Adinath Sankul
CompletedAurangabad (M Corp.), Aurangabad 431005 |Promoter: Adinath Developers
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Completed
- Buildings
- 1
- Land area for this project
- 864 sq m (9,300 sq ft)
- Permissible built-up area
- 2,652 sq m (28,544 sq ft)
- Sanctioned built-up area
- 1,696 sq m (18,251 sq ft)
- Address
- Gut No 51 Plot No 19, 20 And 21, Shivaji Nagar Road, Garkheda ParisarPIN 431005
- Designated bank account
- State Bank Of India
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Location
Coordinates as published by MahaRERA
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Mar 2023
The latest completion date on record passed 3 years and 7 months ago.
- Registered
- 5 Aug 2021
- Promised
- 31 Mar 2023
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51500030198 | 5 Aug 2021 | 31 Mar 2023 | — | Adinath Developers | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Adinath Sankul | 6 | — |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
0 units registered
Parking
| Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 | 18 |
| Open Space | 0 | 0 | 0 | 0 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress
Work completed, as the promoter reported it to MahaRERA (Form 1)
Adinath Sankul
Common areas and amenities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Documents
18 documents held by Deedo, 26 filings listed on MahaRERA's project page
Others
- Other28 Jun 2021ViewSource
- Other28 Jun 2021ViewSource
- Other28 Jun 2021ViewSource
- Other28 Jun 2021ViewSource
- Other28 Jun 2021ViewSource
- Other30 Jul 2021ViewSource
- Other30 Jul 2021ViewSource
- Other30 Jul 2021ViewSource
- Other30 Jul 2021ViewSource
- Other8 Aug 2023ViewSource
- Other6 Sep 2023ViewSource
- Other6 Sep 2023ViewSource
- Other6 Sep 2023ViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
Document library
- Details of encumbrancesEncumbrance Certificate.PDF · uploaded 28 Jun 2021View
- Building Plan Approval / NA Order for plotted developmentBuilding Plan.pdf · uploaded 28 Jun 2021View
- Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 28 Jun 2021View
- Declaration about Commencement CertificateDeclaration Format D.PDF · uploaded 28 Jun 2021View
- Declaration in FORM BAffidavit (Form B).PDF · uploaded 28 Jun 2021View
- Proforma of Allotment letterATS RERA.pdf · uploaded 28 Jun 2021View
- Proforma of Allotment letterAllotment Letter.pdf · uploaded 28 Jun 2021View
- Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 28 Jun 2021View
- OtherPartnership Deed and RC.pdf · uploaded 20 Jul 2021View
- Copy of the legal title reportFormat A.pdf · uploaded 30 Jul 2021View
- Copy of the legal title report1.pdf · uploaded 30 Jul 2021View
- Copy of the legal title report2.pdf · uploaded 30 Jul 2021View
- Copy of the legal title report3.pdf · uploaded 30 Jul 2021View
- Architect’s Certificate on Completion of Project (Form 4)Architect Certificate Form 4 and OC.pdf · uploaded 8 Aug 2023View
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOCCUPANCY.pdf · uploaded 6 Sep 2023View
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentBUILDING PLAN 1_compressed.pdf · uploaded 6 Sep 2023View
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentBUILDING PLAN 2_compressed.pdf · uploaded 6 Sep 2023View
Promoter documents
Other legal documents
- OtherPartnership Deed and RC.pdfView
Proforma allotment letter
- Proforma allotment letterATS RERA.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Aurangabad (M Corp.), Aurangabad taluka
Survey, CTS, gat or plot numbers
As published on MahaRERA's project page
GUT NO 51 PLOT NO 19, 20 AND 21
Boundaries
- North
- Plot No 18
- South
- 15 Meter Wide Road
- East
- 9 Meter Wide Road
- West
- Amc Reserved Area For School Ground
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Shruti Deshpande | — |
| Chartered accountant | Kapvalt & Co | — |
| Engineer | Shivraj Tupe | — |
| Other | Abhijit Jeewanwal | — |
Source: MahaRERA project page. Contact details are not shown.