BHUSHANJADHAV ARCHITECT(B.ARCH) FORM-1 [see Regulation 3] ARCHITECT’S CERTIFICATE To Date:31.12.2024 M/s Shree Swami Samarth Builders 101, SHH Residency, Lake Road, Near TATA Power, Shiva indl Estate, Bhandup(W), Mumbai-400078. Subject: Certificate of Progress of Work of Project –Virginia CHS for new registration under Maharera being Developed by M/s Shree Swami Samarth Builders Sir, I/ we Bhushan Jadhav have undertaken assignment as Architect / Licensed Surveyor of certifying Percentage of Completion of Construction Work of Project - Virginia CHS for new registration under Maharera being Developed by M/s Shree Swami Samarth Builders Based on Site Inspection, with respect to each of the Building / Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building / Wing of the Real Estate Project to be registered under RERA is as per table A herein below. The percentage of the work executed with respect to each of the major activity of the Building / Wing and Overall Percentage of the work done with respect to each Building / Wing is detailed in the Table B. MOB.-9967199472 Email-bhushanjadhav1123@rediffmail.com Address:- 709, Exim Link C.H.S., NearRunwal Green, MulundGoregaonLink Road,Nahur West, Mumbai - 400078. Table A for Composite Building Tasks /Activity Percentage Sr. No of work done 1 Excavation 100% 2 Number of Basement 100% 3 Plinth 50% 4 Podiums NA 5 Stilt Floor 0% 6 Slabs of Super Structure 0% 7 Internal walls, Internal Plaster, Floorings, Doors and Windows 0% within Flat Premises. 8 Sanitary Fittings within the Flat/Premises. 0% 9 Staircases , Lift Wells, Lobbies at each Floor Over head and 0% Underground water Tank. 10 External plumbing and External Plaster, elevation, completion 0% of terraces with waterproofing of the Building/Wing 11 Installation of lifts, water pumps, Fire Fighting Fittings and 0% Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment/CRZ NOC, Finishing to entrance Lobby/s, Plinth Protection, Pving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete the Project as per Specification in Agreement of Sale. Any other activities. TABLE – B Internal & External Development Works in Respect of the project S. No. Common Roads and Facilities, Proposed Percentage of Details Amenities (Yes/No) Work done 1 Internal Roads & FootPaths No NA 2 Water Supply Yes 0% water connection will be obtained after the completion of the building 3 Sewerage (chamber, sewage Yes 0% Will be completed lines), as per SWD Storm Water Drains remarks 4 Landscaping & Tree Planting No NA 5 Common area Lighting Yes 0% Will be completed before OCC 6 Water conservation, Rain water Yes 0% Will be completed harvesting as per remarks of RWH 7 Fire protection and fire safety Yes 0% Will be completed requirements as per CFO NOC 8 Electrical meter room, sub- Yes 0% Will be completed station, receiving station as per norms of MSEDCL Yours Faithfully MR. BHUSHAN JADHAV BHUSHAN Digitally signed by BHUSHAN VITTHAL JADHAV DN: c=IN, o=Personal, title=4108, 2.5.4.20=71568aa38c9412d697db592a76f36 VITTHAL 2f1182943156deea437bd89de469c4de6bd, postalCode=400078, st=Maharashtra, serialNumber=e29f3085ca9e63d116ea2e1d JADHAV 5ce161539b8262bcff1c1aa585fee2f657e1a2 c1, cn=BHUSHAN VITTHAL JADHAV Date: 2025.08.06 14:07:55 +05'30' Architect License No. CA/2012/57189 Agreed & Accepted By Promoter M/s Swami Samarth Builders Mr. Vaibhav A Kokate partner Date: 31.12.2024