Aurangabad (M Corp.), Aurangabad 431001 |Promoter: Sanjay Arjundas Dawarani

16 Feb 2022Registered with MahaRERA
10 Aug 2024Promised completion
1Building
26Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Lapsed
Buildings
1
Unit types
Office space, Shop, Store26 units in all
Land area for this project
300 sq m (3,226 sq ft)
Permissible built-up area
1,026 sq m (11,044 sq ft)
Sanctioned built-up area
1,026 sq m (11,044 sq ft)
Address
17631, Nutan Colony, AurangabadPIN 431001
Designated bank account
Axis Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Kbc Towers is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 10 Aug 2024

The latest completion date on record passed 2 years and 2 months ago.

Registered
16 Feb 2022
Promised
10 Aug 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150003338416 Feb 202210 Aug 2024—Sanjay Arjundas DawaraniProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Kbc Towers926

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

26 units registered

Office space · 20 unitsShop · 3 unitsStore · 3 units
TypeCarpet areaUnits
Office space25.68 sq m · 276 sq ft5
Office space29.76 sq m · 320 sq ft5
Office space30 sq m · 323 sq ft5
Office space33.6 sq m · 362 sq ft5
Shop6.1 sq m · 66 sq ft1
Shop45.93 sq m · 494 sq ft1
Shop64.75 sq m · 697 sq ft1
Store8.1 sq m · 87 sq ft3

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Kbc Towers

  • Excavation100%
  • Basement (if any)40%
  • Podiums (if any)0%
  • Plinth40%
  • Stilt Floor0%
  • Slabs of Super Structure15%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyWORK IN PROGRESS0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)WORK IN PROGRESS0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingWORK IN PROGRESS0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementswork in progress0%
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingWORK IN PROGRESS0%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

13 documents held by Deedo, 16 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Commencement Certificates / NA Order for plotted developmentCommencement Certficate.PDF · uploaded 7 Sep 2021View
  • Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 12 Sep 2021View
  • Proforma of Allotment letteragreement to sale.pdf · uploaded 29 Oct 2021View
  • Building Plan Approval / NA Order for plotted developmentPlan 1 nov 2021.pdf · uploaded 22 Jan 2022View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate.PDF · uploaded 22 Jan 2022View
  • Declaration in FORM BForm B.PDF · uploaded 27 Jan 2022View
  • Details of encumbrancesNon Encumbramce Certificate.PDF · uploaded 27 Jan 2022View
  • Declaration about Commencement CertificateFormat D.PDF · uploaded 27 Jan 2022View
  • CERSAI detailsKBC CERSAI.pdf · uploaded 27 Jan 2022View
  • Copy of the legal title reportSearch Report.PDF · uploaded 4 Feb 2022View
  • Copy of Layout Approval (in case of layout)download.pdf · uploaded 4 Feb 2022View

Promoter documents

  • Declaration Form BForm B.PDF · uploaded 27 Jan 2022View
  • Legal Title reportSearch Report.PDF · uploaded 4 Feb 2022View

Technical documents

  • Building Plan ApprovalPlan 1 nov 2021.pdfView
  • Layout Approvaldownload.pdfView

Proforma allotment letter

  • Proforma allotment letterALLOTMENT LETTER.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (M Corp.), Aurangabad taluka

Survey, CTS, gat or plot numbers

17631

As published on MahaRERA's project page

17631

Boundaries

North
Road
South
House Of Yaqub Bastan
East
House Of Nanaklal Wadhwani
West
House Of Mohd Khaja Quireshi

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMd Yunus & Associates—
Chartered accountantS A Jaju & Company—
Engineermd yunus & associates—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology