FORM1 [seeRegulation3] ARCHITECT'SCERTIFICATE (To be submitted atthe time ofRegistration of Ongoing Projectandfor withdrawal ofMoney from Designated Account ) Date:22.04.2021 To M/S. PARANJAPE SCHEMES (CONSTRUCTION) LIMITED, Pune Subject:Certificate of Percentage ofCompletion of Construction Work of 3 buildings of the Forest Trails The Highland Tower 9,10&11oftheProject[MahaRERA Registration NumberP52100000067] situated on the Sector no R12B ,S.No.16/1 and Others demarcated by its boundaries(Latitude180 30'28.03"NLongitude73044'14.19"E ) , Part of sector no R12 tothe East, Part of sector G8 to the west,Survey no-85tothe North , andpart of 18.0m township road and part of sector G8tothe south, of west division-Pune, Village–Mouje hugaon, Taluka–Mulshi, District-Pune 412115admeasuring 14628.96sq.mts.AreabeingdevelopedbyM/S. PARANJAPE SCHEMES (CONSTRUCTION) LIMITED, out of which plot area admeasuring 3853.48sq.mts is OS7 to be used as common area & facility and balance plot area admeasuring 10775.48 sq.mts is sector R12B to be used for construction. Sir, I, Radhika A. Vaidya have undertaken assignment as Architect/Licensed Surveyorof certifying Percentage of Completion of Construction Work of 3 buildings of the Forest Trails Highland Tower 9,10&11oftheProject [MahaRERA Registration NumberP52100000067] situated on the Sector no R12B ,S.No.16/1 and Others demarcated by its boundaries (Latitude180 30'28.03"N Longitude73044'14.19"E) , Part of sector no R12 to the East, Part of sector G8 to the west, survey no-85 to the South, , and part of 18.0m township road and part of sector G8 to the south, of west division-Pune, Village –Mouje Bhugaon, Taluka – Mulshi, District-Pune 412115 admeasuring 14628.96 sq.mts. Area being developed by M/S. PARANJAPE SCHEMES (CONSTRUCTION) LIMITED, out of which plot area admeasuring 3853.48 sq. mts is OS7 to be used as common area &facility and balance plot area admeasuring 10775.48 sq.mts is sector R12B to be used for construction. 1. Followingtechnical professionalsare appointedby Owner/ Promoter:- (i) Ar. Radhika A. Vaidya asL.S. / Architect; (ii) JW consultants LLPasStructuralConsultant (iii)Aquamate consultants Pvt. Ltd as MEP Consultant (iv) Rajesh Pawar as Site Supervisor. BasedonSiteInspection,withrespecttoeachoftheBuilding/Wingoftheaforesaid Real Estate Project , I certify that as on the date of this certificate, the Percentage of Workdoneforeachofthebuilding/WingoftheRealEstateProjectasregisteredvide number under MahaRERA is as per table A herein below. The percentageoftheworkexecutedwithrespecttoeachoftheactivityoftheentirephase is detailedinTable B. 1 Table A Forest Trails HighlandTower 9 (to be prepared separately for each Building/Wing of the Project) Sr.No Tasks /Activity Percentage Ofwork done 1 Excavation 100% 2 Plinth 90% 3 number of Podiums 90% 4 Stilt Floor 80% 5 number ofSlabs of Super Structure 50% 6 Internal walls, Internal Plaster, Floorings within Flats/Premises, 15% Doors andWindows toeachofthe Flat/Premises 7 SanitaryFittings withinthe Flat/Premises, Electrical Fittings within 0% the Flat/Premises 8 Staircases,Lifts Wells andLobbies ateach Floorlevel 10% connectingStaircases andLifts, OverheadandUndergroundWater Tanks 9 The external plumbingandexternal plaster, 0% elevation,completionofterraceswithwaterproofingof the Building/Wing 10 Installationof 0% lifts,waterpumps,FireFightingFittingAndEquipmentasperCFONOC,El ectricalfittingsto Common Areas, electro, mechanical equipment, Compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, CompoundWall andallotherrequirementsasmaybe requiredto ObtainOccupation /Completion Certificate 2 Table A Forest Trails HighlandTower 10 (to be prepared separately for each Building/Wing of the Project) Sr. No Tasks /Activity Percentage Of work done 1 Excavation 100% 2 Plinth 90% 3 number of Podiums 90% 4 Stilt Floor 90% 5 number ofSlabs of Super Structure 35% 6 Internal walls,Internal Plaster, Floorings within 04% Flats/Premises, Doors andWindows toeachofthe Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical 0% Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level 0% connecting Staircases and Lifts, Overhead and Underground Water Tanks 9 The external plumbing and external plaster, 0% elevation, completion of terraces with waterproofing of the Building/Wing 10 Installation of lifts, water pumps, Fire Fighting Fitting And 0% Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, CompoundWall andallotherrequirementsasmaybe requiredto ObtainOccupation /Completion Certificate 3 Table A Forest Trails HighlandTower 11 (to be prepared separately for each Building/Wing of the Project) Sr. No Tasks /Activity Percentage Of work done 1 Excavation 100% 2 Plinth 90% 3 number of Podiums 90% 4 Stilt Floor 90% 5 number ofSlabs of Super Structure 5% 6 Internal walls,Internal Plaster, Floorings within 0% Flats/Premises, Doors andWindows toeachofthe Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical 0% Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level 0% connecting Staircases and Lifts, Overhead and Underground Water Tanks 9 The external plumbing and external plaster, 0% elevation, completion of terraces with waterproofing of the Building/Wing 10 Installation of lifts, water pumps, Fire Fighting 0% Fitting And Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, CompoundWall andallotherrequirementsasmaybe requiredto ObtainOccupation /Completion Certificate 4 Internal&ExternalDevelopmentWorksinRespectoftheentireRegisteredPhase S.No CommonareasandFacilities, Amenities Proposed Percentageof Details (Yes/No) Workdone 1. InternalRoads&Footpaths Yes 65% Footpath only no internal roads 2. WaterSupply Yes 85% 3. Sewarage (chamber, lines, Septic Tank Yes 80% STP of sector R12 ,STP) (Part)of township 4. StormWaterDrains Yes 90% 5. Landscaping&TreePlanting Yes 80% 6. Street Lighting Yes 90% 7. CommunityBuildings No - 8. Treatment and disposal of sewage and Yes 0% STP of sector R12 sullage water (Part)of township 9. Solid Waste Yes 10% management& Disposal 10. Water conservation, Rain water Yes 0% 11. harvesting Energy management Yes 0% 12. Fireprotectionandfiresafety Yes 40% requirements 13. Electricalmeterroom,sub-station, Yes 15% receivingstation 14. Aggregate area of recreational open Yes 80% Work done for space aggregate open space of township 15. Open parking Yes 0% 16. Clubhouse Yes 95% 17. Multipurpose hall Yes 100% 18. Swimming pool Yes 95% YoursFaithfully For Aniruddha Vaidya & Associates AR.RADHIKA VAIDYA L.S/ Architect License No CA/85/8968 5