BEFORE THE MAHARASHTRA REAL ESTATE REGULATORY AUTHORITY, MUMBAI HEARING HELD THROUGH HYBRID MODE REGULATORY CASE NO. 590 OF 2026 PROMOTER NAME GODREJ MACBRICKS PRIVATE LIMITED PROJECT NAME GODREJ EXQUISITE EXTENSION NO. EA29072621926 PROJECT REGISTERATION NO. P51700024496 ORDER (In an extension application) August 21st, 2026 (Date of hearing – 13.08.2026-matter reserved for order) Coram: Manoj Saunik, Chairperson, MahaRERA Advocate Akshada Thakare a/w Saloni Vyas are present for the applicant promoter. 1. The applicant is the promoter within the meaning of section 2(zk) of the Act who has registered the project namely “GODREJ EXQUISITE” under section 5 of the said Act bearing MahaRERA Project Registration No. P51700024496 (hereinafter referred to as the “Project”). 2. The promoter has filed an extension application no. EA29072621926 (hereinafter referred to as “extension application”) seeking extension of the project under section 7(3) of the Act, which was heard by this Authority on 13.08.2026, wherein the following Roznama was recorded. 1. Heard the representatives appearing for the promoter organization before this Authority. 2. This is the third extension being sought by the applicant in the present project. The applicant submits that the earlier extension was granted under Section 6 of the RERA Act and now seeks further extension up to 31.12.2027. The applicant further submits that about 12% of the allottees have consented to the proposed extension. 3. Out of the total 678 units in the project, 605 units have been sold. The applicant submits that only one complaint is pending before this Authority as on date. Matter is reserved for orders. Page 1 of 5 3. Before proceeding further, the Authority notes that the registration details are already on record. The promoter, while seeking registration of the project, declared the date of completion as 30.09.2024. MahaRERA granted extensions on account of the COVID-19 pandemic to all projects registered with MahaRERA and qualifying under Notifications/Orders Nos. 13, 14, and 21 dated 02.04.2020, 18.05.2020, and 06.08.2021. Thereafter, upon applications made by the promoter, MahaRERA granted extensions under Section 6 of the Act, whereby the date of completion was extended up to 30.09.2026. The promoter submitted that the project was delayed due to failure of the original contractor and the consequent appointment and mobilisation of a new contractor, coupled with post-pandemic shortage of skilled labour, supply-chain disruptions and delays in procurement of construction materials. The progress was further affected by heavy and unseasonal rainfall, escalation in labour and material costs, reduced market demand and consequential financial and cash-flow constraints The promoter has, therefore, applied for a further extension under Section 7(3) of the Act. 4. Thus, the issue before this Authority is regarding grant of an extension under Section 7(3) of the Act. In this regard, it is pertinent to note that the promoter has not obtained 51% majority consent of the allottees of the project. In this context, the relevant extract of Section 7(3) is reproduced hereinbelow for ease of reference: “7 (3) The Authority may, instead of revoking the registration under sub-section (1), permit it to remain in force subject to such further terms and conditions as it thinks fit to impose in the interest of the allottees, and any such terms and conditions so imposed shall be binding upon the promoter.” Page 2 of 5 Section 7(3) provides that instead of revoking the registration, this Authority can impose certain terms and conditions as it thinks fit to let the registration remain in force. 5. The following submissions of the promoter are noteworthy before examining the issue of grant of extension under Section 7(3) of the Act: a) The promoter submitted that the project has been delayed primarily due to the failure of the originally appointed contractor to complete the construction within the stipulated timeline, necessitating termination of the contractor, settlement of related matters, and appointment and mobilisation of a new contractor. b) The promoter further submitted that the project was further affected by prolonged post-pandemic challenges, including shortage of skilled labour, disruption in the supply and procurement of construction materials, and adverse weather conditions, including heavy and unseasonal rainfall, which impacted site productivity and delayed critical construction activities. c) The promoter also submitted that escalation in labour and material costs, reduced market demand and consequential cash-flow constraints adversely affected the promoter’s ability to make timely payments to contractors and vendors and to maintain the required pace of construction. d) The promoter reported that as regards the steps for completion, the RCC work has been completed 100%, finishing work is presently in progress, fit-out materials have been ordered, and additional vendors have been appointed for expeditious completion of the balance finishing and infrastructure works. Page 3 of 5 6. In view of the above submission of the promoter, the issue of the extension under Section 7(3) of the Act, as sought by the promoter without 51% consent of the allottees, needs to be examined considering the above-mentioned fact. The Authority would like to bring on record the statements of objects and reasons of the Act, which are reproduced hereinbelow for ease of reference: “An Act to establish the Real Estate Regulatory Authority for regulation and promotion of the real estate sector and to ensure sale of plot, apartment or building, as the case may be, or sale of real estate project, in an efficient and transparent manner and to protect the interest of consumers in the real estate sector and to establish an adjudicating mechanism for speedy dispute redressal and also to establish the Appellate Tribunal to hear appeals from the decisions, directions or orders of the Real Estate Regulatory Authority and the adjudicating officer and for matters connected therewith or incidental thereto.” 7. The Act aims to promote transparency and efficiency in the real estate sector while protecting the interests of allottees. Non-grant of extension would result in stoppage of the project and impede the promoter from undertaking necessary steps for completion due to lack of valid registration, which would be harsh to the interests of the allottees. Accordingly, the balance of convenience lies in granting extension, subject to conditions ensuring completion of the project. The Authority further notes that extension under Section 7(3) of the Act is necessary to avoid interruption in completion. Therefore, in the interest of the allottees, extension of registration is granted from 30.09.2026 to 31.12.2027 without prejudice to the rights and remedies of the allottees under the Act. “The extension application is accordingly allowed, subject to directions hereinbelow. FINAL ORDER 8. The extension application is allowed, and the extension for the project is granted from 30.09.2026 to 31.12.2027 with the following conditions: Page 4 of 5 A. The Promoter shall complete the remaining construction work and obtain the Occupancy Certificate within the extended period, without prejudice to the statutory and contractual rights of the allottees under the Agreement for Sale, the allottees shall extend necessary cooperation for completion of the Project. B. The Promoter shall submit quarterly progress reports to MahaRERA and the allottees, clearly indicating milestone achievements from time to time. C. The Promoter shall adhere to the revised completion timeline and ensure completion of all balance work within the extended validity period. D. Any delay, non-compliance, or deviation without sufficient cause shall invite appropriate regulatory action under the relevant provisions of the Real Estate (Regulation and Development) Act, 2016 and the rules and regulations framed thereunder. E. It is hereby directed that the grant of extension shall not affect the rights, claims, or remedies of the allottees in the Project. MANOJ Digitally signed by MANOJ SAUNIK SAUNIK Date: 2026.08.21 12:00:23 +05'30' Manoj Saunik Chairperson, MahaRERA Page 5 of 5