Aurangabad (M Corp.), Aurangabad 431001 |Promoter: Aurangabad Industrial Trade Centre Private Limited

26 Apr 2019Registered with MahaRERA
30 Mar 2024Promised completion
1Building
46Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Lapsed
Buildings
1
Unit types
Shop 1, Shop 2, Shop 3, Shop 4, Shop 5, Shop 6, Shop 7, Shop 846 units in all
Land area for this project
1,128 sq m (12,142 sq ft)
Permissible built-up area
1,128 sq m (12,142 sq ft)
Sanctioned built-up area
1,128 sq m (12,142 sq ft)
Address
P-85, Jalna Road, Chikalthana MidcPIN 431001
Designated bank account
Idbi Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Aurangabad Industrial Trade Centreaitc - is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Mar 2024

The latest completion date on record passed 2 years and 7 months ago.

Registered
26 Apr 2019
Promised
30 Mar 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150002061926 Apr 201930 Mar 2024—Aurangabad Industrial Trade Centre Private LimitedProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Aurangabad Industrial Trade Centre Aitc246

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

46 units registered

Shop 1 · 18 unitsShop 2 · 2 unitsShop 3 · 4 unitsShop 4 · 2 unitsShop 5 · 2 unitsShop 6 · 2 unitsShop 7 · 2 unitsShop 8 · 14 units
TypeCarpet areaUnits
Shop 113.5 sq m · 145 sq ft18
Shop 212.8 sq m · 138 sq ft2
Shop 315.14 sq m · 163 sq ft4
Shop 415.42 sq m · 166 sq ft2
Shop 516.87 sq m · 182 sq ft2
Shop 616.6 sq m · 179 sq ft2
Shop 716.26 sq m · 175 sq ft2
Shop 813.33 sq m · 143 sq ft14

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space000014

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Aurangabad Industrial Trade Centre Aitc

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyMIDC CONNECTON0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)AS PER BUILDING PLAN0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingAS PER MIDC REQUIREMENT0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsAS PER MIDC NORMS0%
  • Electrical meter room, sub-station, receiving stationDP0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open Parking14 CARS PARKING0%
  • COMMON WASHROOMAS PER BUILDING PLAN0%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

23 documents held by Deedo, 29 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Commencement Certificates / NA Order for plotted developmentCommencement certificate.pdf · uploaded 3 Apr 2019View
  • Copy of the legal title reportSearch report.pdf · uploaded 3 Apr 2019View
  • Building Plan Approval (IOD)Building Plan.pdf · uploaded 3 Apr 2019View
  • Declaration in FORM BForm B_.pdf · uploaded 12 Apr 2019View
  • Details of encumbrancesEncumberance certificate_.pdf · uploaded 12 Apr 2019View
  • Proforma of Allotment letterDeclaration for not having agreement to sale_.pdf · uploaded 12 Apr 2019View
  • OtherDeclaration For Authorized Signatory.pdf · uploaded 12 Apr 2019View
  • Copy of Layout Approval (in case of layout)Approved layout.pdf · uploaded 19 Apr 2019View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)19-20.pdf · uploaded 11 Apr 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)20-21.pdf · uploaded 11 Apr 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)18-19.pdf · uploaded 11 Apr 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)19-20.pdf · uploaded 11 Apr 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)21-22.pdf · uploaded 11 Apr 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 22-23 Aurangabad Industrial (1).PDF · uploaded 12 Mar 2024View
  • Declaration in FORM BForm B.pdf · uploaded 18 Apr 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsInterest on other real estate organisations_Manish Bhandari.pdf · uploaded 18 Apr 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsInterest on other real estate organisations_Sameer Kanadkhedkar.pdf · uploaded 18 Apr 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsInterest on other real estate organisations_Satish Lonikar.pdf · uploaded 18 Apr 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsInterest on other real estate organisations_Swati Jaiswal.pdf · uploaded 18 Apr 2024View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about seperate bank account.pdf · uploaded 18 Apr 2024View
  • Disclosure of sold/ booked inventoryDisclosure of Sold Inventory.pdf · uploaded 18 Apr 2024View
  • CERSAI detailsCERSAI_Search_Report_200304114177_For_Asset_Based_Search_18_04_2024_08_42_45_458.pdf · uploaded 18 Apr 2024View

Promoter documents

  • Legal Title reportSearch report.pdf · uploaded 3 Apr 2019View
  • Declaration Form BForm B_.pdf · uploaded 12 Apr 2019View
  • Declaration Form BForm B.pdf · uploaded 18 Apr 2024View

Technical documents

  • Building Plan ApprovalBuilding Plan.pdfView
  • Layout ApprovalApproved layout.pdfView

Other legal documents

  • OtherDeclaration For Authorized Signatory.pdfView

Proforma allotment letter

  • Proforma allotment letterDeclaration for not having agreement to sale_.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (M Corp.), Aurangabad taluka

Survey, CTS, gat or plot numbers

P85

As published on MahaRERA's project page

P-85

Boundaries

North
Green Belt 10 Mtr Wide
South
Midc Road 20 Mtr Wide
East
Midc Road 20 Mtr Wide
West
Midc Road 6 Mtr Wide

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectYogesh Zawar—

Source: MahaRERA project page. Contact details are not shown.