Chandra Sai Apartment

Active

Aurangabad (M Corp.), Aurangabad 431005 |Promoter: Chandra Builder And Developers

Residential / Group HousingRERAP51500016559
23 May 2018Registered with MahaRERA
31 May 2024Promised completion
31 Mar 2027Revised completionPushed back 2 years and 10 months
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Active
Buildings
1
Land area for this project
713 sq m (7,674 sq ft)
Permissible built-up area
1,810 sq m (19,487 sq ft)
Sanctioned built-up area
980 sq m (10,550 sq ft)
Planning authority
Aurangabad Municipal Corporation Aurangabad
Address
Plot No 15, 16, 17 Gut No 12 Pankaj Hou Soc Kanchanwadi Aurangabad, Paithan Road, KanchanwadiPIN 431005
Designated bank account
Hdfc Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.83708, 75.29830
Chandra Sai Apartment is at latitude 19.83708, longitude 75.29830.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 2 years and 10 months

Registered
23 May 2018
Promised
31 May 2024
Revised
31 Mar 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150001655923 May 201831 May 202431 Mar 2027Chandra Builder And DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Chandra Sai Apartment7—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Chandra Sai Apartment

  • Excavation100%
  • Basement (if any)80%
  • Podiums (if any)0%
  • Plinth80%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsNot applicable
  • Water SupplyBOREWELL50%
  • Water SupplyBOREWELL50%
  • Water SupplyBOREWELL50%
  • Water SupplyBOREWELL50%
  • Water SupplyBOREWELL50%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEPTIC TANK0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEPTIC TANK0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEPTIC TANK0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEPTIC TANK0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEPTIC TANK0%
  • Storm Water DrainsNot applicable
  • Storm Water DrainsNot applicable
  • Storm Water DrainsNot applicable
  • Storm Water DrainsNot applicable
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Street LightingNot applicable
  • Street LightingNot applicable
  • Street LightingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Community BuildingsNot applicable
  • Community BuildingsNot applicable
  • Community BuildingsNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingUP TO THE BOREWELL0%
  • Water conservation /Rain water harvestingUP TO THE BOREWELL0%
  • Water conservation /Rain water harvestingUP TO THE BOREWELL0%
  • Water conservation /Rain water harvestingUP TO THE BOREWELL0%
  • Water conservation /Rain water harvestingUP TO THE BOREWELL0%
  • Energy managemcntNot applicable
  • Energy managemcntNot applicable
  • Energy managemcntNot applicable
  • Energy managemcntNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationMETER0%
  • Electrical meter room, sub-station, receiving stationMETER0%
  • Electrical meter room, sub-station, receiving stationMETER0%
  • Electrical meter room, sub-station, receiving stationMETER0%
  • Electrical meter room, sub-station, receiving stationMETER0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable
  • Open ParkingNot applicable
  • Open ParkingNot applicable
  • Open ParkingNot applicable
  • Open ParkingNot applicable
  • LIFT00%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

29 documents held by Deedo, 34 filings listed on MahaRERA's project page

Others

Registration certificate

Extension certificate

Document library

  • Declaration in FORM BFORM B05012018122430.pdf · uploaded 1 May 2018View
  • Details of encumbrancesSEARCH REPORT05012018121434.pdf · uploaded 1 May 2018View
  • Copy of the legal title reportSEARCH REPORT05012018121434.pdf · uploaded 1 May 2018View
  • Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERT.pdf · uploaded 1 May 2018View
  • Building Plan Approval (IOD)SANCTION BUILD PLAN.pdf · uploaded 1 May 2018View
  • Proforma of Allotment letterATS05012018121317.pdf · uploaded 1 May 2018View
  • Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 1 May 2018View
  • Building Plan Approval (IOD)CHANDRASAI.pdf · uploaded 18 May 2018View
  • Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 21 Jan 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Chandra Builders-RERA certificate FY 19-20.pdf · uploaded 24 May 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Chandra Builder-Rera Certificate fy 20-21.pdf · uploaded 24 May 2022View
  • Declaration about Commencement CertificateChandra Sai Apartment.pdf · uploaded 31 May 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Chandra Sai_compressed.pdf · uploaded 31 May 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Dec 2021 Form 2A_compressed.pdf · uploaded 31 May 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)March 2022 Form 2 A_compressed.pdf · uploaded 31 May 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Chandra Builder-RERA CERTIFICATE FY 21-22.pdf · uploaded 4 May 2023View
  • Disclosure of sold/ booked inventorySold Unsold June 2024_compressed.pdf · uploaded 22 Jul 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Chandra Form-1 Mar 24.pdf · uploaded 2 Aug 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Chandra Form-2A Mar 24.pdf · uploaded 2 Aug 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Chandra Form-1 Jun 24.pdf · uploaded 2 Aug 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Chandra Form-2 Mar 24.pdf · uploaded 2 Aug 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Chandra Form-2 Jun 24.pdf · uploaded 2 Aug 2024View
  • Commencement Certificates / NA Order for plotted development2019 permission.pdf · uploaded 16 Nov 2024View
  • Commencement Certificates / NA Order for plotted development2019 permission.pdf · uploaded 16 Nov 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Chandra Sai Builders Form-5.pdf · uploaded 14 Dec 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Chandra Builders Form-5 04-12-24.pdf · uploaded 16 Dec 2024View
  • Declaration in FORM BChandra Builders Form-B.pdf · uploaded 29 Jan 2025View

Promoter documents

  • Declaration Form BFORM B05012018122430.pdf · uploaded 1 May 2018View
  • Legal Title reportSEARCH REPORT05012018121434.pdf · uploaded 1 May 2018View
  • Declaration Form BChandra Builders Form-B.pdf · uploaded 29 Jan 2025View

Technical documents

  • Building Plan ApprovalSANCTION BUILD PLAN.pdfView
  • Layout ApprovalLAYOUT.pdfView
  • Building Plan ApprovalCHANDRASAI.pdfView

Proforma allotment letter

  • Proforma allotment letterATS05012018121317.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (M Corp.), Aurangabad taluka

Survey, CTS, gat or plot numbers

161617 GUT NO 12 PANKAJ HOU SOC KANCHANWADI AURANGABADPLOT NO 15PLOT NO 15

As published on MahaRERA's project page

PLOT NO 15, 16,17 GUT NO 12 PANKAJ HOU SOC KANCHANWADI AURANGABAD

Boundaries

North
12 M W Dp Road
South
15 M W Dp Road
East
12 M W Dp Road
West
7 M W Dp Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDhananjay Doifode—
ArchitectVarsha Lekhraj Ahuja—
Chartered accountantIndapurakar & Mundada—
Chartered accountantMkmm & Associates—
EngineerVarsha Lekhraj Ahuja—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology