VINYASACONSULTANTS cONSTRUCTION COST CONSULTANT &QUANTITY SURVEYOR Annexure- B FORM-2 ENGINEER'S CERTIFICATE (To be submitted at the time of ongoing project and for withdrawalof Money from Designated Account- Project Wise) To, 31$T MARCH' 2025 GODREJ PROPERTIES LIMITED, 5th Floor, Godrej One, Pirojsha Nagar VikhroliEast, Mumbai 400 079 Subject: Certificate of cost Incurred for development of Godrej Sky Terraces, Chembur having MahaRERA Registration Number P51800053882 being developed by Godrej Properties Limited. Sir, 1 VWe Vinyasa Consultants have undertaken assignment of certifying estimated cost for Godrej Sky Terraces, Chembur having MahaRERA Registration number P51800053882 (Only Applicable after project Registration being developed by Godrej Properties Limited. 2 We have estimated the cost of civil, MEP, and allied works required for completion of the apartments and proportion completion of internal &external works of the project as per specifications mentioned in agreement of sale. Our estimated cost calculations are based on the drawings/plans made available to us for the project under reference by the developer/ consultants. The schedule of items and quantity required for the entire work as calculated by Quantity surveyort M/s. Plannerfy appointed by Developer/Engineer, the assumption of the cost of material, Labour and other inputs made by developer, and the site inspection carried out by us to ascertain/ confirm the above analysis given to us. 3. We estimated Total Estimated cost of completion of the aforesaid project under reference at Rs.1,64,77,99,080.85 (Total of Table A and B) at the time of registration. The estimated total cost of project is with reference to the Civil, MEP and Allied works required for completion of the apartments and proportionate completion of internal & external works, as per spe cifications mentioned in agreement of sale and for the purpose of obtaining occupation certificate / completion certificate for the Building(s), /Wing(s) / Layout /Plotted Development from the BNCMC being the planning Authority under whose jurisdiction the aforesaid Project is being implemented. 4. Estimated cost incurred till date is calculated at Rs. 21,04,82,346.45 (Total of Table A and B). The Amount of estimnated Cost Incurred is calculated on the basis of input materia/ Services used and unit cost of these items. 5. The balance cost of completion of the Civil, MEP and Allied works for completion of the apartment and proportionate completion of internal and external works, as per specifications mentioned in agreement of sale, of the project is estimated at Rs. 1,43,73,16,734.40 (Total of Table Aand B). 6. Icertify that the cost of Civil, MEP and Allied work for the apartments and propotionate internal & external works, as per specifications mentioned in agreement of sale, of the aforesaid Project as completed on the date of this certificate is as given in Table AandB Below: KALPATARU HARMONY, KASPATE WASTI, MANKAR CHOUK, WAKAD, PUNE- 411057 | VInyasaconsultants@gmail com Uo909 622 6262 VINYASACONSULTANTS CONSTRUCTION COST CONSULTANT &QUANTITY sURVEYOR Table A Building / Wing/ Layout / Plotted development bearing Building / Wing/ Layout / Plotted development bearing Survey number CTS No.673, 673/1 to 673/20 &783 (Part) of Village Borla, situate at Chembur, Mumbai Demarcated by its boundaries CTS nos. 674 &676 to East, CTS no. 783 part &668 to West, 36.60 m wide V.N. Purav road to North and 36.6m wide Choithram gidwani road to the South admeasuring 7795.31 sqm Area being developed by Godrej Properties Limited. Sr. Particulars Amount (In Rs) No. SKY TERRACES Total Estimated cost of the building /wing as on date of Registration 1,56,04,93,831.25 2 Cost incurred as on date of Certification till 31ST MAR25 (based on the Estimated cost) 21,04,82,346.45 3 Work done in Percentage (as Percentage of the estimated cost) 13.49% 4 Balance Cost to be Incurred (Based on Estimated Cost) 5 Cost Incurred on Additional /Extra ltems not included in the Estimated 1,35,00,11,484.80 Cost (Annexure A) 0.00 Table B Internal &External Development Works in Respect of the Registered Phase Sr. No. Particulars Amount (Crs) Total 1 Total Estimated cost of the Internal and External Development Works including amenities, Retail and Facilities in the layout as on date of Registration 8,73,05,249.60 2 Cost incurred as on date of certification till 31sT MAR25 (based on the Estimated cost) 0.00 3 Work done in Percentage (as Percentage of the estimated cost) 0.00% 4 Balance Cost to be Incurred (Based on Estimated Cost) 8,73,05,249.60 5 Cost Incurred on Additional /Extra Items not included in the Estimated Cost 0.00 (Annexure A) Yours Faithfully (Signature of Engineer) lePUNE KSIMdO VINYASACONSULTANTS PARAAG RODE | ECI REG. NO: PEI00010/25 KALPATARU HARMONY. KASPATE WASTI. MANKAR CHOUK, WAKAD, PUNE- 411057| vinyasaconsultants@amail.com | 0909 622 6262 VINYASACONSULTANTS cONSTRUCTION COST CONSULTANT & OUANTITY SURVEYOR Agreed and Accepted by: Signature of Promoter Name: Avaneeh Aya Date: Note: 1. The scope of work is to complete Registered Real Estate Project as per drawings approved from time to time and as per specifications mentioned in agreement of sale. 2 () Quantity survey can be done by office of engineer or can be done by an independent Quantity surveyor, whose certificate of quantity calculated can be relied upon by the Engineer. In case of independent Quantity surveyor being appointed by developer, the name has to be mentioned at the placed marked (*) and in case quantity are being calculated by office of Engineer, the name of the person in the office of the Engineer, who is responsible for the Quantity calculated should be mentioned at the place marked (*). The details as calculated by quantity Surveyor* M/s. Plannerfy / Godrej Properties Limited (GPL) and not cross verified by M/s. Vinyasa Consultants. 3. (**) Balance cost to be incurred (4) may vary from Difference between Total Estimated cost (1) and Actual cost incurred (2) due to deviation in quantity required / escalation of cost etc. As this is an estimated cost, any deviation in quantity required for development of the Real Estate Project will be result in amended of the cost incurred / to be incurred. 4 Allcomponents of the work with specifications are indicative and not exhaustive. 5 Please specify if there are any deviation / qualifications. Example: Any deviations input material used from specifications in agreement of sale. Table C List of Extra/Additiona/Deleted Items Considered in Cost (Which were not part of the original estimate of Total cost) Sr. No. List of Extra / Additiona/ Deleted Itenms Amount (ln INR Cr) 1 2 KALPATARUHARIMONY, KASPATE WASTI, MANKAR CHOUK, WAKAD, PUNE- 411057 | vinyasaconsultants @gmail.com | 0909 622 6262