Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
4
Land area for this project
3,375 sq m (36,333 sq ft)
Permissible built-up area
8,888 sq m (95,673 sq ft)
Sanctioned built-up area
8,388 sq m (90,291 sq ft)
Recreational open space
379 sq m (4,075 sq ft)
Planning authority
Aurangabad Mahanagarpalika
Address
Gut No 83 P Deolai, Beed Bypass, DeolaiPIN 431007
Designated bank account
State Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.83965, 75.35455
Anandam Residency is at latitude 19.83965, longitude 75.35455.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2027

Registered
2 Mar 2022
Promised
31 Dec 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P515000336712 Mar 202231 Dec 2027—A B DevelopersProject page

4 buildings

Buildings and wings named in the registration

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Apartment BuildingClosed/Covered00001
Apartment BuildingOpen Space00000
Rowhouse Block IClosed/Covered00000
Rowhouse Block IOpen Space00000
Rowhouse Block IIClosed/Covered00000
Rowhouse Block IIOpen Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Apartment Building

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rowhouse Block I

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rowhouse Block II

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsCompleted100%
  • Water SupplyCompleted100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Completed100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingCompleted100%
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingCompleted100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirements0%
  • Electrical meter room, sub-station, receiving stationCompleted100%
  • Aggregate area of recreational Open Space0%
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

90 documents held by Deedo, 106 filings listed on MahaRERA's project page

Title report

Encumbrance details

Commencement certificate (2)

Form B

Other (43)

Show all 196 documentsShow fewer documents

Other (43)

Allotment letter (2)

Registration certificate

Form 1 (10)

Form 2 (10)

Form 2A (9)

Form 5 (4)

Layout plan

Building plan (5)

Document library

  • Copy of the legal title reportSearch Report Deolai Gut N.pdf · uploaded 19 Feb 2022View
  • Details of encumbrancesNon Encumberance Declaration_0001.pdf · uploaded 19 Feb 2022View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate Gut No83 (p) Deolai.pdf · uploaded 19 Feb 2022View
  • Copy of Layout Approval (in case of layout)HPSCANNER3000.pdf · uploaded 19 Feb 2022View
  • Building Plan Approval / NA Order for plotted developmentHPSCANNER3000.pdf · uploaded 19 Feb 2022View
  • Building Plan Approval / NA Order for plotted developmentHPSCANNER3001.pdf · uploaded 19 Feb 2022View
  • Building Plan Approval / NA Order for plotted developmentHPSCANNER3002.pdf · uploaded 19 Feb 2022View
  • Building Plan Approval / NA Order for plotted developmentHPSCANNER3003.pdf · uploaded 19 Feb 2022View
  • Building Plan Approval / NA Order for plotted developmentHPSCANNER3004.pdf · uploaded 19 Feb 2022View
  • Building Plan Approval / NA Order for plotted developmentHPSCANNER3005.pdf · uploaded 19 Feb 2022View
  • Declaration about Commencement CertificateDeclaration About Commencemnt Certificate_0001.pdf · uploaded 19 Feb 2022View
  • Declaration in FORM BForm ''B''_0001.pdf · uploaded 19 Feb 2022View
  • CERSAI detailsUndertaking_0001.pdf · uploaded 19 Feb 2022View
  • CERSAI detailsAsset Based Search.pdf · uploaded 19 Feb 2022View
  • Proforma of Allotment letterAllotment Letter.pdf · uploaded 19 Feb 2022View
  • Proforma of Allotment letterAFS.pdf · uploaded 19 Feb 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certi 31-3-22.pdf · uploaded 20 Oct 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certi 30-06-2022.pdf · uploaded 20 Oct 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certi 30-09-2022.pdf · uploaded 20 Oct 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certi 31-03-22.pdf · uploaded 20 Oct 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certi 30-06-2022.pdf · uploaded 20 Oct 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certi 30-09-2022.pdf · uploaded 20 Oct 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Supervisors Certi 31-03-2022.pdf · uploaded 20 Oct 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Supervisor Certi 30-06-2022.pdf · uploaded 20 Oct 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Supervisors Certi 30-09-22.pdf · uploaded 20 Oct 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Annual Report 31-3-2022.pdf · uploaded 8 Feb 2023View
  • Disclosure of sold/ booked inventoryDisclosure Of Sold Booked Mar-22.pdf · uploaded 27 Feb 2023View
  • Disclosure of sold/ booked inventoryDisclosure Of Sold Booked June-22.pdf · uploaded 27 Feb 2023View
  • Disclosure of sold/ booked inventoryDisclosure Of Sold Booked Sept-22.pdf · uploaded 27 Feb 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)site engineer certi dec-22.pdf · uploaded 27 Feb 2023View
  • Disclosure of sold/ booked inventoryDisclosure Of sold booked Dec-22.pdf · uploaded 27 Feb 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certifi Dec-22.pdf · uploaded 27 Feb 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers certi dec-22.pdf · uploaded 27 Feb 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate Form 1.pdf · uploaded 2 Jun 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)1 Eng certificate.pdf · uploaded 2 Jun 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Site Supervisor's Certificate From 2A.pdf · uploaded 2 Jun 2023View
  • Disclosure of sold/ booked inventoryDisclosure Of Sold Booked Mar 23.PDf · uploaded 2 Jun 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Eng certificate.pdf · uploaded 4 Aug 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Site Supervisor's Certificate From 2A.pdf · uploaded 4 Aug 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects certificate pdf.pdf · uploaded 19 Aug 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)engineers certificate june 23.pdf · uploaded 19 Aug 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Site Supervisor june 2023.pdf · uploaded 19 Aug 2023View
  • Disclosure of sold/ booked inventoryDiscloser of sold booked inv.pdf · uploaded 19 Aug 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificte.pdf · uploaded 20 Oct 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 20 Oct 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Supervisor Certificate.pdf · uploaded 20 Oct 2023View
  • Disclosure of sold/ booked inventoryDisclosure of Sold Booked.pdf · uploaded 20 Oct 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form-5 AB Developers_0001.pdf · uploaded 1 Dec 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 18 Jan 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 18 Jan 2024View
  • Disclosure of sold/ booked inventoryDisclosure of sold unsold.pdf · uploaded 18 Jan 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Disclosure of sold unsold.pdf · uploaded 18 Jan 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Supervisor Certificate.pdf · uploaded 18 Jan 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 19 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)EnggCertificate.pdf · uploaded 19 Apr 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Supervisor Certificate.pdf · uploaded 19 Apr 2024View
  • Disclosure of sold/ booked inventorydisclosure sold booked.pdf · uploaded 22 Apr 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 20 Jul 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer certificate.pdf · uploaded 20 Jul 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Supervisor Certificate.pdf · uploaded 20 Jul 2024View
  • Disclosure of sold/ booked inventoryDisclosure Certificate.pdf · uploaded 20 Jul 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate.pdf · uploaded 19 Oct 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 19 Oct 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Supervisor Certificate.pdf · uploaded 19 Oct 2024View
  • Disclosure of sold/ booked inventoryDisclosure of Sold Booked.pdf · uploaded 19 Oct 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 18 Jan 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 18 Jan 2025View
  • Disclosure of sold/ booked inventorydisclosure of sold booked inventory.pdf · uploaded 18 Jan 2025View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)supervisor certificate.pdf · uploaded 18 Jan 2025View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form-5 A B Developers Dt-20-01-2025_0001.pdf · uploaded 20 Jan 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 17 Apr 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 17 Apr 2025View
  • Disclosure of sold/ booked inventoryDisclosure of Sold Unsold.pdf · uploaded 17 Apr 2025View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Annexure c Mar 25 Revised.pdf · uploaded 18 Apr 2025View
  • Form 1Architect Certificate.pdf · uploaded 13 Sep 2025View
  • Form 2Engineer Certificate.pdf · uploaded 13 Sep 2025View
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Unsold.pdf · uploaded 13 Sep 2025View
  • OthersSupervisor Certificate.pdf · uploaded 13 Sep 2025View
  • Form 1Architect Certificate.pdf · uploaded 22 Sep 2025View
  • Form 2Engineer Certificate.pdf · uploaded 22 Sep 2025View
  • Disclosure of Sold and Booked InventoryDisclosesure of soled unsoled.pdf · uploaded 22 Sep 2025View
  • OthersSupervisor Certificate form 2A.pdf · uploaded 22 Sep 2025View
  • Form 5 (FY 2024-2025)Form-5 AB Devlopers_0001.pdf · uploaded 30 Sep 2025View
  • Form 1Architect Certificate.pdf · uploaded 12 Nov 2025View
  • Form 2Engineer Certificate New.pdf · uploaded 12 Nov 2025View
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory.pdf · uploaded 12 Nov 2025View
  • OthersSupervisors Certificate.pdf · uploaded 12 Nov 2025View
  • Occupational CertificateCOMPLETION CERTIFICATE (2).pdf · uploaded 26 Dec 2025View
  • Occupational CertificateMAIL TO MAHARERA.pdf · uploaded 26 Dec 2025View
  • Withdrawal Update Form 1Form 1.pdf · uploaded 25 Jun 2026View
  • Withdrawal Update Form 2Engineer certificate.pdf · uploaded 25 Jun 2026View
  • Withdrawal Update Form 1Form 1.pdf · uploaded 25 Jun 2026View
  • Withdrawal Update Form 2form 2 (4).pdf · uploaded 25 Jun 2026View
  • Withdrawal Update Form 1Form 1.pdf · uploaded 25 Jun 2026View
  • Withdrawal Update Form 2form 2 (4).pdf · uploaded 25 Jun 2026View
  • Occupational CertificateDeclaration (2).pdf · uploaded 11 Aug 2026View

Promoter documents

  • Legal Title reportSearch Report Deolai Gut N.pdf · uploaded 19 Feb 2022View
  • Declaration Form BForm ''B''_0001.pdf · uploaded 19 Feb 2022View

Technical documents

  • Layout ApprovalHPSCANNER3000.pdfView
  • Building Plan ApprovalHPSCANNER3000.pdfView
  • Building Plan ApprovalHPSCANNER3001.pdfView
  • Building Plan ApprovalHPSCANNER3002.pdfView
  • Building Plan ApprovalHPSCANNER3003.pdfView
  • Building Plan ApprovalHPSCANNER3004.pdfView
  • Building Plan ApprovalHPSCANNER3005.pdfView

Proforma allotment letter

  • Proforma allotment letterAllotment Letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (M Corp.), Aurangabad taluka

Survey, CTS, gat or plot numbers

Gut No 83 P Deolai

As published on MahaRERA's project page

Gut No 83 P Deolai

Boundaries

North
9 Mtr Wide Road
South
Remaining land of Gut No 83
East
Remaining Land of Gut No 83
West
Remaining Land of Gut No 83

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPramod Narale—
Chartered accountantLathi and Tapdiya—
Chartered accountantNarendra Navandar & Company—
EngineerN G Kharkhane—