Form 1 ARCHITECT'S CERTIFICATE Date: 4th January 2024 To, M/s. Krishna Developers Metro Chambers, 3rd & 4th Floor, Plot No. 137ab, Kandivali Co-op- Govt, Ind. Estate Ltd, Charkop , Kandivali (West), Mumbai- 400067. Subject: Certificate of Percentage of Completion of Construction Work of Disha Darshan registered under MahaRERA vide registration No. P51800053854 being developed by M/s. Krishna Developers. Sir, I, Mr. Ashish R. Solanki have undertaken assignment as Architect of certifying Percentage of Completion of Construction Work of Disha Darshan. registered under MahaRERA vide registration No. P51800053854 being developed by M/s. Krishna Developers. Based on Site Inspection, with respect to the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the Wings of the Real Estate Project registered under MahaRERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A Sr. Tasks /Activity Percentage No. of work done 1 Excavation 100% 2 Basements, if any N.A. 3 Podiums, if any N.A. 4 Plinth 100% 5 Stilt Floor 100% 6 10 number of Slabs of Super Structure 60% 7 Internal walls, Internal Plaster, Floorings, Doors and Windows within 5% Flat/Premises 8 Sanitary Fittings within the Flat/Premises 0% 9 Staircases, Lifts Wells and Lobbies at each Floor level, Overhead and 40% Underground Water Tanks 10 The external plumbing and external plaster, elevation, completion of 10% terraces with waterproofing of the Building/Wing 11 Installation of lifts, water pumps, Fire Fighting Fittings and 10% Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale 12 Any other activities N.A. Table B Internal & External Development Works in Respect of the entire project. Sr. Common areas and Proposed Percentage of Details No. Facilities, Amenities ( Yes / No ) work done 1 Internal Roads & No NA Not Applicable. Footpaths 2 Water Supply Yes 30% On completion of the building as per H.E. NOC. 3 Sewerage (chamber, lines, Yes 10% Internal Chambers and Septic Tank , STP) lines proposed. No STP Proposed. 4 Storm Water Drains Yes 10% Will be connected to Municipal Storm Water Drain. 5 Landscaping & Tree Yes 0% As per Tree NOC. Planting 6 Street Lighting No NA Not Applicable. 7 Community Buildings No NA Not Applicable. 8 Treatment and disposal of No NA Not Applicable. sewage and sullage water 9 Solid Waste management Yes 10% Vermiculture Bin will & Disposal be provided as per requirement by MCGM. 10 Water conservation, Rain Yes 0% Recharge pit proposed water harvesting as per Remarks given by RWH Consultants. 11 Energy management No NA Not Applicable. 12 Fire protection and fire Yes 10% As per CFO NOC. safety requirements 13 Electrical meter room, Yes 5% As per requirement by sub-station, receiving Electricity Supply station Company. 14 Others (Option to Add No NA Not Applicable. more) Yours Faithfully, For AASHISH SOLANKI a r c h i t e c t s ASHISH Digitally signed by ASHISH RAMNIKLAL SOLANKI DN: c=IN, o=Personal, title=2619, RAMNIKL pseudonym=4DA4990582609B6F5AB6B 7C3244B345F, 2.5.4.20=eccceae4677b4c2ab63624eca6 0fe886cb0b489b692e4d889153451669b AL 49a89, postalCode=400057, st=Maharashtra, serialNumber=9DB82C5CD99A333AD65 B652B476BA6DF1C16CE7B0F3170528B2 SOLANKI EBE341207558F, cn=ASHISH RAMNIKLAL SOLANKI Date: 2024.01.04 10:27:11 +05'30' Ashish R. Solanki Regn. No.: CA/2000/26252 Agreed and Accepted by: For M/s. Krishna Developers. Mr. Hiten K. Kothari (Partner) Date: