Mahalaxmi Alankar

Completed

Aurangabad (M Corp.), Aurangabad 431005 |Promoter: Mahalaxmi Builders

Residential / Group HousingRERAP51500001362
27 Jul 2017Registered with MahaRERA
30 Dec 2024Promised completion
3Buildings
60Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
3
Unit types
2 BHK60 units in all
Land area for this project
1,836 sq m (19,765 sq ft)
Permissible built-up area
4,012 sq m (43,180 sq ft)
Sanctioned built-up area
2,562 sq m (27,573 sq ft)
Address
Gut No 70, Plot 27-30PIN 431005
Designated bank account
Saraswat Cooperative Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.85050, 75.35210
Mahalaxmi Alankar is at latitude 19.85050, longitude 75.35210.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2024

The latest completion date on record passed 1 year and 10 months ago.

Registered
27 Jul 2017
Promised
30 Dec 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150000136227 Jul 201730 Dec 2024—Mahalaxmi BuildersProject page

3 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Wing A720
Wing B720
Wing C720

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

60 units registered

2 BHK · 60 units
BuildingTypeCarpet areaUnits
Wing A2 BHK45.97 sq m · 495 sq ft5
Wing A2 BHK47.59 sq m · 512 sq ft5
Wing A2 BHK50.78 sq m · 547 sq ft5
Wing A2 BHK52.4 sq m · 564 sq ft5
Wing B2 BHK47.59 sq m · 512 sq ft10
Wing B2 BHK52.4 sq m · 564 sq ft10
Wing C2 BHK45.97 sq m · 495 sq ft5
Wing C2 BHK47.59 sq m · 512 sq ft5
Wing C2 BHK50.78 sq m · 547 sq ft5
Wing C2 BHK52.4 sq m · 564 sq ft5

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Wing AClosed/Covered00001
Wing AOpen Space00000
Wing BClosed/Covered00001
Wing BOpen Space00000
Wing CClosed/Covered00001
Wing COpen Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Wing A

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Wing B

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Wing C

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyBy Boarwell Only100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Drainage Line till Corporation Chamber100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingTree Plantation around compound wall100%
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRain Water Harvesting As per corporation norms100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationMeter Room100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

23 documents held by Deedo, 28 filings listed on MahaRERA's project page

Commencement certificate

Title report

Form B

Form 2 (2)

Encumbrance details

Form 1 (2)

Show all 51 documentsShow fewer documents

Form 5

Registration certificate

Occupancy / completion certificate

  • Occupancy / completion certificate5 Dec 2022ViewSource

Other (10)

Layout plan

Allotment letter

Document library

  • Copy of Layout Approval (in case of layout)Building PLAN Mahalaxmi Alankar.pdf · uploaded 17 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentimg-717095143.pdf · uploaded 17 Jul 2017View
  • Building Plan Approval (IOD)Building PLAN Mahalaxmi Alankar.pdf · uploaded 17 Jul 2017View
  • Copy of the legal title reportsearch report.pdf · uploaded 20 Jul 2017View
  • Declaration in FORM BDeveloper Form B.pdf · uploaded 21 Jul 2017View
  • Proforma of Allotment letterATS Malaxmi Alankar.pdf · uploaded 21 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 24 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg Certificate.pdf · uploaded 24 Jul 2017View
  • Details of encumbrancesRERA LETTER 1.pdf · uploaded 25 Jul 2017View
  • OtherPropsed Plan 1compressed.pdf · uploaded 25 Jul 2017View
  • OtherProposed Plan 2-compressed.pdf · uploaded 25 Jul 2017View
  • Certificates of CA (Form 5)Report (1).pdf · uploaded 13 Oct 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 13 Oct 2018View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg Certificate (1).pdf · uploaded 13 Oct 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 13 Oct 2018View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg Certificate (1).pdf · uploaded 13 Oct 2018View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupancy Certificate.pdf · uploaded 5 Dec 2022View
  • Status of ConveyanceAOP Alankar-1-12_compressed.pdf · uploaded 5 Dec 2022View
  • Status of ConveyanceAOP Alankar-13-24_compressed.pdf · uploaded 5 Dec 2022View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)alankar 1 form 1.pdf · uploaded 7 Dec 2022View
  • Status of Formation of Legal Entity (Society/Co Op etc.)AOP Alankar-1-12_compressed.pdf · uploaded 7 Dec 2022View

Promoter documents

  • Legal Title reportsearch report.pdf · uploaded 20 Jul 2017View
  • Declaration Form BDeveloper Form B.pdf · uploaded 21 Jul 2017View

Technical documents

  • Layout ApprovalBuilding PLAN Mahalaxmi Alankar.pdfView
  • Building Plan ApprovalBuilding PLAN Mahalaxmi Alankar.pdfView

Other legal documents

  • OtherPropsed Plan 1compressed.pdfView
  • OtherProposed Plan 2-compressed.pdfView

Proforma allotment letter

  • Proforma allotment letterATS Malaxmi Alankar.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (M Corp.), Aurangabad taluka

Survey, CTS, gat or plot numbers

Gut No 70Plot 2730

As published on MahaRERA's project page

Gut No 70 , Plot 27-30

Boundaries

North
7-5 M wide Road
South
Plot 26 Open Space of Layout and Plot 31
East
9 M Wide Road
West
7-5 M Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDhananjay Doifode—
EngineerAbhay Patil—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology