VB+/\ vlvek bhosale associates architects+ Interior designers 'FORM 1' ARCHITECT'S CERTIFICATE th 7 ,January ,2026 To, M/s. Makwise Homes LLP B / 902, Lords CHS. Ltd. Plot no. 35 /35A, Sector 15, CBD Belapur, Navi Mumbai 400 614 Subject: Certificate of Percentage of Completion of Construction Work of "Anuvidnyan Nagar Co. Op. Housing Society Ltd." Composite Building, comprising of Two Wings 'A'&'B' on Plot bearing Survey No. 141 (Pt), CTS No.178{pt), 179 (pt.), 174 (pt.), Village Mankhurd, Near Datta Mandir, Agarwadi, M/East Ward, Mankhurd, Mumbai- 400088.Demarcated by its boundaries, (latitude and longitude of the end points of plot) 19°02'53.71nN,72°SS'31.48"Eto the East (18.30 Mt. Wide Agarwadi Rd.),19°02'55.42"N,72°SS'31.93"Eto the North (Railway Boundary),19°02'56.62"N,72°55'31.0S"Eto the West (Nalla side), 19°02'54.47"N,72°SS'29.67HEto the South (Prop. D.P. Rd.)of Division Konkan, village Mankhurd , Ta Iuka Kurla District Mumbai Suburban, PIN400088, Admeasuring Plot area 3631.70 Sq. Mt. having MahaRERA Registration Number: P51800053906, Being developed by M/s. Makwise Homes LLP Sir, I Architect Vivek Bhosale of M/s. Vivek Bhosale Associates have undertaken assignment as Architect for certifying Percentage of Completion of Construction Work of Building, comprising of Two Wings 'A'&'B' on Plot bearing Survey No. 141 (Pt), CTS No. 178(pt), 179 (pt.), 174 (pt.), Village Mankhurd, Near Datta Mandir, Agarwadi, M/East Ward, Mankhurd, Mumbai- 400088. Admeasuring Plot area 3631.70 Sq. Mt., being developed by M/s. Makwise Homes LLP 1. Following Technical Professionals are appointed by Promoter: (i) Ar. Vivek Bhosale of M/s. Vlvek Bhosale Associates as the Architects (ii) Er. Samarth P. Agarwal of M/s. Adharshlla Consultants as the Structural Consultant. {ill) Er. Kanhaiya Yadav, M/s. KY MEP Consultants as the MEP Consultant. {Iv) Er. Sachln S. Yadav as the Site Supervisor Based on Site Inspection, with respect to each of the Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the Wings of the Real Estate Project is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. 1 A, DR. DAMJI SADAN, A. 5. GAWDE MARG, RA/GAD CHOWK, GHATKOPAR (E), MUMBAI 400077, H (OFF.)+919930639636, {DIR} +91 9870199673, EMAIL: vbarch@qmail.com, vbo.studio@qmail.com WEB SITE: www.vboarcl ~~}2£ 011t., ~ ~ -, " I..,- ~ •~ r ._ I -~ *- - ~, #,,,....., ., /I VB+A vlvek bhosale associates architects+ Interior designers TABLE-A (For Wing "A") Sr. No. Tasks / Activity Percentage of Work done (1) (2) (3) 1 Excavation 100% 2 Basement (Pit Parking) 100% 3 Plinth 100% 4 Podium NIL 5 Stilt Floor 100% 6 Fifteen (15) Number of Slabs of Super Structure 84%(12th floor Slab Completed) 7 Internal Walls, Internal Plaster, Floorings within 0% Flats/Premises, Doors and Windows to each of the Flat/Premises. 8 Sanitary Fittings within the Flat/Premises, Electrical 0% Fittings within the Flat/Premises 9 Staircases, Lifts Wells and Lobbies at each Floor level 0% connecting Staircases and Lifts, Overhead and Underground Water Tanks 10 The external plumbing and external plaster, 0% elevation, completion of terraces with waterproofing of the Building/Wing. 11 Installation of lifts, water pumps, Fire Fighting 0% Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/ Completion Certificate l A, DR. DAMJI SADAN, A. 5. GA WOE MARG, RA/GAD CHOWK, GHATKOPAR (E}, MUMBAI 4fJ0077, (OFF.)+919930639636, {DIR} +91 9870199673, EMAIL: vbarch@qmail.com, vbo.studlo@qmall.com WEB SITE: www.vbaor • ·~=:::::--... I I / /· --......::::::=::::::;.-- VB+/\ vlvek bhosale associates architects+ Interior designers TABLE-A (For Wing "B") Sr. No. Tasks/ Activity Percentage of Work done (1) (2) (3) 1 Excavation 100% 2 Basement (Pit Parking) 100% 3 Plinth 100% 4 Podium NIL 5 Stilt Floor 100% th 6 Fifteen (15) Number of Slabs of Super Structure 84%(12 floor Slab Completed) 7 Internal Walls, Internal Plaster, Floorings within 0% Flats/Premises, Doors and Windows to each of the Flat/Premises. 8 Sanitary Fittings within the Flat/Premises, Electrical 0% Fittings within the Flat/Premises 9 Staircases, Lifts Wells and Lobbies at each Floor level 0% connecting Staircases and Lifts ,Overhead and Underground Water Tanks 10 The external plumbing and external plaster, 0% elevation, completion of terraces with waterproofing of the Building/Wing. 11 Installation of lifts, water pumps, Fire Fighting 0% Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation / Completion Certificate 1 A, DR. DAMJI SADAN, A. 5. GA WOE MARG, RA/GAD CHOWK, GHATKOPAR (E}, MUMBAI 400077 (OFF.)+9199306 39636, {DIR} +919870199673, EMAIL: vbarch@qmail.com, vbo.studio@qmail.com WEB SITE: w~w.vbaarc • ~=::::::-..... j VB+ /\ vlvek bhosa le asso ciate s architects+ Interio r design ers TABLE-8 Internal and External Development Works in respect of the entire Project Sr.No. Common Areas and Proposed Percentage Details Facilities Amenities Yes/No Work Done (2) (3) (4) (5) (1) 1 Internal Road & Foot Paths NO 0% NIL Water Supply YES 0% Connection to be Taken 2 From MCGM 3 Sewerage (chamber, lines, YES 0% Only Internal Sewerage Septic Tank, STP). Line to be laid - 4 Storm Water Drains YES 0% Internal Strom Water drain to be made s Landscape / Tree Planting. YES 0% Tree Planting As per Requireme nt of MCGM 6 Street Lighting NO 0% NIL 7 Communit y Buildings NO 0% NIL 8 Treatment and disposal of NO 0% NIL sewage and sullage water. 9 Solid Waste management & YES 0% NIL Disposal 10 Water Conservation, Rain YES 0% NIL Water Harvesting 11 Energy management NO 0% NIL 12 Fire protection and YES 0% As Per Requireme nt of fire safety requirements Chief Fire Officer 13 Electrical Meter Room, Yes 0% Only Electrical Meter Substation, Receiving Room Station 14 Other Option &More NO NO NIL Yours Truly, Vivek Bhosale: Architect COA Regd. No. CA/2007/396'36 for, M/s. VIVEK BHOSALE ASSOCIATES Agreed and Accepted by Mr. Dinesh R. Purohit (Promoter / Developer) For, M/s. Makwise Homes LLP 1 A, DR. DAMJI SADAN, A. S. GA WOE MARG, RA/GAD CHO WK, GHA TKOPAR (E), MUMBAI 400077, moil.com WEB SITE: www.vbaorch itects.in (OFF.)+91 99306 39636, (DIR) +91 9870199673, EMAIL: vborch@qmoi l.com, vbp.studio@q