Building Permission Cell, Greater Mumbai / MHADA (A designated Planning for MHADA layouts constituted as per government regulation No.TPB4315/167/CR- 51/2015/UD-11 DT. 23 May, 2018.) FURTHER COMMENCEMENT CERTIFICATE No. MH/EE/(BP)/GM/MHADA-87/1292/2024/FCC/2/Amend Date : 05 November, 2024 To mahesh Lira Verat (M/s. Gurukrupa Realcon Lifespaces LLP) C-106, Vashi Plaza, Sector – 17, Vashi, Navi Mumbai – 400 703 Sub : Proposed Redevelopment Building no.07 Known as “Dahisar Megha Co-Op Housing Society Ltd”, on Plot bearing CTS No.1665 (Pt) Village Dahisar (East), Shailendra Nagar, Dahisar (E) Mumbai.400068. Dear Applicant, With reference to your application dated 03 July, 2023 for development permission and grant of Further Commencement Certificate under section 44 & 69 of Maharashtra Regional Town Planning Act, 1966 to carry out development and building permission under section 45 of Maharashtra Regional and Town Planning Act, 1966 to Proposed Redevelopment Building no.07 Known as “Dahisar Megha Co-Op Housing Society Ltd”, on Plot bearing CTS No.1665 (Pt) Village Dahisar (East), Shailendra Nagar, Dahisar (E) Mumbai.400068.. The Commencement Certificate/Building permission is granted on following conditions. 1. The land vacated in consequence of endorsement of the setback line / road widening line shall form part of the public street. 2. That no new building or part thereof shall be occupied or allowed to be occupied or used or permitted to be used by any reason until occupancy permission has been granted. 3. The Commencement Certificate / Development permission shall remain valid for one year from the date of its issue. 4. This permission does not entitle you to develop land which does not vest in you or in contravention of the provision of coastal zone management plan. 5. This Certificate liable to be revoked by the VP & CEO, MHADA if: 6. If construction is not commenced this commencement certificate is renewable every year but such extended period shall be in no case exceed three years provided further that such laps shall not bar any subsequent application for fresh permission under section 44 of the Maharashtra Regional and Town Planning Act, 1966. a. The development work in respect of which permission is granted under this certificate is not carried out or the use thereof is not in accordance with the sanctioned plans. b. Any of the condition subject to which the same is granted or any of the restrictions imposed by the VP & CEO, MHADA is contravened or not complied with. c. The VP & CEO, MHADA is satisfied that the same is obtained by the applicant through fraud or misrepresentation and the appellant and every person deriving title through or under him in such an event shall be deemed to have carried out the development work in contravention of section 43 and Page 1 of 3 event shall be deemed to have carried out the development work in contravention of section 43 and 45 of the Maharashtra Regional Town Planning Act, 1966 7. This CC shall be re-endorsed after obtaining IOA for work beyond plinth. 8. The conditions of this certificate shall be binding not only on the applicant but on his heirs, executors, assignees, administrators and successors and every person deriving title through or under him. VP & CEO / MHADA has appointed Shri. Rupesh M. Totewar, Executive Engineer to exercise his powers and function of the Planning Authority under section 45 of the said Act. This CC is valid upto dt. 19 September, 2025 Issue On : 20 September, 2023 Valid Upto : 19 September, 2024 Application No. : MH/EE/(BP)/GM/MHADA-87/1292/2023/CC/1/New Remark : This C.C. is granted for work upto Plinth level (i.e., height up to 0.15m above AGL) as per approved plans dtd. 12.06.2023. Issue On : 19 December, 2023 Valid Upto : 19 September, 2024 Application No. : MH/EE/(BP)/GM/MHADA-87/1292/2023/FCC/1/New Remark : Now, this C.C. is Re-endorsed upto Plinth (i.e., height up to 0.15m above AGL) as per approved Amended plans dtd. 28.11.2023. Note:- That the Guidelines issued by Chief Engineer(D.P.) BMC dt. 15/09/2023 & Hon’ble Municipal Commissioner (BMC) dt. 25/10/2023 shall be strictly followed on Site in respect of control of Air Pollution. Issue On : 09 January, 2024 Valid Upto : 19 September, 2024 Application No. : MH/EE/(BP)/GM/MHADA-87/1292/2024/FCC/1/Amend Remark : This F.C.C. is now granted for building Comprising of wing A & Wing B and consisting of basement in wing B having depth of 5.00 mt. for pump room, + Part Ground floor for Entrance Lobby & meter room & Part stilt for Pit Puzzle Car parking, surface car parking, + 1st floor Part for Fitness Centre & residential user and Part for double height Puzzle Parking + 2nd floor Part for Residential user and Part for double height Puzzle Parking + 3rd to 9th floor for residential user with height 30.15 Mtr. As per approved Amended plans issued vide/no. MH/EE/BP Cell/GM/MHADA -87/1292/2023dated: 28.11.2023. Issue On : 24 June, 2024 Valid Upto : 19 September, 2024 Application No. : MH/EE/(BP)/GM/MHADA-87/1292/2024/FCC/1/Old Remark : This C.C. is Further Extended for wing A from 10th to 14th upper floor for residential users i.e height 44.65 mt. AGL and wing B from 10th to 15th upper floor for residential users i.e height 47.55 mt. AGL As per last approved amended plan issued by MHADA on dtd.25.06.2024 vide u/No.MH/EE/(BP)/GM/MHADA-87/1292/2023. Dated. 28/11/2023. Issue On : 10 September, 2024 Valid Upto : 19 September, 2024 Application No. : MH/EE/(BP)/GM/MHADA-87/1292/2024/FCC/1/Amend Remark : Page 2 of 3 Remark : This C.C. is Now Further extended for 'Wing A' from 15th to 18th upper floor for residential user i.e. height 56.69 mt. AGL and 'Wing B' from 16th to 19 th upper floor for residential user i.e. 61.06 mt. AGL, as per approved plan u/no. MH/EE/BP Cell/GM/MHADA -87/1292/2023 dated: 28.11.2023 " That the guidelines for reduction of Air Pollution issued by Chief Engineer (D.P.) BMC dt. 15/09/2023,Hon’ble Municipal Commissioner (BMC) dt. 25/10/2023 and MHADA circular vide No. ET-321, dtd. 25.10.2023 shall be strictly followed on site. Issue On : 05 November, 2024 Valid Upto : 19 September, 2025 Application No. : MH/EE/(BP)/GM/MHADA-87/1292/2024/FCC/2/Amend Remark : This C.C. is now Further extended for wing ‘A’ from 18th to 19th upper floor (i.e. for entire work for Wing ‘A’ & Wing ‘B’ upto 19th floor for residential user with total height 61.06 mt. mt. including LMR + OHT) as per approved plans u/no. MH/EE/BP Cell/GM/MHADA -87/1292/2023 dated: 28.11.2023. That the guidelines for reduction of Air Pollution issued by Chief Engineer (D.P.) BMC dt. 15/09/2023,Hon’ble Municipal Commissioner (BMC) dt. 25/10/2023 and MHADA circular vide No. ET-321, dtd. 25.10.2023 shall be strictly followed on site. Digitally signed by Rupesh Muralidhar Totewar Date: 05 Nov 2024 15:38:13 Organization :MHADA Designation :Executive Engr. Authority_Sign Executive Engineer/B.P.Cell Greater Mumbai/MHADA Copy submitted in favour of information please 1. Chief Officer Mumbai Board. 2. Deputy Chief Engineer /B.P. Cell/MHADA. 3. Asst. Commissioner R North Ward MCGM. 4. Chief ICT officer/MHADA for information & uploaded to MHADA website. Copy to : - 5. EE Borivali Division / MB. 6. A.E.W.W R North Ward MCGM. 7. A.A. & C R North Ward MCGM 8. Architect / LS - Hansraj Raghuraj Vishwakarma. 9. Secretary Dahisar Megha Co-Op Housing Society Ltd Page 3 of 3