Jogeshwari Apartment

Lapsed

Aurangabad (M Corp.), Aurangabad 431009 |Promoter: Panchshil Builders

Residential / Group HousingRERAP51500055087
29 Feb 2024Registered with MahaRERA
23 Dec 2024Promised completion
30 Jun 2025Revised completionPushed back 6 months
1Building
16Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Lapsed
Buildings
1
Unit types
2BHK16 units in all
Land area for this project
557 sq m (6,000 sq ft)
Permissible built-up area
1,232 sq m (13,258 sq ft)
Sanctioned built-up area
1,232 sq m (13,258 sq ft)
Address
Plot No 17-18 Gut No 51/4 Garkheda, Plot No 17-18, Gut No 51/4, , GarkhedaPIN 431009
Designated bank account
Hdfc Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Jogeshwari Apartment is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 6 months

The latest completion date on record passed 1 year and 4 months ago.

Registered
29 Feb 2024
Promised
23 Dec 2024
Revised
30 Jun 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150005508729 Feb 202423 Dec 202430 Jun 2025Panchshil BuildersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Jogeshwari Apartment516

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

16 units registered

2BHK · 16 units
TypeCarpet areaUnits
2BHK63.97 sq m · 689 sq ft16

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space000016

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Jogeshwari Apartment

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyNot applicable
  • Sewerage (Chamber, Lines, Septic Tank , STP)YET TO START70%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationYET TO START70%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

41 documents held by Deedo, 56 filings listed on MahaRERA's project page

Others

Registration certificate

Extension certificate

Document library

  • Copy of the legal title reportSearch Report.pdf · uploaded 9 Jan 2024View
  • a Details of encumbrances concerned to Financeencumbrace legal.pdf · uploaded 9 Jan 2024View
  • a Details of encumbrances concerned to Financeno encumbrace legal.pdf · uploaded 9 Jan 2024View
  • b Details of encumbrances concerned to Legalencumbrace legal.pdf · uploaded 9 Jan 2024View
  • b Details of encumbrances concerned to Legalno encumbrace legal.pdf · uploaded 9 Jan 2024View
  • Copy of Layout Approval (in case of layout)33 02 SANCTIONED BP POROPSAL 24012024.pdf · uploaded 9 Jan 2024View
  • Building Plan Approval / NA Order for plotted developmentpermission.pdf · uploaded 9 Jan 2024View
  • Commencement Certificates / NA Order for plotted developmentpermission.pdf · uploaded 9 Jan 2024View
  • Declaration about Commencement Certificateformat d permission.pdf · uploaded 9 Jan 2024View
  • Disclosure of Interest in Other Real Estate Organizationsann a Sachin.pdf · uploaded 9 Jan 2024View
  • Disclosure of Interest in Other Real Estate Organizationsann a satish.pdf · uploaded 9 Jan 2024View
  • Proforma of Agreement for saleRERA_Agreement_for_Sale_Format _1_.pdf · uploaded 9 Jan 2024View
  • Proforma of Allotment letterFinal Allotment letter.pdf · uploaded 9 Jan 2024View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameformat a bank.pdf · uploaded 9 Jan 2024View
  • Deviation Report with respect to Allotment letterdevialtion allotmemt.pdf · uploaded 9 Jan 2024View
  • Deviation Report with respect to model copy of Agreementdeviation ats.pdf · uploaded 9 Jan 2024View
  • a Details of encumbrances concerned to Financecertificate legal.pdf · uploaded 9 Jan 2024View
  • b Details of encumbrances concerned to Legalcertificate legal.pdf · uploaded 9 Jan 2024View
  • Declaration in FORM Bform b developer.pdf · uploaded 11 Jan 2024View
  • Other – LegalGmail - Fwd_ 33 02 SANTION BP POROPSAL 24012024.pdf · uploaded 27 Jan 2024View
  • CERSAI detailsNO cresai.pdf · uploaded 27 Jan 2024View
  • CERSAI detailscresai report.pdf · uploaded 27 Jan 2024View
  • Copy of Layout Approval (in case of layout)33 02 SANCTIONED BP POROPSAL 24012024.pdf · uploaded 27 Feb 2024View
  • Other – TechnicalSanjay Rathi to Krishna Malu_1_compressed.pdf · uploaded 27 Feb 2024View
  • Other – TechnicalSanjay Rathi to Krishna Malu_2_compressed.pdf · uploaded 27 Feb 2024View
  • Building Plan Approval / NA Order for plotted developmentpermission plan2.pdf · uploaded 27 Feb 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Letter RERA.pdf · uploaded 2 May 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH CERTIFICATE.pdf · uploaded 6 Jun 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Form 17 May 24.pdf · uploaded 6 Jun 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECTS CERTIFICATE 30_06_2024.pdf · uploaded 2 Jan 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECTS CERTIFICATE 30_09_2024.pdf · uploaded 2 Jan 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE 30_06_2024.pdf · uploaded 2 Jan 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE 30_09_2024.pdf · uploaded 2 Jan 2025View
  • Disclosure of sold/ booked inventorysold inventory 1.pdf · uploaded 2 Jan 2025View
  • Disclosure of sold/ booked inventorysold inventory 2.pdf · uploaded 2 Jan 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 31_03_25 panchshil.pdf · uploaded 14 Apr 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 31_3_25.pdf · uploaded 14 Apr 2025View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)form 2a 31_3_25.pdf · uploaded 14 Apr 2025View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)form 5 31_03_25.pdf · uploaded 14 Apr 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)formarchitect certificate.pdf · uploaded 14 Apr 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2engineer certifiate.pdf · uploaded 14 Apr 2025View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)form 2a 31_3_25.pdf · uploaded 14 Apr 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 31_03_25 panchshil.pdf · uploaded 19 May 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 31_3_25.pdf · uploaded 19 May 2025View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)form 5 31_03_25.pdf · uploaded 19 May 2025View
  • Declaration in FORM BForm B Rera Panchshil Builders.pdf · uploaded 19 May 2025View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5 31_03_25.pdf · uploaded 19 May 2025View

Promoter documents

  • Legal Title reportSearch Report.pdf · uploaded 9 Jan 2024View
  • Declaration Form Bform b developer.pdf · uploaded 11 Jan 2024View
  • Declaration Form BForm B Rera Panchshil Builders.pdf · uploaded 19 May 2025View

Technical documents

  • Layout Approval33 02 SANCTIONED BP POROPSAL 24012024.pdfView
  • Building Plan Approvalpermission.pdfView
  • Layout Approval33 02 SANCTIONED BP POROPSAL 24012024.pdfView
  • Building Plan Approvalpermission plan2.pdfView

Other legal documents

  • Other – LegalGmail - Fwd_ 33 02 SANTION BP POROPSAL 24012024.pdfView

Proforma allotment letter

  • Proforma allotment letterFinal Allotment letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (M Corp.), Aurangabad taluka

Survey, CTS, gat or plot numbers

PLOT NO 1718 GUT NO 51/4 GARKHEDA

As published on MahaRERA's project page

PLOT NO 17-18 GUT NO 51/4 GARKHEDA

Boundaries

North
Plot No 16
South
Plot No 19
East
9 Mtr Wide Road
West
Area For School And Play Ground

Source: registration certificates and MahaRERA's project page, as stated there.