AR DESIGN STUDIO ARCHITECTURE | INTERIORS | PMC | LANDSCAPE FORM 1 ARCHITECT'S CERTIFICATE Date: 30/06/2026 To, JPV Realtors Private Limited, 701, 7th Floor, Jet Prime, Andheri East, 400093. Subject: Certificate of Percentage of Completion of Construction work of Pratap Legacy Redevelopment of Building known as "Parle Aparajita CHSL" on plot bearing C.T.S. No. 873, F.P. No. 7 TPS Vile Parle-VI of village Vile Parle(W), situated at Dadabhai Road, Vile parle (West), Mumbai. in K Ward Mumbai admeasuring 874.80 Sq.mt. area being developed by M/s. JPV Realtors Private Limited. Sir, I, Shri. Ankit U. Jain have undertaken assignment as Architect of certifying Percentage of Completion of Construction Work for on plot bearing C.T.S. No. 873, F.P. No. 7 TPS Vile Parle- VI of village Vile Parle(W), situated at Dadabhai Road, Vile parle (West), Mumbai. In K Ward Mumbai, in K Ward admeasuring 874.80 Sq.mt. area being developed by M/s. JPV Realtors Private Limited. 1. Following technical professionals are appointed by Owner / Promoter: - (i) Shri. Ankit U Jain of M/s. AR Design Studio as Architect. (ii) Shri. Gautam U. Chande as Structural Consultant. (iii) Shri. Subhash G. Mhatre as Site Supervisor. Based on Site Inspection, with respect to each of the Building/Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project as registered vide number P51800052555 under MahaRERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. 2127 & 2128, Eaze Zone Mall, Goregoan Mulund link Road, Sunder Nagar, Malad West. ardesignstudio2017@gmail.com | work@ardesignstudio.co.in https://ardesignstudio.co.in/ +912240169458 / +917738723684 / 85 Table A Building /Wing Number_ (to be prepared separately for each Building /Wing of the Project) Sr. Percentage of Work as on Tasks / Activity No. (30-06-2026) 1 Excavation 100% 2 Number of Basement(s) 00% 3 Number of Podiums 00% 4 Plinth 100% 5 Stilt Floor 100% 6 Number of Slabs of Super Structure 100% 7 Internal walls, Internal Plaster, Floorings within 100% Flats/Premises, Doors and Windows to each of the Flat/Premises 8 Sanitary Fittings within the Flat/Premises, Electrical 100% Fittings within the Flat/Premises 9 Staircases, Lifts Wells and Lobbies at each Floor level 100% connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10 The external plumbing and external plaster, elevation, 100% completion of terraces with waterproofing of the Building/Wing 11 Installation of lifts, water pumps, Fire Fighting 100% Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other 00% requirements as may be required to Obtain Occupation /Completion Certificate TABLE-B Internal & External Development Works in Respect of the entire Registered Phase Sr. Percentage of Common Area & Facilities, No Proposed completion as Details Amenities on (30-06-2026) 1. Internal Road & Footpaths No 00% - 2. Water Supply Yes 100% Will be completed as per consultant Remarks 3. Sewerage Chamber Lines, Yes 100% Will be completed Septic Tank, STP as per consultant Remarks 4. Storm water Drains Yes 100% Will be completed as per consultant Remarks 5. Landscape & Tree Planting Yes 100% Will be completed as per Tree NOC 6. Street Lighting No 00% - 7. Community Building No 00% - 8. Treatment and Disposal of No 00% - Sewerage & Sullage Water 9. Solid Waste Management & Yes 00% SWM NOC taken Disposal by developer 10. Water conservation & Rain Yes 100% Will be completed water Harvesting as per consultant Remarks 11. Energy Management No 00% - 12. Fire Protection & Fire Safety Yes 100% Will be completed Requirement as per provisional Fire NOC 13. Electric Meter room, Yes 100% Will be complied substation, Receiving Station by developer. 14 Others (Option to Add more) No 00% Will be completed by developer. Yours Faithfully, Agreed and Accepted by Digitally signed by Ankit Ankit Uttamchand Uttamchand Jain Date: 2026.06.30 Jain 15:28:44 +05'30' Shri. Ankit U. Jain of M/s. AR Design Studio. Signature of Promoter Lic. No. CA/2014/64556 Name: JPV Realtors Private Limited Date: