Skip to content
Deedo home
Menu

Tejal Srushti G Building

Lapsed

Aurangabad (Cb), Aurangabad 431008 |Promoter: Bhausaheb V Kale Huf

Residential / Group HousingRERAP51500009069
19 Aug 2017Registered with MahaRERA
19 Jul 2022Promised completion
1Building
28Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Lapsed
Buildings
1
Unit types
G flated building28 units in all
Land area for this project
1,407 sq m (15,149 sq ft)
Permissible built-up area
1,168 sq m (12,569 sq ft)
Sanctioned built-up area
1,168 sq m (12,569 sq ft)
Recreational open space
724 sq m (7,792 sq ft)
Address
Gut No 03PIN 431008
Designated bank account
Yes Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 21.10288, 79.02778
Tejal Srushti G Building is at latitude 21.10288, longitude 79.02778.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 19 Jul 2022

The latest completion date on record passed 4 years and 3 months ago.

Registered
19 Aug 2017
Promised
19 Jul 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150000906919 Aug 201719 Jul 2022—Bhausaheb V Kale HufProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Tejal Srushti G828

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

28 units registered

G flated building · 28 units
TypeCarpet areaUnits
G flated building1,065.8 sq m · 11,472 sq ft28

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00004
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Tejal Srushti G

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water Supply0100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)0100%
  • Storm Water Drains0100%
  • Landscaping & Tree Planting0100%
  • Street Lighting0100%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvesting0100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open Space0100%
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

15 documents held by Deedo, 18 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Copy of the legal title reportSearch report.pdf · uploaded 29 Jul 2017View
  • Details of encumbrancesEMBURSEMENT.pdf · uploaded 29 Jul 2017View
  • Copy of Layout Approval (in case of layout)LAYOUT PLAN.pdf · uploaded 29 Jul 2017View
  • Proforma of Allotment letterDraft Agreement for sale.pdf · uploaded 29 Jul 2017View
  • Building Plan Approval (IOD)BUILDING PLN.pdf · uploaded 29 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentCIDCO PERMISSION.pdf · uploaded 29 Jul 2017View
  • Declaration in FORM BFORM B.pdf · uploaded 29 Jul 2017View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)FORM NO 05 2122.pdf · uploaded 14 Mar 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM NO 05 1819.pdf · uploaded 14 Mar 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM NO 05 1920.pdf · uploaded 14 Mar 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM NO 05 2021.pdf · uploaded 14 Mar 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM NO 05 2122.pdf · uploaded 14 Mar 2024View
  • Disclosure of sold/ booked inventoryDocScanner 14-Mar-2024 1-37 pm.pdf · uploaded 14 Mar 2024View

Promoter documents

  • Legal Title reportSearch report.pdf · uploaded 29 Jul 2017View
  • Declaration Form BFORM B.pdf · uploaded 29 Jul 2017View

Technical documents

  • Layout ApprovalLAYOUT PLAN.pdfView
  • Building Plan ApprovalBUILDING PLN.pdfView

Proforma allotment letter

  • Proforma allotment letterDraft Agreement for sale.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (CB), Aurangabad taluka

Survey, CTS, gat or plot numbers

GUT NO 03

As published on MahaRERA's project page

GUT NO 03

Boundaries

North
Building No H
South
12 Metre Wide Road
East
15 Metre Wild Road
West
Open Space

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPradeep V Mote—
EngineerPradeep V Mote—
OtherG H Constro World—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology