Omkara Heights

Completed

Aurangabad (Cb), Aurangabad 431001 |Promoter: MCM Developers

1 Sep 2017Registered with MahaRERA
31 Dec 2017Promised completion
1Building
49Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Completed
Buildings
1
Unit types
2BHK, 3BHK, Shop, Showroom49 units in all
Land area for this project
1,540 sq m (16,576 sq ft)
Permissible built-up area
3,041 sq m (32,734 sq ft)
Sanctioned built-up area
3,041 sq m (32,734 sq ft)
Address
4874PIN 431001
Designated bank account
The Jalgaon Peopels Cooperative Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.87459, 75.30866
Omkara Heights is at latitude 19.87459, longitude 75.30866.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2017

The latest completion date on record passed 8 years and 10 months ago.

Registered
1 Sep 2017
Promised
31 Dec 2017

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P515000120381 Sep 201731 Dec 2017—MCM DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Omkara Heights949

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

49 units registered

2BHK · 20 units3BHK · 10 unitsShop · 15 unitsShowroom · 4 units
TypeCarpet areaUnits
2BHK59.41 sq m · 639 sq ft5
2BHK62.24 sq m · 670 sq ft1
2BHK62.25 sq m · 670 sq ft4
2BHK63.01 sq m · 678 sq ft1
2BHK63.82 sq m · 687 sq ft1
2BHK65.04 sq m · 700 sq ft1
2BHK65.12 sq m · 701 sq ft4
2BHK65.89 sq m · 709 sq ft1
2BHK79.36 sq m · 854 sq ft1
2BHK79.59 sq m · 857 sq ft1
3BHK90.25 sq m · 971 sq ft4
3BHK90.47 sq m · 974 sq ft1
3BHK90.52 sq m · 974 sq ft4
3BHK90.61 sq m · 975 sq ft1
Shop25.71 sq m · 277 sq ft1
Shop27.81 sq m · 299 sq ft1
Shop28.1 sq m · 302 sq ft1
Shop28.72 sq m · 309 sq ft2
Shop29.1 sq m · 313 sq ft5
Shop29.86 sq m · 321 sq ft1
Shop31.35 sq m · 337 sq ft1
Shop32.41 sq m · 349 sq ft1
Shop34.02 sq m · 366 sq ft1
Shop36.18 sq m · 389 sq ft1
Showroom52 sq m · 560 sq ft4

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000030
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Omkara Heights

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyWater Supply lines from OHWT is completed100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Completed100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingCompleted100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot yet started95%
  • Electrical meter room, sub-station, receiving stationcompleted100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

15 documents held by Deedo, 17 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Copy of the legal title reporttitle mcm developers_opt.pdf · uploaded 29 Jul 2017View
  • Details of encumbrancesmcm no encrumbabces.pdf · uploaded 29 Jul 2017View
  • Proforma of Allotment letterMcm Developers Allotment_opt.pdf · uploaded 29 Jul 2017View
  • Declaration in FORM BNotarised Form V.pdf · uploaded 29 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)architect mcm_opt.pdf · uploaded 29 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer_opt.pdf · uploaded 29 Jul 2017View
  • Proforma of Allotment letterAgreement.pdf · uploaded 29 Jul 2017View
  • Copy of Layout Approval (in case of layout)MCD.pdf · uploaded 29 Jul 2017View
  • Building Plan Approval (IOD)MCD.pdf · uploaded 29 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 29 Jul 2017View
  • Certificates of Architect (Form 4)Project of Omkara Hieghts dated.pdf · uploaded 12 Feb 2018View
  • Certificates of CA (Form 5)MCM Developers Annual Report 2017-18.pdf · uploaded 29 Sep 2018View

Promoter documents

  • Legal Title reporttitle mcm developers_opt.pdf · uploaded 29 Jul 2017View
  • Declaration Form BNotarised Form V.pdf · uploaded 29 Jul 2017View

Technical documents

  • Layout ApprovalMCD.pdfView
  • Building Plan ApprovalMCD.pdfView

Proforma allotment letter

  • Proforma allotment letterMcm Developers Allotment_opt.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (CB), Aurangabad taluka

Survey, CTS, gat or plot numbers

4874

As published on MahaRERA's project page

4874

Boundaries

North
CTS 4874 4 and 5
South
9 m wide road
East
Cts 4889
West
Service Lane

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectManish Kale—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology