FORM 1 [see Regulation 3] ARCHITECT'S CERTIFICATE R/1905/2024/Rera 2 30.05.2024 To M/s Gun Rajan Constructions C.A. to Owner Shop No.1, Bldg. No.11, Sah Niwas Co-op Hsg. Soc. Ltd., Near Dutt Mandir. Vivek College Road ,Siddharth Nagar No.4, Goregaon (West), Sir, Subject: Certificate of Percentage of Completion of Construction Work of “Vallabh Krupa CHSL” having MAHARERA R e g i s t r a ti o n N u m be r _ _ being developed by ( M/s Gun Rajan Constructions). Sir, I/ We M/s. Rasik P. Hingoo Associates have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of Completion of Construction Work of “Vallabh Krupa CHS” having MAHARERA Registration Number __ being developed by (M/s Gun Rajan Constructions). Based on Site Inspection, with respect to Layout / each of the Building/Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MAHARERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. ..2.. -:2:- Table A Building /Wing Number (Two Wings - Wing ‘A’ & ‘B’ (to be prepared separately for each Building/Wing of the Project) Wing ‘A’ Sr. No Tasks /Activity Percentage of work done 1. Excavation 90% 2. Nil number of Basement(s) and 1 no. of Plinth 80% 3. 03 numbers of Podium NA 4. Stilt Floor 0% 5. 18 number of Slabs of Super Structure (excluding podium floors) 0% 6. Internal walls, Internal Plaster, Floorings 0% within Flats/Premises, Doors and Windows to each of the Flat/Premises 7. Sanitary Fittings within the Flat/Premises, 0% Electrical Fittings within the Flat/Premises 8. Staircases, Lifts Wells and Lobbies at each Floor 0% level connecting Staircases and Lifts, Overhead and Underground Water Tanks 9. The external plumbing and external plaster, 0% elevation, completion of terraces with waterproofing of the Building/Wing, 10. Installation of lifts, water pumps, Fire Fighting 0% Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate ..3.. -:3:- Table A Building /Wing Number -Two Wings - Wing ‘A’ & ‘B’ (to be prepared separately for each Building/Wing of the Project) Wing ‘B’ Sr. No Tasks /Activity Percentage of work done 1. Excavation 100% 2. Nil number of Basement(s) and 1 no. of Plinth 100% 3. 03 numbers of Podium NA 4. Stilt Floor 0% 5. 18 number of Slabs of Super Structure 0% (excluding podium floors) 6. Internal walls, Internal Plaster, Floorings 0% within Flats/Premises, Doors and Windows to each of the Flat/Premises 7. Sanitary Fittings within the Flat/Premises, 0% Electrical Fittings within the Flat/Premises 8. Staircases, Lifts Wells and Lobbies at each Floor 0% level connecting Staircases and Lifts, Overhead and Underground Water Tanks 9. The external plumbing and external plaster, 0% elevation, completion of terraces with waterproofing of the Building/Wing, 10. Installation of lifts, water pumps, Fire Fighting 0% Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate ..4.. -:4:- TABLE-B Internal & External Development Works in Respect of the entire Registered Phase Sr. Common areas and Facilities, Amenities Proposed Percentage Details No. (Yes/ of Work No) done 1 Internal Roads & Footpaths No -- NA 2 Water Supply Yes 0% -- 3 Sewarage (chamber, lines, Septic Tank, Yes 0% -- STP) 4 Storm Water Drains Yes 0% -- 5 Landscaping & Tree Planting Yes 0% -- 6 Street Lighting No -- NA 7 Community Buildings No -- NA 8 Treatment and disposal of sewage and No -- NA sullage water 9 Solid Waste management & Disposal No - NA 10 Water conservation, Rain water harvesting Yes 0% -- 11 Energy Management No -- NA 12 Fire protection and fire safety requirements Yes 0% -- 13 Electrical meter room, sub-station, receiving Yes 0% -- station 14 Others (Option to Add more) - - -- 15 Aggregate Area of Recreational open Space - - -- Yours faithfully, Rasik Digitally signed by Rasik Prabhudas Hingoo DN: c=IN, o=Personal, title=4209, pseudonym=FA08880A556CF5E64AD6C6 Prabhuda 16C4D5B977B2A050BE, 2.5.4.20=a752684f3f32c1590778bc1a21d eb1d8855169331130dab2ad4d5a2fc97cb dca, postalCode=400104, st=Maharashtra, s Hingoo serialNumber=9AE235D56A09CE35CFEBB 5CFF0EEFF2FB92A669F77E3D7792A0890 A476667FA7, cn=Rasik Prabhudas Hingoo Date: 2024.05.30 18:42:42 +05'30' RASIK P. HINGOO CA/84/8385 Agreed and accepted by: M/s Gun Rajan Constructions Digitally signed by RAJESH JAYANTILAL SHAH RAJESH DN: c=IN, postalCode=400104, st=MAHARASHTRA, street=2201 22ND FLOOR SIDDHARTH NAGAR SAKET CHS LTD SIDDHARTH NAGAR NO 4MUMBAI SUBURBANGOREGAON WESTOPP VIVEK COLLEGE 400104, l=MUMBAI SUBURBAN, o=Personal, title=4728, JAYANTILAL SHAH serialNumber=50094145a466e8de994c6bac3788b8f6f5a58adcbca00414ed10e293700 14ead, pseudonym=472820230111181358567, 2.5.4.20=daee3cfe285d0fdcba8ab1b3e0a895e8e98f2cc94c689ebd365392688482df2f, email=RAJESHMAN.SHAH@GMAIL.COM, cn=RAJESH JAYANTILAL SHAH Date: 2024.05.31 12:47:10 +05'30' Rajesh J. Shah