Millenia Heights

Completed

Aurangabad (M Corp.), Aurangabad 431001 |Promoter: Laxminarayan Shriramji Attal

2 Jan 2018Registered with MahaRERA
15 Dec 2019Promised completion
9 Sep 2022Revised completionPushed back 2 years and 9 months
2Buildings
15Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Completed
Buildings
2
Unit types
Gfa, Gfb, Gfc, TypA, TypB, TypC15 units in all
Land area for this project
579 sq m (6,231 sq ft)
Permissible built-up area
1,187 sq m (12,774 sq ft)
Sanctioned built-up area
792 sq m (8,529 sq ft)
Address
Plot 44, CTS no. 20295/2/5, Ashoka Layout, BhagyanagarPIN 431001
Designated bank account
Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.87461, 75.32024
Millenia Heights is at latitude 19.87461, longitude 75.32024.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 2 years and 9 months

The latest completion date on record passed 4 years and 1 month ago.

Registered
2 Jan 2018
Promised
15 Dec 2019
Revised
9 Sep 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P515000147632 Jan 201815 Dec 20199 Sep 2022Laxminarayan Shriramji AttalProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Building (P51500014763)——
Millenia Heights715

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

15 units registered

Gfa · 1 unitGfb · 1 unitGfc · 1 unitTypA · 4 unitsTypB · 4 unitsTypC · 4 units
TypeCarpet areaUnits
Gfa56.79 sq m · 611 sq ft1
Gfb64.17 sq m · 691 sq ft1
Gfc57.34 sq m · 617 sq ft1
TypA79.58 sq m · 857 sq ft4
TypB77.28 sq m · 832 sq ft4
TypC71.94 sq m · 774 sq ft4

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000010
Open Space00006

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Millenia Heights

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyMunicipal Water Supply50%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Municipal Drainage line100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRain Water Harvesting100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open Parking6 cars parking proposed100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

33 documents held by Deedo, 48 filings listed on MahaRERA's project page

Title report

Commencement certificate (5)

Encumbrance details (3)

Show all 81 documentsShow fewer documents

Encumbrance details (3)

Form B

Registration certificate

Form 5 (4)

Allotment letter (2)

Other (6)

Occupancy / completion certificate (2)

  • Occupancy / completion certificate12 Jan 2022ViewSource
  • Occupancy / completion certificate18 Jul 2022ViewSource

Extension certificate

Form 4

Layout plan (5)

Building plan

Document library

  • Copy of the legal title reportSearch report_Legal.pdf · uploaded 12 Dec 2017View
  • Commencement Certificates / NA Order for plotted developmentConstruction Permission.pdf · uploaded 12 Dec 2017View
  • Building Plan Approval (IOD)Scanned_Approved_plan_Resized.pdf · uploaded 12 Dec 2017View
  • Details of encumbrancesLatest_PR Card.pdf · uploaded 19 Dec 2017View
  • Proforma of Allotment letterModel Agreement to sale_Rera.pdf · uploaded 20 Dec 2017View
  • Declaration in FORM BForm B_Affidavit_Resized.pdf · uploaded 23 Dec 2017View
  • Copy of Layout Approval (in case of layout)Scanned_Approved_plan_Resized.pdf · uploaded 27 Dec 2017View
  • Certificates of CA (Form 5)Form 5.pdf · uploaded 29 Sep 2018View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)CA Form 5 FY18-19.pdf · uploaded 28 Dec 2019View
  • OtherDECLARATION.pdf · uploaded 27 Jan 2020View
  • Proforma of Allotment letterAGREEMENT TO SALE.pdf · uploaded 27 Jan 2020View
  • Commencement Certificates / NA Order for plotted developmentRevised Commencement certificate.pdf · uploaded 28 Apr 2021View
  • Disclosure of sold/ booked inventoryDisclosure of sold booked inventory_compressed.pdf · uploaded 28 Apr 2021View
  • Building Plan Approval (IOD)Combined Revised plan_compressed (1).pdf · uploaded 28 Apr 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Millenia Heights_Form 5_FY 19-20.pdf · uploaded 4 Dec 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Millenia Heights_Form 5_FY 20-21.pdf · uploaded 4 Dec 2021View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPart Completion_compressed.pdf · uploaded 12 Jan 2022View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentDocScanner Jul 13, 2022 3-38 PM.pdf · uploaded 18 Jul 2022View
  • Commencement Certificates / NA Order for plotted developmentLast commencement.pdf · uploaded 27 Jul 2022View
  • Declaration about Commencement CertificateDeed of Correction 2.pdf · uploaded 28 Jul 2022View
  • Declaration about Commencement CertificateDeed of Correction_Final.pdf · uploaded 28 Jul 2022View
  • Copy of Layout Approval (in case of layout)Permission_March 1 of 2_compressed.pdf · uploaded 28 Jul 2022View
  • Copy of Layout Approval (in case of layout)Permission_March 2 of 2_compressed.pdf · uploaded 28 Jul 2022View
  • Copy of Layout Approval (in case of layout)Final Permission 1 of 2_compressed.pdf · uploaded 28 Jul 2022View
  • Copy of Layout Approval (in case of layout)Final Permission_2 of 2_compressed.pdf · uploaded 28 Jul 2022View
  • Building Plan Approval (IOD)Permission_March 1 of 2_compressed.pdf · uploaded 28 Jul 2022View
  • Building Plan Approval (IOD)Permission_March 2 of 2_compressed.pdf · uploaded 28 Jul 2022View
  • Building Plan Approval (IOD)Final Permission 1 of 2_compressed.pdf · uploaded 28 Jul 2022View
  • Building Plan Approval (IOD)Final Permission_2 of 2_compressed.pdf · uploaded 28 Jul 2022View
  • b Details of encumbrances concerned to LegalFree from encumberances letter.pdf · uploaded 5 Sep 2022View
  • Disclosure of sold/ booked inventoryDisclosure of Sold Booked inventory.pdf · uploaded 5 Sep 2022View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate bank account declaration.pdf · uploaded 5 Sep 2022View
  • Architect’s Certificate on Completion of Project (Form 4)Form 4 signed copy.pdf · uploaded 20 Oct 2022View

Promoter documents

  • Legal Title reportSearch report_Legal.pdf · uploaded 12 Dec 2017View
  • Declaration Form BForm B_Affidavit_Resized.pdf · uploaded 23 Dec 2017View

Technical documents

  • Layout ApprovalPermission_March 1 of 2_compressed.pdfView
  • Layout ApprovalPermission_March 2 of 2_compressed.pdfView
  • Layout ApprovalFinal Permission 1 of 2_compressed.pdfView
  • Layout ApprovalFinal Permission_2 of 2_compressed.pdfView
  • Building Plan ApprovalPermission_March 1 of 2_compressed.pdfView
  • Building Plan ApprovalPermission_March 2 of 2_compressed.pdfView
  • Building Plan ApprovalFinal Permission 1 of 2_compressed.pdfView
  • Building Plan ApprovalFinal Permission_2 of 2_compressed.pdfView
  • Building Plan ApprovalScanned_Approved_plan_Resized.pdfView
  • Layout ApprovalScanned_Approved_plan_Resized.pdfView
  • Building Plan ApprovalCombined Revised plan_compressed (1).pdfView

Other legal documents

  • OtherDECLARATION.pdfView

Proforma allotment letter

  • Proforma allotment letterModel Agreement to sale_Rera.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (M Corp.), Aurangabad taluka

Survey, CTS, gat or plot numbers

20295/2/544CTS no. 20295/2/5Plot 44

As published on MahaRERA's project page

Plot 44, CTS no. 20295/2/5

Boundaries

North
Land Belongs to SCR
South
Layout road 9m
East
Layout Road 12m
West
Layout Open Space

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectInnerspace DesignStudio—
ArchitectSachin Sangshetty Architects—
EngineerAnil Datar & Associates—
OtherS K Constructions—

Source: MahaRERA project page. Contact details are not shown.