Tushar Bhor Architect 10/60, Madhu Sadan, Jain Society, Sion West, Mumbai ~ 400 0221 Maharashti'a I India I FORM 1 [see Regulation 3] ARCHITECT'S CERTIFICATE Date 31-Dec-24 TO' M/s. Saptarishi Urban Space Private Limited, 801-802, Crystal Tower CHS Ltd. Maruti Lane, Fort, Mumbai 400001 Subject: Certificate of Percentage of Completion of Construction Work of Meluha having MahaRERA Registration Number P51800053441 being developed by M/s. Saptarishi urban Space Private limited Sir' I Tushar Bhor have undertaken assignment as Architect of certifying Percentage of Completion of Construction Work of Meluha having MahaRERA Registration Number P51800053441 being developed by M/s. Saptarishi Urban Space Private Limited Based on Site Inspection, with respect to Layout/each of the Building/Wing of the aforesaid Real Estate Project,I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table a. TABLE-A Building Name Me[uha Sr. No. Tasks /Activity Percentage of work done (1) (2) (3) 1. Excavation 20% 2. Basement(s) (if any) 0% 3. Podiums (if any) 0% 4. Plinths 0% 5. Stilt Floor 0% 6. Slabs of Super Structure 0% 7. Internal Walls, Internal Plaster, Floorings, Doors and Windows 0% within Flat/Premises. Page 1 of 3 Tushar Bhor Architect 10/60, Madhu Sadan, Jain Society, Sion West, Mumbai -400 0221 Maharashtra I India I 8. Sanitary Fittings within the Flat/Premises. 0% 9. Staircase, Lift wells and Lobbies at each Floor level Overhead and 0% Underground Water Tanks 10. External plumbing and external plaster, elevation, completion of 0% terraces with waterproofing of the Building/Wing. 11. Installation of lifts, water pumps, Fire Fighting Fittings and 0% Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment /CRZ NOC, finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any Other activities. TABLE-B Internal and External Development Works in respect of the entire Registered Phase S.NO.(1) Common areas and Facilities, Amenities(2) Proposed(Yes/No)(3) Percentage ofWorkdone(4) Details(5) 1 Internal Roads & Foothpaths No 2 Water Supply Yes 0% As per MCGMapproval 3 Sewerage (chamber, lines, Septic Tank , Yes 0% As per MCGM STP) approval 4 Storm Water Drains Yes 0% As per MCGMapproval 5 Landscaping & Tree Planting Yes 0% 6 Street Lighting NO 7 Community Buildings No 8 Treatment and disposal of sewage and Yes 0% As per MCGM sullage water approval 9 Solid Waste management & Disposal Yes OO/o As per MCGMapproval Page 2 of 3 Tushar Bhor Architect 10/60, Madhu Sadan, Jain Society, Sion West, Mumbai -400 0221 Maharashtra I India I 10 Water conservation, Rainwater harvesting Yes 0% As per MCGMapproval 11 Energy management Yes 0% As per MCGMapproval 12 Fire protection and fire safety requirements Yes 0% As per MCGMapproval 13 Electrical meter room, sub-station, Yes 0% As per MCGM receiving station approval 14 Others (Option to Add more) 5`!'i.8?|2.o3"q%;`,!T (License No. CA/2008/42031) Principal Architect Agreed and Accepted by of Promoter Page 3 of 3