21Buildings
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Active
Buildings
21
Land area for this project
18,300 sq m (1,96,979 sq ft)
Permissible built-up area
12,409 sq m (1,33,569 sq ft)
Sanctioned built-up area
7,757 sq m (83,496 sq ft)
Recreational open space
1,830 sq m (19,698 sq ft)
Address
240PIN 431007
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.79470, 75.49564
Shivar is at latitude 19.79470, longitude 75.49564.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2026

Registered
11 Aug 2017
Promised
30 Dec 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150000573311 Aug 201730 Dec 2026—Econ DevelopersProject page

21 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A4—
B4—
C4—
E1-E22—
E3-E42—
E5-E62—
E7-E82—
G1—
H4—
I2—
J2—
K13,k14,k27-K301—
K15-K261—
K1-K121—
K31-K401—
K41-K44,k61-K621—
K45-K601—
K63-K661—
K67-K701—
K71-K741—
K75-K84,f,d1—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
AClosed/Covered00000
AOpen Space00008
BClosed/Covered00000
BOpen Space00008
CClosed/Covered00000
COpen Space00000
E1-E2Closed/Covered00000
E1-E2Open Space00002
E3-E4Closed/Covered00000
E3-E4Open Space00002
E5-E6Closed/Covered00000
E5-E6Open Space00002
E7-E8Closed/Covered00000
E7-E8Open Space00002
GClosed/Covered00000
GOpen Space00000
HClosed/Covered00000
HOpen Space00008
IClosed/Covered00000
IOpen Space00004
JClosed/Covered00000
JOpen Space00002
K13,k14,k27-K30Closed/Covered00000
K13,k14,k27-K30Open Space00006
K15-K26Closed/Covered00000
K15-K26Open Space000012
K1-K12Closed/Covered00000
K1-K12Open Space000012
K31-K40Closed/Covered00000
K31-K40Open Space000010
K41-K44,k61-K62Closed/Covered00000
K41-K44,k61-K62Open Space00006
K45-K60Closed/Covered00000
K45-K60Open Space000016
K63-K66Closed/Covered00000
K63-K66Open Space00004
K67-K70Closed/Covered00000
K67-K70Open Space00004
K71-K74Closed/Covered00000
K71-K74Open Space00004
K75-K84,f,dClosed/Covered00000
K75-K84,f,dOpen Space000012

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

A

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

B

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

C

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

E1-E2

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

E3-E4

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

E5-E6

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

E7-E8

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

G

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

H

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

I

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

J

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

K13,k14,k27-K30

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

K15-K26

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

K1-K12

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

K31-K40

  • Excavation100%
  • Basement (if any)60%
  • Podiums (if any)0%
  • Plinth60%
  • Stilt Floor0%
  • Slabs of Super Structure60%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
  • Sanitary Fittings within the flats / premises60%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

K41-K44,k61-K62

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

K45-K60

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure50%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
  • Sanitary Fittings within the flats / premises50%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

K63-K66

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

K67-K70

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

K71-K74

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

K75-K84,f,d

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsALL CEMEMT CONCRETE ROAD DONE100%
  • Water Supply100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)100%
  • Storm Water DrainsSEPTIC TANK PROVIDEDNot applicable
  • Landscaping & Tree Planting70%
  • Street LightingFEW TREES AND ROUGH PATHWAY70%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvesting0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirements0%
  • Electrical meter room, sub-station, receiving stationDP(1) FUNCTIONAL WITH ALL INDIVIDUAL METER100%
  • Aggregate area of recreational Open SpaceLAWN AREA CLEARED70%
  • Open ParkingPLANTED TREES AND PHERIPHERINot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

36 documents held by Deedo, 41 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Copy of the legal title reportECON_TITLE_SEARCH.pdf · uploaded 31 Jul 2017View
  • Details of encumbrancesNo Encumberance.pdf · uploaded 31 Jul 2017Source
  • Copy of Layout Approval (in case of layout)sanction_plan_91_R.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)sanction_plan_92_R.pdf · uploaded 31 Jul 2017View
  • Declaration in FORM Bform b_2.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Shivar - 91 R Engineer Calculation.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Shivar - 92 R Engineer Calculation.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)building_sanction_91_r_pdf.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)building_sanction_92_r_pdf.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)architects_certificate_-_91_R.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)architects certificate- 92 R.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterARTICLES OF AGREEMENT-SHIVAR Final copy.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterAllotment letter - Shivar.pdf · uploaded 31 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentNA 9100 PDF.pdf · uploaded 7 Apr 2018View
  • Commencement Certificates / NA Order for plotted developmentna 9200 R.pdf · uploaded 7 Apr 2018View
  • Disclosure of sold/ booked inventorysold inventories.pdf · uploaded 16 Oct 2021View
  • OtherNew Partnership details_compressed.pdf · uploaded 16 Oct 2021View
  • Disclosure of sold/ booked inventorySALE OF FLAT.pdf · uploaded 22 Sep 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)REAR FORM 5 2017 2018.pdf · uploaded 14 Jan 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)RERA FORM 5 2018 2019.pdf · uploaded 14 Jan 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)RERA FORM 2019 2020_compressed.pdf · uploaded 14 Jan 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)RERA FORM 2019 2020.pdf · uploaded 14 Jan 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)RERA FORM 5 2020 2021.pdf · uploaded 14 Jan 2023View
  • Proforma of Agreement for saleARTICLES OF AGREEMENT-SHIVAR Final copy.pdf · uploaded 14 Jan 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)RERA FORM 5 2021 2022.pdf · uploaded 14 Jan 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Adobe Scan 03 Jan 2024.pdf · uploaded 9 Jan 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Econ Ca Certificate 23-24.pdf · uploaded 7 Nov 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT COMPLETION.pdf · uploaded 14 Feb 2025View
  • Other – FinanceNon withdrawal.pdf · uploaded 14 Feb 2025View
  • Disclosure of sold/ booked inventorySHIVAR 2024 BOOK.pdf · uploaded 14 Feb 2025View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Shivar - 91 R Engineer Calculation new 2025.pdf · uploaded 14 Feb 2025View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Shivar - 92 R Engineer Calculation new 2025.pdf · uploaded 14 Feb 2025View

Promoter documents

  • Legal Title reportECON_TITLE_SEARCH.pdf · uploaded 31 Jul 2017View
  • Declaration Form Bform b_2.pdf · uploaded 31 Jul 2017View

Technical documents

  • Layout Approvalsanction_plan_91_R.pdfView
  • Layout Approvalsanction_plan_92_R.pdfView
  • Building Plan Approvalbuilding_sanction_91_r_pdf.pdfView
  • Building Plan Approvalbuilding_sanction_92_r_pdf.pdfView

Other legal documents

  • OtherNew Partnership details_compressed.pdfView

Financial documents

  • Other – FinanceNon withdrawal.pdf · uploaded 14 Feb 2025View

Proforma allotment letter

  • Proforma allotment letterARTICLES OF AGREEMENT-SHIVAR Final copy.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Apatgaon, Aurangabad taluka

Survey, CTS, gat or plot numbers

240

As published on MahaRERA's project page

240

Boundaries

North
240
South
280 And 281
East
240
West
276

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPrashant Pardeshi—
Chartered accountantS M Unecha And Co—
EngineerRavindra Bansode—
OtherShivam Construction—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology