Construction Status: o Has the construction on the project started post COVID lockdown? Yes Pre Monsoon Work o If yes, When did it start? 15th June 2020 - Labour availability:40% o Percentage of labour available on site against needed (For example: If you need 100 labour for doing existing work, but only fifty are available due to Labour migration then percentage shall be 50%): Considering the way ahead, Maharera feels that all the promoters should take their flat purchasers into the confidence about the issues and progress of the project. Hence Maharera feels that society or association of the allotees should be formed as per norms and keep them updated with the situation. Therefore please submit the following information. Engagement with Allottees: o Has the Association of Allottees or society formed?No o Are you engaging with allottees communicating the impact of COVID on the project:Yes You are kindly requested to upload this data on the MahaRERA portal on the document uploads section under the tab “Details of Restarting Construction Post Lockdown”, enabling us to support you to best capacity. MahaRERA, as regulatory and development authority, is always considering measures to assist Promoters in re-starting the projects and real estate sector. Maharera would certainly a bridge between buyer’s plight and your genuine difficulties. Pl do share your plans