1/3, Shree Vivekanand CHS Ltd., A. A. MOHARE & CO. Guru Mandir Road, Saraswat Colony, Dombivli (East) 421 201. M : 9223 543 842 / LL : 0251 – 2473000 CHARTERED ACCOUNTANTS Email : amit@aamco.in Form-3 (See Regulation-3) To, Ganesha Developers 1st Floor, Vaibhav Apartment, Nehru Road, Dombivli East. 2024-25 Q3 Subject - Certificate of Financial Progress of work of Gaurang Apartment having MahaRERA Registration No. P51700048961 being developed by Ganesha Developers Sir, This certificate is being issued for RERA compliance for the Gaurang Apartment having MahaRERA Reg. No P51700048961 being developed by Ganesha Developers and is based on the records and documents produced before me and explanations provided to me by the management of the company. Table A- Estimated cost of the project ( at the time of Registration of the Project) Estimated Cost (at the time of Sr Registration of No Particulars Project) ` 1 Land Cost: a) Value of the land as ascertained from the Annual Statement of Rates (ASR). - b) Estimated amount of Premium payable to obtain development rights, FSI, additional - FSI, fungible area, and any other incentive/concession in deficiency under DCR from Local Authority or State Government/UT Administration or any Statutory Authority. c) Estimated Acquisition cost of TDR (if any) 1,50,00,000 d) Estimated amounts payable to State Government/UT Administration or competent 15,00,000 authority or any other statutory authority of the State or Central Government, towards stamp duty, transfer charges, registration fees etc.; and e) Estimated Land Premium payable as per annual statement of rates (ASR) for - redevelopment of land owned by public authorities. f) Under Rehabilitation scheme: i) Estimated construction cost of rehab building including site development and - infrastructure for the same as certified by Engineer. ii) Estimated Cost towards clearance of land of all or any encumbrances including 2,80,00,000 cost of removal of legal/illegal occupants, cost for providing temporary transit accommodation or rent in lieu of Transit Accommodation, overhead cost, amounts payable to slum dwellers, tenants, apartment owners or appropriate authority or government or concessionaire which are not refundable and so on. iii) Estimated Cost of ASR linked premium, fees, charges and security deposits or 16,48,000 maintenance deposits, or any amount whatsoever payable to any authorities towards and in project of rehabilitation. iv) Any other cost including interest incurred on the borrowing done specifically for - construction of rehabilitation component. Sub-Total of Land Cost 4,61,48,000 2 Development Cost / Cost of Construction: a) Estimated Cost of Construction as certified by Engineer 3,34,71,670 b) Cost incurred on additional items not included in estimated cost (as certified by - Engineer) c) Estimated cost for development of entire project excluding cost of construction as per 1,50,00,000 (i) or (ii) above, i.e. salaries, consultants fees, site overheads, development works, cost of services (including water, electricity. sewerage, drainage, layout roads etc.), cost of machineries and equipment including its hire and maintenance costs, consumables etc. d) Estimated taxes, cess, fees, charges, premiums interest etc. to any statutory Authority. 10,00,000 e) Interest payable to financial institutions, scheduled banks, non-banking financial 60,00,000 institution (NBFC) or money lenders on construction funding or money borrowed for construction. Sub-Total of Development Cost 5,54,71,670 Total Cost of Project (Estimated) 10,16,19,670 * Pass through charges or indirect taxes not included in estimated cost of the project. * Estimated cost shall be revised through correction application. Table B- Actual cost of the project working considered up to - 31/12/2024 Sr Amount Incurred No Particulars ` 1 Land Cost: a) Value of the land as ascertained from the Annual Statement of Rates (ASR). - b) Incurred expenditure on Premium payable to obtain development rights, FSI, additional - FSI, fungible area, and any other incentive/concession in deficiency under DCR from Local Authority or State Government/UT Administration or any Statutory Authority. c) Incurred expenditure for Acquisition of TDR (if any) 36,50,000 d) Amount paid to State Government/UT Administration or competent authority or any - other statutory authority of the State or Central Government, towards stamp duty, transfer charges, registration fees etc.; and e) Land Premium paid for redevelopment of land owned by public authorities. - f) Under Rehabilitation scheme: i) Incurred expenditure for construction of rehabilitation building. Minimum of (a) - or (b) to be considered (a) Cost incurred for construction of rehab building - including site development and infrastructure for the same as certified by Engineer. (b) Incurred expenditure for construction of rehab - building including as per books of accounts as certified by CA. ii) Incurred expenditure towards clearance of land of all or any encumbrances 2,98,14,200 including cost of removal of legal/illegal occupants, cost for providing temporary transit accommodation or rent in lieu of Transit Accommodation, overhead cost, amounts payable to slum dwellers, tenants, apartment owners or appropriate authority or government or concessionaire which are not refundable and so on. iii) Incurred expenditure toward ASR linked premium, fees, charges and security - deposits or maintenance deposits, or any amount whatsoever payable to any authorities towards and in project of rehabilitation. iv) Any other cost including interest incurred on the borrowing done specifically for - construction of rehabilitation component. Sub-Total of Land Cost 3,34,64,200 2 Development Cost / Cost of Construction: i) Expenditure for construction. Minimum of (a) or (b) to be considered 4,32,68,061 (a) Construction cost incurred including site development 5,02,25,000 and infrastructure for the same as certified by Engineer. (b) Actual cost of construction incurred as per books of 4,32,68,061 accounts as verified by CA. ii) Cost incurred on additional items not included in estimated cost (as per Engineer - certificate) iii) Incurred expenditure for development of entire project excluding cost of construction 4,51,935 as per (i) or (ii) above, i.e. salaries, consultants fees, site overheads, development works, cost of services (including water, electricity. sewerage, drainage, layout roads etc.), cost of machineries and equipment including its hire and maintenance costs, consumables etc. b) Incurred expenditure towards taxes, cess, fees, charges, premiums interest etc. to any - statutory Authority. c) Interest payable to financial institutions, scheduled banks, non-banking financial - institution (NBFC) or money lenders on construction funding or money borrowed for construction. Sub-Total of Development Cost 4,37,19,996 3 Total Cost of Project (Actual incurred as on date of certificate) 7,71,84,196 4 Proportion of the Cost incurred on Land Cost and Construction Cost to the Total Estimated 75.95% Cost (Table A) 5 Amount Which can be withdrawn from the Designated Account. 7,71,84,196 6 Less: Amount withdrawn till date of this certificate from the Designated Account** 5,88,10,072 7 Net Amount which can be withdrawn from the Designated Bank Account under this 1,83,74,124 certificate * Pass through charges or indirect taxes not included in estimated cost of the project. ** This amount is 70% of the net collection amount. Table C - Statement for Calculation of Receivables from the Sales of the Real Estate Project Sold Inventory To Outsider Allottees Sr. No Flat No. Carpet Area Unit Consideration as per Received Amount Balance Receivable (in sq mts) Agreement/Letter of Allotment 1 S-004 17.32 10,00,000 2,85,000 7,15,000 2 401 50.68 42,00,000 37,23,000 4,77,000 3 502 66.67 45,00,000 52,25,000 -7,25,000 4 O-005 44.59 50,00,000 49,50,000 50,000 5 O-006 8.78 22,00,000 21,00,000 1,00,000 6 O-101 48.20 7 O-102 59.03 2,15,00,000 2,00,25,000 14,75,000 8 O-103 30.72 9 O-104 44.68 10 201 48.20 11 202 59.03 1,80,00,000 1,42,50,000 37,50,000 12 203 30.72 13 204 44.68 14 301 50.68 15 302 66.67 1,50,00,000 1,26,63,850 23,36,150 16 303 33.58 17 503 33.58 26,50,000 15,20,000 11,30,000 18 504 50.00 35,00,000 8,55,000 26,45,000 sub- Total 787.81 7,75,50,000 6,55,96,850 1,19,53,150 To Landowners 19 304 50.00 20,00,000 18,08,509 1,91,491 20 403 33.58 30,00,000 27,99,750 2,00,250 21 404 50.00 20,00,000 15,48,250 4,51,750 22 501 50.68 20,00,000 17,20,000 2,80,000 23 601 50.68 50,00,000 - 50,00,000 24 701 18.48 7,00,000 3,80,000 3,20,000 25 702 27.21 18,00,000 15,95,600 2,04,400 26 703 49.94 25,00,000 10,00,000 15,00,000 27 704 15.89 26,00,000 - 26,00,000 28 706 50.00 22,30,000 19,00,000 3,30,000 29 S-001 18.90 10,00,000 16,00,000 -6,00,000 30 S-002 17.32 45,00,000 37,23,430 7,76,570 31 S-003 17.32 10,00,000 3,42,000 6,58,000 sub- Total 450.00 3,03,30,000 1,84,17,539 1,19,12,461 Gross Total 1237.81 10,78,80,000 8,40,14,389 2,38,65,611 * Unit consideration as per agreement / letter of allotment and amount received does not include pass through charges and indirect taxes. Unsold Inventory Valuation (Ready Recknor Rate as on the date of Certificate of the Residential Rs. 76,900 per sm./Commercial premises Rs. 97,300 per sm./ Office premises Rs. 88,100 per sm.) Sr. No Unit No. Carpet Area Unit Consideration as per Unit Considertation = (in sq mts) Read Reckoner Rate (ASR) Carpet Area * 20% * Rate 32 402 66.67 61,52,308 33 602 66.67 61,52,308 34 603 33.58 30,98,762 35 604 50.00 46,14,000 36 705 34.60 31,92,888 Total 3785.69 2,32,10,266 Table D - Comparison between Balance Cost and Receivables Sr Amount No Particulars ` 1 Estimated Balance Cost to Complete the Real Estate Project (Difference of Total Estimated 2,44,35,474 Project cost less Cost incurred) 2 Balance amount of receivables from sold apartments as per Table C of this certificate (as 2,38,65,611 certified by Chartered Accountant as verified from the records and books of Accounts) 3 (i) Balance unsold area (to be certified by Management and to be verified by CA from the 3,785.69 records and books of accounts), (ii) Estimated amount of sales proceeds in respect of unsold apartments (calculated as per 2,32,10,266 ASR multiplied to unsold area as on the date of certificate, to be calculated and certified by CA) as per Annexure A to this certificate. 4 Estimated receivables of ongoing project. Sum of 2 + 3 (ii) 4,70,75,877 5 (To be filled for ongoing projects only) 70% Amount to be deposited in Designated Account - 70% or 100% If 4 is greater than 1, then 70% of the balance receivables of ongoing project will be deposited in designated account If 4 is lesser than 1, than 100% of the balance receivables of ongoing project will be deposited in designated Account. Table E - Designated Bank Account Details Designated Bank Account Details - 100304180004449 Actual Amount till date Sr (From 24/01/2023 to No Particulars 31/12/2024) 1 Opening Balance 4,236.29 2 Deposits 6,67,31,261.00 3 Withdrawals 6,67,14,458.96 4 Closing Balance 21,038.33 I hereby certify that required proportion of money, as specified in the act, collected from allottees of the project unit as indicated in Table C has been deposited in Designated RERA Bank Account. I hereby certify that Ganesha Developers has utilised the required proportion of money, as specified in the act, collected from allottees for this project only for land and construction of this project. Table E - Means of Finance Estimated* Proposed / Estimated Actual (At the time of (As on the date of (As on the date of Registration) ` certificate) certificate) Sr (proposed and ` ` No Particulars indicative) 1 Own Funds 10,16,19,670 10,16,19,670 - 2 Total Borrowed Funds (Secured) - - - - Drawdown availed till date 3 Total Borrowed Funds (Unsecured) - - - - Drawdown availed till date 4 Customer receipts used for project - - 7,71,84,196 5 Total Funds for project 10,16,19,670 10,16,19,670 7,71,84,196 6 Total Estimated Cost (As per Table A) 10,16,19,670 10,16,19,670 - Table G - Any comments / observations of CA Sr No Particulars 1 Bank Account No. 100304180004449 is RERA Collection Account as specified in the Application for Registration. This was a old account of the promoter. After RERA Registration the collection from customer was credited to this account and later on transferred to business current account based on expenses incurred for the project. The promoter has collected amount from allottees from account other than the RERA Designated Separate account. This is a violation of basic provisions of RERA. 2 For the purpose of quarterly update as required by MahaRERA, self certified unaudited cost is considered as per books of accounts of the promoter. 3 Table G - Customer receipts used for project are actual collection from customers in RERA collection Account. 4 Table E - Means of Finance estimated figures are as certified by the management. Yours Faithfully, Agreed and accepted by UDIN - 25148601BMIKBH3940 Signature of Promoter Date : 21/04/2025 Name - Girish Mahindre Place : Dombivli Date : 21/04/2025 Place : Dombivli