PRANAY CHAN D RATREYA ATch itect 4, Sumedha society, Behind Aditya Shagun mall" NDA Pashan Road, Bavdhan Khurd, Pune 411021. cell:9766356580 AnnFxqre A FORM 1 [.9ee Regulation 3] ARCHITECT'S C E RTI FICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date:09.07.2022 To, Surabhi constructions, 6, Mithila Apaftments, Lane no.14, Prabhat Road, Pune 38 Subject: Ceftificate of Percentage of Completion of Construction Work of Ashwinl Apaftments, S.no.56,Plot no.34, Bhonde colony, Erandawane, Pune, having MahaRERA Registration Number (Only applicable after Project Registration) being Developed by Sudhir Constructions, Pune. Sir, I have undeftaken assignment as Architect of Certifying Percentage of Completion of Construction Work of Ashwini Apartments, S.no.56, Plot no.34, Bhonde colony, Erandawane, Pune, having MahaRERA Registration Number (Only applicable after Project Registration) being Developed by Sudhir Constructions, Pune. Based on the Site Inspection, with respect to the Layout / each Building/Wing of the aforesaid Real Estate Project, I certify that as on date of this Ceftiflcate, the Percentage of Work Done for each of the Building/Wing of the Real Estate Project under MahaREM is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. TABLE.A Layout / Building / Wing Number _ (to be prepared separately for each Layout/Building/Wing of Project) s. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Ceftificate) (1) (2) (3) 1. Excavation 0o/o 2. Basements (if any) 0o/o 3. Podiums (if any) 0o/o 4. Plinth Oo/o 5, Stilt Floor 0o/o 6. Slab of Super Structure Oo/a 7" Internal Walls, Internal Plaster, Floorings, Doors, 0o/o windows within Flats / Premises B. Sanitary Fittings within Flats / Premises 0o/o 9. Staircases, Lift Wells & Lobbies at each Floor Level 0o/o Overhead and Underqround Water Tanks 10. External Plumbing & External Plaster, Elevation, jo/a Completion of Terraces, with waterproofing of the Buildinq / Winq 11. Installation of Lifts, Water Pumps, Fire Fighting Fittings 0o/o and Equipments as per CFO NOC, Electrical Fittings, Mechanical Equipments, Compliance to conditions of Environment I CRZ NOC, Finishing to Entrance Lobby/s, [,linth Protection, Paving of Areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activitv TABLE.B Common Areas (Internal & External Development Works) in respect of the Registered Phase / Project Number s. Common Areas & Facilities Proposed Percentage of actual Details No. (Yes / Work Done NO) (As on date of Certificate) (1) (2]. (3) (4) (s) 1. Internal Roads & Footpaths No 2. Water Supply Yes 3. Sewerage (Chambe;, Lines, Septic Yes Tank, STP) 4. Strom Water Drains Yes 5. Landscapinq & Tree Plantinq Yes 6. Street Liqhtinq No /t 7. CommuniW Buildinqs No 8. Treatment & Disposal of Sewage No and Sullaqe Water 9. Solid Waste Management & No Disoosal 10. Water Consenration / Rain Water Yes Haruestino 11. Enerqv Manaqement No 12. Fire Protection & Fire Safety Yes requirements 13" Electrical Meter Room, Sub- No Station, Receiving Station L4, Others (Option to Add more) Yours faithfully, Ar. Pranay Chandratreya, Pune. License Number: CAl99 125207 . Agreed & accepted by: Signature of Promoter Name: Surabhi Constructions, PunE Date: