19 Mar 2020ViewSource
- Other19 Mar 2020ViewSource
- Other19 Mar 2020ViewSource
- Other30 Mar 2023ViewSource
- Other30 Mar 2023ViewSource
- Other30 Mar 2023ViewSource
- Other30 Mar 2023ViewSource
- Other3 Apr 2023ViewSource
- Other3 Apr 2023ViewSource
- Other3 Apr 2023ViewSource
- Other9 Jan 2025ViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
Document library
- Copy of the legal title reportSEARCH REPORT - NATH PARK.pdf · uploaded 19 Mar 2020View
- Details of encumbrancesTCL ENCUMBRANCE DECLARATION.pdf · uploaded 19 Mar 2020View
- Copy of Layout Approval (in case of layout)LAYOUT PLAN - NATH PARK.pdf · uploaded 19 Mar 2020View
- Building Plan Approval / NA Order for plotted developmentBUILDING PLAN - NATH PARK.pdf · uploaded 19 Mar 2020View
- Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE - NATH PARK.pdf · uploaded 19 Mar 2020View
- Declaration in FORM BFORM B - NATH PARK.pdf · uploaded 19 Mar 2020View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE FORM 2 - NATH PARK.pdf · uploaded 19 Mar 2020View
- Proforma of Allotment letterAGREEMENT TO SALE DRAFT - NATH PARK.pdf · uploaded 19 Mar 2020View
- Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 TAPADIA ESTATE PHASE 1 TAPADIA INFRAPROJECTS FY 2019 20.pdf · uploaded 30 Mar 2023View
- Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 TAPADIA ESTATE PHASE 1 TAPADIA INFRAPROJECTS FY 2020 21.pdf · uploaded 30 Mar 2023View
- Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 TAPADIA ESTATE PHASE 1 TAPADIA INFRAPROJECTS FY 2021 22.pdf · uploaded 30 Mar 2023View
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOCCUPANCY CERTIFICATE - NATH PARK AMC 03032022.pdf · uploaded 30 Mar 2023View
- Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 - NATH PARK - TAPADIA CON LTD FY 2019-20.pdf · uploaded 3 Apr 2023View
- Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 - NATH PARK - TAPADIA CON LTD FY 2020-21.pdf · uploaded 3 Apr 2023View
- Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 - NATH PARK - TAPADIA CON LTD FY 2021-22.pdf · uploaded 3 Apr 2023View
- Architect’s Certificate on Completion of Project (Form 4)Form 4 - Architect's Completion Certificate - Nath Park.pdf · uploaded 9 Jan 2025View
Promoter documents
Technical documents
Proforma allotment letter
- Proforma allotment letterAGREEMENT TO SALE DRAFT - NATH PARK.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Aurangabad (M Corp.), Aurangabad taluka
Survey, CTS, gat or plot numbers
As published on MahaRERA's project page
PLOT NO. 8 TO 16, GUT NO. 155 PART
Boundaries
- North
- Remaining Land In Gut No 155 Mitmita
- South
- Layouted Plot No 7
- East
- Remaining Land In Gut No 155 Mitmita
- West
- 7 And Half Metre Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Sarthak Associates Proprietor Santosh Sakhare | — |
| Chartered accountant | Pankaj K Gangwal | — |
| Engineer | Chaitanyi S Bhalerao | — |
Source: MahaRERA project page. Contact details are not shown.