Hrim Sky City Elite
ActiveAurangabad (M Corp.), Aurangabad 431010 |Promoter: Narayanii Buildcreation Private Limited
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Active
- Buildings
- 5
- Unit types
- 3BHK51 units in all
- Land area for this project
- 2,849 sq m (30,666 sq ft)
- Permissible built-up area
- 10,878 sq m (1,17,092 sq ft)
- Sanctioned built-up area
- 5,180 sq m (55,759 sq ft)
- Address
- Gut No 65 Part 1 2 3 Opposite Mit College Near Beed Bypass Tq And Dist Chhatrapati Sambhajinagar, Beed Bypass, Opposite Mit CollegePIN 431010
- Designated bank account
- State Bank Of India
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Location
Coordinates as published by MahaRERA
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2028
- Registered
- 15 Feb 2024
- Promised
- 31 Dec 2028
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51500054900 | 15 Feb 2024 | 31 Dec 2028 | — | Narayanii Buildcreation Private Limited | Project page |
5 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Row House 18 to 31 | 2 | 14 |
| Row House 1 to 5 | 2 | 5 |
| Row House 32 to 44 | 2 | 13 |
| Row House 54 to 60 | 2 | 7 |
| Row House 6 To 17 | 2 | 12 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
51 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Row House 18 to 31 | 3BHK | 88.89 sq m · 957 sq ft | 14 |
| Row House 1 to 5 | 3BHK | 88.89 sq m · 957 sq ft | 5 |
| Row House 32 to 44 | 3BHK | 88.89 sq m · 957 sq ft | 13 |
| Row House 54 to 60 | 3BHK | 88.89 sq m · 957 sq ft | 7 |
| Row House 6 To 17 | 3BHK | 88.89 sq m · 957 sq ft | 12 |
Parking
| Building | Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|---|
| Row House 18 to 31 | Closed/Covered | 0 | 0 | 0 | 0 | 14 |
| Row House 18 to 31 | Open Space | 0 | 0 | 0 | 0 | 14 |
| Row House 1 to 5 | Closed/Covered | 0 | 0 | 0 | 0 | 5 |
| Row House 1 to 5 | Open Space | 0 | 0 | 0 | 0 | 5 |
| Row House 32 to 44 | Closed/Covered | 0 | 0 | 0 | 0 | 13 |
| Row House 32 to 44 | Open Space | 0 | 0 | 0 | 0 | 13 |
| Row House 54 to 60 | Closed/Covered | 0 | 0 | 0 | 0 | 7 |
| Row House 54 to 60 | Open Space | 0 | 0 | 0 | 0 | 7 |
| Row House 6 To 17 | Closed/Covered | 0 | 0 | 0 | 0 | 12 |
| Row House 6 To 17 | Open Space | 0 | 0 | 0 | 0 | 12 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress
Work completed, as the promoter reported it to MahaRERA (Form 1)
Row House 18 to 31
Row House 1 to 5
Row House 32 to 44
Row House 54 to 60
Row House 6 To 17
Common areas and amenities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Documents
62 documents held by Deedo, 64 filings listed on MahaRERA's project page
Others
- Other3 Jun 2023ViewSource
- Other3 Nov 2023ViewSource
- Other3 Nov 2023ViewSource
- Other3 Nov 2023ViewSource
- Other3 Nov 2023ViewSource
- Other3 Nov 2023ViewSource
- Other3 Nov 2023ViewSource
- Other3 Nov 2023ViewSource
- Other3 Nov 2023ViewSource
- Other3 Nov 2023ViewSource
- Other10 Nov 2023ViewSource
- Other10 Nov 2023ViewSource
- Other10 Nov 2023ViewSource
- Other10 Nov 2023ViewSource
- Other16 Nov 2023ViewSource
- Other16 Nov 2023ViewSource
- Other29 Jan 2024ViewSource
- Other3 Feb 2024ViewSource
- Other20 Dec 2025ViewSource
- Other20 Dec 2025ViewSource
- Other20 Dec 2025ViewSource
- Other20 Dec 2025ViewSource
- Other20 Dec 2025ViewSource
- Other20 Dec 2025ViewSource
- Other20 Dec 2025ViewSource
- Other20 Dec 2025ViewSource
- Other20 Dec 2025ViewSource
- Other20 Dec 2025ViewSource
- Other20 Dec 2025ViewSource
- Other20 Dec 2025ViewSource
- Other20 Dec 2025ViewSource
- Other20 Dec 2025ViewSource
- Other20 Dec 2025ViewSource
- Other20 Dec 2025ViewSource
- Other20 Dec 2025ViewSource
- Other20 Dec 2025ViewSource
- Other29 Dec 2025ViewSource
- Other29 Dec 2025ViewSource
- Other29 Dec 2025ViewSource
- Other11 Feb 2026ViewSource
- Other11 Feb 2026ViewSource
- Other11 Feb 2026ViewSource
- Other12 Feb 2026ViewSource
- Other12 Feb 2026ViewSource
- Other26 May 2026ViewSource
- Other26 May 2026ViewSource
- Other26 May 2026ViewSource
- Other13 Aug 2026ViewSource
- Other13 Aug 2026ViewSource
- Other13 Aug 2026ViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
Document library
- Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 3 Nov 2023View
- Deviation Report with respect to Allotment letterAllotment Letter.pdf · uploaded 3 Nov 2023View
- Deviation Report with respect to model copy of AgreementAgreement To Sale.pdf · uploaded 3 Nov 2023View
- Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 3 Nov 2023View
- CERSAI detailsCERSAI Declaration.pdf · uploaded 3 Nov 2023View
- a Details of encumbrances concerned to FinanceNo Eng Fin.pdf · uploaded 3 Nov 2023View
- a Details of encumbrances concerned to FinanceNo Eng Legal.pdf · uploaded 3 Nov 2023View
- b Details of encumbrances concerned to LegalNo Eng Fin.pdf · uploaded 3 Nov 2023View
- b Details of encumbrances concerned to LegalNo Eng Legal.pdf · uploaded 3 Nov 2023View
- Disclosure of Interest in Other Real Estate OrganizationsAnnexure-A ( Ashwin Baheti ).pdf · uploaded 3 Nov 2023View
- Disclosure of Interest in Other Real Estate OrganizationsAnnexure-A ( Ashokkumar Baheti ).pdf · uploaded 3 Nov 2023View
- Proforma of Allotment letterModal From Of Allotment Letter.pdf · uploaded 3 Nov 2023View
- Proforma of Agreement for saleATS Draft RERA.pdf · uploaded 3 Nov 2023View
- Copy of Layout Approval (in case of layout)layout_compressed.pdf · uploaded 3 Nov 2023View
- Building Plan Approval / NA Order for plotted developmentorganized layout_compressed.pdf · uploaded 3 Nov 2023View
- Copy of the legal title reportNarayani - Search Report.pdf · uploaded 10 Nov 2023View
- Declaration about Commencement CertificateFormat D.pdf · uploaded 10 Nov 2023View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Sep-23.pdf · uploaded 10 Nov 2023View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Sep-23.pdf · uploaded 10 Nov 2023View
- Other – TechnicalAPPENDIX F (1)_compressed.pdf · uploaded 16 Nov 2023View
- Declaration in FORM BForm B ( Devlopers ).pdf · uploaded 16 Nov 2023View
- Building Plan Approval / NA Order for plotted development8 of 8_compressed.pdf · uploaded 16 Nov 2023View
- Other – TechnicalCC Verification Mail.pdf · uploaded 29 Jan 2024View
- Other – TechnicalNarayani Plot Declaration.pdf · uploaded 3 Feb 2024View
- Building Plan Approval / NA Order for plotted development7 of 8_compressed.pdf · uploaded 3 Feb 2024View
- Form 1Form-1 Dec 23.pdf · uploaded 20 Dec 2025View
- Form 2Form-2 Dec 23.pdf · uploaded 20 Dec 2025View
- Disclosure of Sold and Booked InventorySold Dec 23.pdf · uploaded 20 Dec 2025View
- Form 1Form-1 June 24.pdf · uploaded 20 Dec 2025View
- Form 2Form-2 June 24.pdf · uploaded 20 Dec 2025View
- Disclosure of Sold and Booked InventorySold June 24.pdf · uploaded 20 Dec 2025View
- Form 1Form-1 Sep 24.pdf · uploaded 20 Dec 2025View
- Form 2Form-2 Sep 24.pdf · uploaded 20 Dec 2025View
- Disclosure of Sold and Booked InventorySold Sep 24.pdf · uploaded 20 Dec 2025View
- Form 1Form-1 Dec 24.pdf · uploaded 20 Dec 2025View
- Form 2Form-2 Dec 24.pdf · uploaded 20 Dec 2025View
- Disclosure of Sold and Booked InventorySold Dec 24.pdf · uploaded 20 Dec 2025View
- Form 1Form-1 March 25.pdf · uploaded 20 Dec 2025View
- Form 2Form-2 March 25.pdf · uploaded 20 Dec 2025View
- Disclosure of Sold and Booked InventorySold March 25.pdf · uploaded 20 Dec 2025View
- Form 1Form-1 June 25.pdf · uploaded 20 Dec 2025View
- Form 2Form-2 June 25.pdf · uploaded 20 Dec 2025View
- Disclosure of Sold and Booked InventorySold June 25.pdf · uploaded 20 Dec 2025View
- Form 11 Form-1 Sep 25.pdf · uploaded 29 Dec 2025View
- Form 22 Form-2 Sep 25.pdf · uploaded 29 Dec 2025View
- Disclosure of Sold and Booked Inventory4 Sold Sep 25.pdf · uploaded 29 Dec 2025View
- Form 1Hrim Sky Dec 2025 Form 1.pdf · uploaded 11 Feb 2026View
- Form 2Hrim Sky Dec 2025 Form 2.pdf · uploaded 11 Feb 2026View
- Disclosure of Sold and Booked InventoryHrim Sky Dec 2025 sold unsold.pdf · uploaded 11 Feb 2026View
- Form 5 (FY 2023-2024)23-24 Form 5.pdf · uploaded 12 Feb 2026View
- Form 5 (FY 2024-2025)Form 5 24-25.pdf · uploaded 12 Feb 2026View
- Form 1Form-1 Mar 26.pdf · uploaded 26 May 2026View
- Form 2Form-2 Mar 26.pdf · uploaded 26 May 2026View
- Disclosure of Sold and Booked InventorySold Mar 26.pdf · uploaded 26 May 2026View
- Form 1Form 1 June-26.pdf · uploaded 13 Aug 2026View
- Form 2Form 2 June-26.pdf · uploaded 13 Aug 2026View
- Disclosure of Sold and Booked InventorySold-Unsold June-26.pdf · uploaded 13 Aug 2026View
Promoter documents
Technical documents
Proforma allotment letter
- Proforma allotment letterModal From Of Allotment Letter.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Aurangabad (M Corp.), Aurangabad taluka
Survey, CTS, gat or plot numbers
As published on MahaRERA's project page
GUT NO 65 PART 1 2 3 OPPOSITE MIT COLLEGE NEAR BEED BYPASS TQ AND DIST CHHATRAPATI SAMBHAJINAGAR
Boundaries
- North
- Remaining Land of Promoter
- South
- Gut no 66 Part
- East
- 7-5 mtr internal project road
- West
- open space of Group Housing permission
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Arch Pramod Narale | — |
| Chartered accountant | D M Samdani and Company | — |
| Chartered accountant | S A Samdani & Co. | — |
| Engineer | J V Structural Engineer | — |
Source: MahaRERA project page. Contact details are not shown.