Til G.M.ARCH Pvr. trD. ARCHITECTS, ENGINEERS, PROJECT MANA6EMENT CONSULTANTS SURVEYORS, TNTER]OR DESIGNERS & VALUERS GSm ilo : 274480G5r6{DlZ0l C tlo: t 452mUHamPIC1285'79 FORM 1 lSee Regulation 3| ARCHTTECT"S CERTIFICATE Date:_ 30t June, 2024 To, I\4/s, tnfinity Narayani Associates 43, Sunvilla, Yashodham, Gen. A.K.VADYA Marg Goregaon (East), Mumbai:-400053. Subr Certificate of Percentage of Completion of Construction work of Gateway Residence having MahaRERA Registration Number: P518m052907 {Only Applicable After Project Register being developed by the lWs. Infinity Narayani Associates. Dear Sir, We M/s. G. M. Arch Pvt. Ltd. have undertaken assignment as Architect of certifying Percentage of Completion of Construction Work of Gateway Residence having MahaRERA Regiskation Number: P5180m52907 {Only Applicable AIter Project Register being developed by the ]\ills. InfiniW Narayani Associates. 1. Following technical professionals are appointed by Owner / Promoter:- (i) M/s. G. M. Arch Pvt. Ltd. as Architect/Licensed Surveyor. (ii) fay Shree Krishna as Structural Consultant (iii) Shri Kishor Velani as Site Engineer. IJased on Site lnspection, with respect to Layout of the Building of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of work done for the Building of the real Estate Project as registered vide number P51800052907. under RERA is as per table A herin below. The percentage of the work executed with respect to each if the major activity of the Building and Overall percentage of work done with respect to Building is detailed in the in the Table B. Head Off:- Mezzanine Floor, P. T Marg, K. X. Chambers. Fort, Mumbai City - 4OO 001, Maharashtra office Address: 3, Mercury cHS, Opp Hall Mark Susiness Plaza, Eandra (E), Mumbai400O51. Cell.: +91 98200326231+919920trJ32623 E-mail: smarch.psr@smail.com. smarch.mumbai@smail.com. smarch@rediffmail.com. info@smarch.in Website: www.gmarch.in Date - 3L0G2(D4 Table A Sr. No Tasly'Activity Percentage of Work Done (As of the date of the Certificate) (1) (2) (3) 1. Excavation 100 % 2. Number of Basement(s) N.A Number of Plinth 700% 1. Number of Podium NA 5. Stilt Floor NA 6. Slabs of Super Structure upto 08th Roor 1007. a. lnternal walls - 2nd to 6rh Floor 100% b. Internal plaster _ 2,'a & 5o, Floor. lm% 7 c. Floorings Nit d. Doors and Windows within Flat / Premises Nil 8. Sanitary Fittings within the Flat/Premises. Not Done Statcases, Lifts Wells, and Lobbies upto 8th Floor level Overhead 9 lWYo Water tanks. The external plumbing and extemal plaster, elevation, completion 10. Not Done of teraces with of the Building/ Wing. Installation of lifu, water pumps, Ftue Fighting Fittings and Equipment as per CFO NOC, Electrical fiftings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, 11. finishing to entrance lobby/s, plinth protection, paving of areas Not Done appurtenant to Building/Wing Compound Wall protection and aII other requirements as may be required to complete the project as per specification in the agreement of sale. Any other activities. Date - 3G'oG2oZ TABLE-B Common Atea (Internal and Extemal Development Worksl in respect of the Registered Phase/Proi Number Percentage of Sr. Conunon areas and Facilities, Proposed Work Done No (As on the Details Amenities (Yes/ No) date of the Certified) (1) (2) (3) (4) (s) 1 lnternal Roads & Footpaths No 0 N.A. 2. Water Suppty Yes 0 As per Approved Plan Sewerage (chamber, Lines, 3. Yes 0 As per Approved Plan Septic Tanl, {P) .1 Storm Water Drairu Yes 0 As per Approved Plan 5 Laadscaphg & Tree Planting Yes 0 NA 6 Street Lighting No 0 NA 7. Community Buildings No 0 NA 8. lreatorent and disposal of No 0 NA rewage a4d sullage water. 9 iolid Waste Management & No 0 NA Disposal Water Conversation & Rain 10 Yes 0 As per Approved Plan Water Harvesting 11 Energy Management No 0 NA 't2. Ffue hotection and fire salety Yes 0 As per Norms requirements Electrical meter room, sub- 13 Yes 0 As per Approved Plan ;tation, receiving station. Aggregate area of recreational 14. Yes 0 NA Spen Space Open Parking No 0 NA Yours Faithfully, l4/s. G. M. Arch Pvt Ltd. Purushottam -::E_ :.::". 6ovind Redekar (P. G. Redekar) (License No - (,/148/LS) Agreed ad Accepted by: Signature of homoter Name: Date: