Annexure A FORM 1 [see Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) R/1901/2025/Rera 11 04.10.2025 To, PRANAV CONSTRUCTIONS LIMITED MUMBAI SUBURBAN, MAHARASHTRA, 400104 Subject : Certificate of percentage of Work of completion of construction work of REDEVELOPMENT OF SHINING STAR CHSL having MahaRERA Registration Number P51800053810 (Only Applicable after project Registartion) being developed by PRANAV CONSTRUCTIONS LIMITED Sir, I/We RASIK P HINGOO AND ASSOCIATES have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of completion of Construction Work of REDEVELOPMENT OF SHINING STAR CHSL having MahaRERA Registration Number P51800053810 (Only Applicable after project Registration, being developed by PRANAV CONSTRUCTIONS LIMITED ) Based on Site Inspection,with respect to Layout / each of the Building/Wing of the aforesaid Real Estate Project I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A Layout/Building/Wing Number: SHINING STAR CHSL- WING A/NA Sr. No. Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100% 2 Basements (if any) 0.00 3 Podiums (if any) 0.00 4 Plinth, 100% 5 Stilt Floor 90% 6 Slabs of Super Structure 100% 7 Internal walls, Internal plaster, Floorings, Floors and windows within 65% Flats/Premises 8 Sanitary Fitting within the Flat/Premises 15% Page 1 of 4 Sr. No. Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) 9 Staircases, lifts Wells and Lobbies at each Floor level Overhead and 90% Underground Water Tanks 10 External plumbing and external plaster, elevation, completion of terraces with 0.00 waterproofing of the Building/wing. 11 Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per 0.00 CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection,paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. Layout/Building/Wing Number: SHINING STAR CHSL- WING B/NA Sr. No. Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100% 2 Basements (if any) 0.00 3 Podiums (if any) 0.00 4 Plinth, 100% 5 Stilt Floor 90% 6 Slabs of Super Structure 100% 7 Internal walls, Internal plaster, Floorings, Floors and windows within 65% Flats/Premises 8 Sanitary Fitting within the Flat/Premises 15.% 9 Staircases, lifts Wells and Lobbies at each Floor level Overhead and 90% Underground Water Tanks 10 External plumbing and external plaster, elevation, completion of terraces with 0.00 waterproofing of the Building/wing. 11 Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per 0.00 CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection,paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. Layout/Building/Wing Number: SHINING STAR CHSL WING C/NA Sr. No. Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100% 2 Basements (if any) 0.00 3 Podiums (if any) 0.00 4 Plinth, 100% 5 Stilt Floor 100% 6 Slabs of Super Structure 100% 7 Internal walls, Internal plaster, Floorings, Floors and windows within 85% Flats/Premises 8 Sanitary Fitting within the Flat/Premises 30% 9 Staircases, lifts Wells and Lobbies at each Floor level Overhead and 90% Underground Water Tanks 10 External plumbing and external plaster, elevation, completion of terraces with 60% waterproofing of the Building/wing. 11 Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per 0.00 CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection,paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. Layout/Building/Wing Number: SHINING STAR CHSL- WING D/NA Sr. No. Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) Page 2 of 4 Sr. No. Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) 1 Excavation 100% 2 Basements (if any) 0.00 3 Podiums (if any) 0.00 4 Plinth, 100% 5 Stilt Floor 90% 6 Slabs of Super Structure 100% 7 Internal walls, Internal plaster, Floorings, Floors and windows within 85% Flats/Premises 8 Sanitary Fitting within the Flat/Premises 30% 9 Staircases, lifts Wells and Lobbies at each Floor level Overhead and 90% Underground Water Tanks 10 External plumbing and external plaster, elevation, completion of terraces with 60% waterproofing of the Building/wing. 11 Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per 0.00 CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection,paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. Page 3 of 4 Table B - Common Areas (Internal and External Development Works) in respect of Registered Phase / Project Number) Sr.No Common areas and facilities Proposed Percentage of Actual Details (Yes / No) Work Done (As on date of the Certificate) (1) (2) (3) (4) (5) 1 Internal Roads & Footpaths No 0.00 NA 2 Water Supply Yes 0.00 WORK TO BE INITIATED 3 Sewerage (Chamber, Lines, Septic Tank , STP) Yes 0.00 WORK TO BE INITIATED 4 Storm Water Drains Yes 0.00 WORK TO BE INITIATED 5 Landscaping & Tree Planting Yes 0.00 WORK TO BE INITIATED 6 Street Lighting No 0.00 NA 7 Community Buildings No 0.00 NA 8 Treatment And Disposal Of Sewage And Sullage Water No 0.00 NA 9 Solid Waste Management And Disposal Yes 0.00 WORK TO BE INITIATED 10 Water conservation /Rain water harvesting Yes 0.00 WORK TO BE INITIATED 11 Energy managemcnt No 0.00 NA 12 Fire protection and fire safety requirements Yes 0.00 WORK TO BE INITIATED 13 Electrical meter room, sub-station, receiving station Yes 0.00 WORK TO BE INITIATED 14 Aggregate area of recreational Open Space No 0.00 NA 15 Open Parking Yes 0.00 WORK TO BE INITIATED Yours Faithfully Rasik Digitally signed by Rasik Prabhudas Hingoo DN: c=IN, o=Personal, title=4209, pseudonym=FA08880A556CF5E64AD6C616C Prabhuda 4D5B977B2A050BE, 2.5.4.20=a752684f3f32c1590778bc1a21deb1 d8855169331130dab2ad4d5a2fc97cbdca, postalCode=400104, st=Maharashtra, serialNumber=9AE235D56A09CE35CFEBB5CF s Hingoo F0EEFF2FB92A669F77E3D7792A0890A47666 7FA7, cn=Rasik Prabhudas Hingoo Date: 2025.10.04 11:14:04 +06'00' RASIK P HINGOO AND ASSOCIATES Signature & Name (IN BLOCK LETTERS) of L.S/ Architect ( License No: CA/84/8385) Date of Certificate: Agreed and accepted by: Digitally signed by PRANAV PRANAV KIRAN ASHAR KIRAN ASHAR Date: 2025.10.06 11:33:26 +05'30' Signature of Promoter Name: PRANAV CONSTRUCTIONS LIMITED Date: Page 4 of 4