Skip to content
Deedo home
Menu

Unicorn Nest II

Certificate Signed

Gunjalwadi, Ahmednagar 422605 |Promoter: Unicorn Developers

Residential / Group HousingRERAP52200025454
3 Jun 2020Registered with MahaRERA
30 Jun 2026Promised completion
30 Oct 2026Revised completionPushed back 4 months
3Buildings
70Units registered33 booked (47%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
3
Unit types
1BHK, 2BHK, 3BHK, Shop70 units in all
Address
S No 115 1/1, 1/3, 1/4, Pune Nashik Highway, SangamnerPIN 422605
Designated bank account
76
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.59277, 74.19150
Unicorn Nest II is at latitude 19.59277, longitude 74.19150.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
3 Jun 2020
Promised
30 Jun 2026
Revised
30 Oct 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P522000254543 Jun 202030 Jun 202630 Oct 2026Unicorn DevelopersProject page

3 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Building C824
Building D928
E Building918

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

33 of 70 units booked (47%), as the promoter reported to MahaRERA

1BHK · 26 units2BHK · 26 units3BHK · 14 unitsShop · 4 units
BuildingTypeCarpet areaUnitsBooked
Building C1BHK460.8 sq m · 4,960 sq ft1212
Building C2BHK577.08 sq m · 6,212 sq ft1212
Building D1BHK524.58 sq m · 5,647 sq ft143
Building D2BHK660.24 sq m · 7,107 sq ft146
E Building3BHK79.22 sq m · 853 sq ft140
E BuildingShop16.95 sq m · 182 sq ft20
E BuildingShop18.7 sq m · 201 sq ft10
E BuildingShop21.15 sq m · 228 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 149 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN.pdf · uploaded 22 Jul 2017Source

Legal

  • Legal Title reportSearch Report-ilovepdf-compressed (1).pdf · uploaded 22 Jul 2017Source
  • Declaration Form BCombine_Form_B.pdf · uploaded 31 Jul 2017Source
  • Other – LegalResolution to correction.PDF · uploaded 11 Jul 2022Source
  • Other – LegalRessolution block D.PDF · uploaded 11 Jul 2022Source
  • Other – LegalSociety Application.pdf · uploaded 20 Jul 2022Source
  • Other – LegalApplication for correction under project_18082022.pdf · uploaded 18 Aug 2022Source
Show all 150 documentsShow fewer documents

Legal

  • Other – LegalConssent to correction by Costomer_compressed.pdf · uploaded 18 Aug 2022Source

Migrated

  • 1 PAN CardPAN.pdf · uploaded 22 Jul 2017Source
  • 1 Copy of the legal title reportSearch Report-ilovepdf-compressed (1).pdf · uploaded 22 Jul 2017Source
  • 1 Building Plan Approval (IOD)Manjur_Nakasha_2.pdf · uploaded 22 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentBandhakaam Parvangi Aadesh 1.pdf · uploaded 22 Jul 2017Source
  • 1 Details of encumbrancesVikasan_Kararnama_2_ (1).pdf · uploaded 31 Jul 2017Source
  • 1 Declaration in FORM BCombine_Form_B.pdf · uploaded 31 Jul 2017Source
  • 1 Proforma of Allotment letterCombine agreement to sale and allotment letter 1.pdf · uploaded 31 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)a2_Indrayani Mam_new_compressed.pdf · uploaded 6 May 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_Amended.pdf · uploaded 6 May 2020Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects Certificate.PDF · uploaded 6 May 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.PDF · uploaded 22 May 2020Source
  • 1 Declaration about Commencement Certificate3Declaration About Commencement certificate.pdf · uploaded 2 May 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)4Quality Assurance certificate.PDF · uploaded 2 May 2022Source
  • 1 Disclosure of sold/ booked inventory5Disclosure of sold.pdf · uploaded 2 May 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Unicorn Annual 5.PDF · uploaded 7 Jul 2022Source
  • 1 Other – LegalResolution to correction.PDF · uploaded 11 Jul 2022Source
  • 2 Other – LegalRessolution block D.PDF · uploaded 11 Jul 2022Source
  • 3 Other – LegalSociety Application.pdf · uploaded 20 Jul 2022Source
  • 4 Other – LegalApplication for correction under project_18082022.pdf · uploaded 18 Aug 2022Source
  • 5 Other – LegalConssent to correction by Costomer_compressed.pdf · uploaded 18 Aug 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.PDF · uploaded 25 Aug 2022Source
  • 2 Disclosure of sold/ booked inventorySold Inventory C and D.pdf · uploaded 16 Jan 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.PDF · uploaded 16 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Unicorn_Rera form 5.pdf · uploaded 11 May 2023Source
  • Form 5 (FY 2021-2022)Annual 5_2122_submitted on Portal.pdf · uploaded 1 Aug 2025Source
  • Form 5 (FY 2022-2023)Annual form 5 2324.PDF · uploaded 1 Aug 2025Source
  • Form 1Form 1.pdf · uploaded 6 Sep 2025Source
  • Form 2Form 2.PDF · uploaded 6 Sep 2025Source
  • Disclosure of Sold and Booked InventoryInventory.pdf · uploaded 6 Sep 2025Source
  • Form 3Form 3.PDF · uploaded 6 Sep 2025Source
  • Form 1Form 1.pdf · uploaded 6 Sep 2025Source
  • Form 2Form 2.PDF · uploaded 6 Sep 2025Source
  • Form 3Form 3.PDF · uploaded 6 Sep 2025Source
  • Disclosure of Sold and Booked InventoryInventory.pdf · uploaded 6 Sep 2025Source
  • Form 5 (FY 2023-2024)Annual form 5 2324.PDF · uploaded 6 Sep 2025Source
  • Form 1Form 1.pdf · uploaded 26 Sep 2025Source
  • Form 2foRM 2.pdf · uploaded 26 Sep 2025Source
  • Form 3form 3.PDF · uploaded 26 Sep 2025Source
  • Disclosure of Sold and Booked InventoryInventory.pdf · uploaded 26 Sep 2025Source
  • Form 1Architect certificate.PDF · uploaded 27 Sep 2026Source
  • Form 2engineer certificate.pdf · uploaded 27 Sep 2026Source
  • Form 3form 3.PDF · uploaded 27 Sep 2026Source
  • Disclosure of Sold and Booked InventoryConsent List_1.pdf · uploaded 27 Sep 2026Source
  • Form 1Architect certificate.PDF · uploaded 27 Sep 2026Source
  • Form 2engineer certificate.pdf · uploaded 27 Sep 2026Source
  • Form 3form 3.PDF · uploaded 27 Sep 2026Source
  • Disclosure of Sold and Booked InventoryConsent List_1.pdf · uploaded 27 Sep 2026Source
  • Form 1Architect certificate.PDF · uploaded 27 Sep 2026Source
  • Form 2engineer certificate.pdf · uploaded 27 Sep 2026Source
  • Form 3form 3.PDF · uploaded 27 Sep 2026Source
  • Disclosure of Sold and Booked InventoryConsent List_1.pdf · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 1Architect certificate.PDF · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 1Architect certificate.PDF · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 1Architect certificate.PDF · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 1Architect certificate.PDF · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 1Architect certificate.PDF · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 1Architect certificate.PDF · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 1Architect certificate.PDF · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 2engineer certificate.pdf · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 2engineer certificate.pdf · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 2engineer certificate.pdf · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 2engineer certificate.pdf · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 2engineer certificate.pdf · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 2engineer certificate.pdf · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 2engineer certificate.pdf · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 3form 3.PDF · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 3form 3.PDF · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 3form 3.PDF · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 3form 3.PDF · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 3form 3.PDF · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 3form 3.PDF · uploaded 27 Sep 2026Source
  • Withdrawal Update Form 3form 3.PDF · uploaded 27 Sep 2026Source
  • Form 1Architect certificate.PDF · uploaded 29 Sep 2026Source
  • Form 2engineer certificate.pdf · uploaded 29 Sep 2026Source
  • Form 3form 3.PDF · uploaded 29 Sep 2026Source
  • Disclosure of Sold and Booked InventoryConsent List_1.pdf · uploaded 29 Sep 2026Source
  • Form 1Architect certificate.PDF · uploaded 29 Sep 2026Source
  • Form 2engineer certificate.pdf · uploaded 29 Sep 2026Source
  • Form 3form 3.PDF · uploaded 29 Sep 2026Source
  • Disclosure of Sold and Booked InventoryConsent List_1.pdf · uploaded 29 Sep 2026Source
  • Form 1Architect certificate.PDF · uploaded 29 Sep 2026Source
  • Form 2engineer certificate.pdf · uploaded 29 Sep 2026Source
  • Form 3form 3.PDF · uploaded 29 Sep 2026Source
  • Disclosure of Sold and Booked InventoryConsent List_1.pdf · uploaded 29 Sep 2026Source
  • Form 1Architect certificate.PDF · uploaded 29 Sep 2026Source
  • Form 2engineer certificate.pdf · uploaded 29 Sep 2026Source
  • Form 3form 3.PDF · uploaded 29 Sep 2026Source
  • Disclosure of Sold and Booked InventoryConsent List_1.pdf · uploaded 29 Sep 2026Source
  • Form 2engineer certificate.pdf · uploaded 29 Sep 2026Source
  • Form 3form 3.PDF · uploaded 29 Sep 2026Source
  • Disclosure of Sold and Booked InventoryConsent List_1.pdf · uploaded 29 Sep 2026Source
  • Form 1Architect certificate.PDF · uploaded 29 Sep 2026Source
  • Form 1Architect certificate.PDF · uploaded 29 Sep 2026Source
  • Form 2engineer certificate.pdf · uploaded 29 Sep 2026Source
  • Form 3form 3.PDF · uploaded 29 Sep 2026Source
  • Disclosure of Sold and Booked InventoryConsent List_1.pdf · uploaded 29 Sep 2026Source
  • Form 1Architect certificate.PDF · uploaded 29 Sep 2026Source
  • Form 2engineer certificate.pdf · uploaded 29 Sep 2026Source
  • Form 3form 3.PDF · uploaded 29 Sep 2026Source
  • Disclosure of Sold and Booked InventoryConsent List_1.pdf · uploaded 29 Sep 2026Source
  • Form 1Architect certificate.PDF · uploaded 29 Sep 2026Source
  • Form 2engineer certificate.pdf · uploaded 29 Sep 2026Source
  • Form 3form 3.PDF · uploaded 29 Sep 2026Source
  • Disclosure of Sold and Booked InventoryConsent List_1.pdf · uploaded 29 Sep 2026Source
  • Form 1Architect certificate.PDF · uploaded 29 Sep 2026Source
  • Form 2engineer certificate.pdf · uploaded 29 Sep 2026Source
  • Form 3form 3.PDF · uploaded 29 Sep 2026Source
  • Disclosure of Sold and Booked InventoryConsent List_1.pdf · uploaded 29 Sep 2026Source
  • Form 1Architect certificate.PDF · uploaded 29 Sep 2026Source
  • Form 2engineer certificate.pdf · uploaded 29 Sep 2026Source
  • Form 3form 3.PDF · uploaded 29 Sep 2026Source
  • Disclosure of Sold and Booked InventoryConsent List_1.pdf · uploaded 29 Sep 2026Source
  • Form 1Architect certificate.PDF · uploaded 29 Sep 2026Source
  • Form 2engineer certificate.pdf · uploaded 29 Sep 2026Source
  • Form 3form 3.PDF · uploaded 29 Sep 2026Source
  • Disclosure of Sold and Booked InventoryConsent List_1.pdf · uploaded 29 Sep 2026Source
  • Form 1Architect certificate.PDF · uploaded 29 Sep 2026Source
  • Form 2engineer certificate.pdf · uploaded 29 Sep 2026Source
  • Form 3form 3.PDF · uploaded 29 Sep 2026Source
  • Disclosure of Sold and Booked InventoryConsent List_1.pdf · uploaded 29 Sep 2026Source
  • Form 1Architect certificate.PDF · uploaded 29 Sep 2026Source
  • Form 2engineer certificate.pdf · uploaded 29 Sep 2026Source
  • Form 3form 3.PDF · uploaded 29 Sep 2026Source
  • Disclosure of Sold and Booked InventoryConsent List_1.pdf · uploaded 29 Sep 2026Source
  • Form 1Architect certificate.PDF · uploaded 29 Sep 2026Source
  • Form 2engineer certificate.pdf · uploaded 29 Sep 2026Source
  • Form 3form 3.PDF · uploaded 29 Sep 2026Source
  • Disclosure of Sold and Booked InventoryConsent List_1.pdf · uploaded 29 Sep 2026Source
  • Form 5 (FY 2020-2021)Annual 5_2021.pdf · uploaded 29 Sep 2026Source
  • Form 5 (FY 2024-2025)Annual form 5_2425.PDF · uploaded 29 Sep 2026Source
  • Form 5 (FY 2025-2026)Unicorn developers_form 5_2526.PDF · uploaded 29 Sep 2026Source
  • Form 2A (FY 2020-2021)Form 2A.pdf · uploaded 2 Oct 2026Source
  • Form 2A (FY 2021-2022)Form 2A.pdf · uploaded 2 Oct 2026Source
  • Form 2A (FY 2022-2023)Form 2A.pdf · uploaded 2 Oct 2026Source
  • Form 2A (FY 2023-2024)Form 2A.pdf · uploaded 2 Oct 2026Source
  • Form 2A (FY 2024-2025)Form 2A.pdf · uploaded 2 Oct 2026Source
  • Form 2A (FY 2025-2026)Form 2A.pdf · uploaded 2 Oct 2026Source

Technical

  • DocumentManjur_Nakasha_2.pdf · uploaded 22 Jul 2017Source
  • Documenta2_Indrayani Mam_new_compressed.pdf · uploaded 6 May 2020Source

Technical (Architect)

  • DocumentArchitect certificate.PDF · uploaded 27 Sep 2026Source

Technical (Engineer)

  • Documentengineer certificate.pdf · uploaded 27 Sep 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Gunjalwadi, Sangamner taluka

Survey, CTS, gat or plot numbers

1/31/4S No 115 1/1

Boundaries

North
114 P
South
Road
East
115 P
West
115 P

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectArvind Vaidya and Associates Eknath Vaidya—
Chartered accountantAditya Sanjay Rathi—
Chartered accountantCA Sanjay S Rathi Shankarlal Rathi—
Chartered accountantShruti Nandkumar Soni—
EngineerDeepak Gaykar Deepak Gaykar—
EngineerSagar Vitthal Shinde—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology