PARAS CONSULTANTS K. H. SHAH CONSULTINGENGINEERS B.E. (Civil) M.I.E. Regn. No. STR S/33 S/197 Mobile : 98673 07061 / 62 EMail: parasconsultants@NabR£om ANNEXURE B Ref, No. FORM-2 Date - [See Regulation 3] ENGINEER'S CERTIFICATE (1obe submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account-Project Wise) For the period 30" JUNE- 2024 To. The The Garodia Nagar Mahavirdham CHS Limited, CTS 195/47,Plot No 48-51, Garodia Nagar, Ghatkopar East, Mumbai-40077 Subject: Certificate of Cost Incurred for Development of Garodia Nagar Mahavirdham CHS Limited Plot No 48-512, bearing C.T.S. No. 195/47 at Village Ghatkopar at Garodia Nagar, Kirol, Kurla, Ghatkopar East, Mumbai Suburban Pin Code 400077 Tehsil: Kurla District: Mumbai Suburban 1839.20 Sq. Mts. having MAHARERA Registration Number P51800052562 being developed by Garodia Nagar Mahavirdham CHS Limited Sir. 1. I/We Mr. K. H. Shah of M/s Paras Consultant have undertaken assignment of certifying Estimated Cost for Garodia Nagar Mahavirdham CHS Limited situated on the Plot No 48-512, bearing C.T.S. No. 195/47 at Village Ghatkopar at Garodia Nagar, Kirol, Kurla, Ghatkopar East, Mumbai Suburban Pin Code 400077 Tehsil: Kurla District: Mumbai Suburban 1839.20 Sq. Mts. Area having MAHARERA Registration Number P51800052562 being developed by Garodia Nagar Mahavirdham CHS Limited. 2. We have estimated the cost of Civil, MEP and allied works required for completion of the apartments and proportionate completion of internal & external works of the project as per specifications mentioned in agreement of sale. Our estimated cost calculations are based on the drawings/plans made available to us for the project under reference by the Developer /Consultants. The Schedule of items and quantity required for the entire work as calculated by Quantity Surveyor* appointed by Developer/Engineer, the assumption of the cost of material, labor and other inputs made by developer, and the site inspection carried out by us to ascertain / confirm the above analysis given to us. 3. We estimate Total Estimated Cost of completion of the aforesaid project under reference at Rs. 25,99,00,000/- (Total of Table A and B) at the time of The estimated Total, Cost of project is with reference to the Civil, MEP and Allied worksRegistration. required for completion of the apartments and proportionate completion of internal & external works, as per specifications mentioned in agreement of sale and for the purpose of obtaining occupation certificate/ completion certificate for the building(s) / Wing(s) /Layout /Plotted Developmeut lros the MCGM being the Planning Authority under whose jurisdiction the aforesaid projeçeis beingBmplemented. C.H.S.Ltd. CONS F ot re r a d :05 ir Dham ARER AUTHORISEDSIGNATORY O-03 ADD: 103,PRINCE PALACE, (JAYANTILAL VAISHNAV X LANE), KHOT LANE, GHATKOPAR (W), MUMBAI-400 086. PARASCONSULTANTS K. H. SHAH CONSULTING ENGINEERS B.E. (Civil) M.I.E. Regn. No. STR S/33 S/197 Mobile :98673 07061 / 62 E Mail: parasconsultants@yahoo.com Ref. No. Date : 4. The Estimated Cost Incurred till date is calculated at Rs. 11,43,61,054/- (Total of Table A nd B). The amount of Estimated Cost Incurred is calculated on the basis of input materials /services used and unit cost of these items. 5 The Balance Cost of Completion of the Civil, MEP and Allied works for completion of the apartments and proportionate completion of internal & external works, as per specifications mentioned in agreement of sale, of the Project is estimated at Rs. 14,55,38,946/-(Total of Table A and B). 6 Icertify that the Cost of the Civil, MEP and allied work for the apartments and proportionate internal on external works, as per specifications mentioned in agreement of sale, of the aforesaid Project as completed & the date of this certificate is as given in Table A and B below: TABLE A Building 1(To be prepared separately for each Building /Wing / Layout Plotted Development of the Real Estate Project) SR. NO. PARTICULARS AMOUNT (IN RS.) 1 Total Estimated Cost of the Building/ Wing/Layout 25,99,00,000/ Plotted Development as on date of Registration is 2 Cost incurred as on date of certificate 30.06.2024 11,43,61,054/ 3 Work done in Percentage (as Percentage of the estimated 44.00% cost) Balance Cost to he Incurred 14,55,38,946/ 4 (Based on Estimated Cost) C.H.S.Ltd. Mahsm 5 Cost Incurred on Additional/Extra items not included in the Negar Estimated Cost (Table -C) GarsdlaMEMBERAWtHORISEDNAON For TABLE B Internal &External Development Works in Respeetof the Registered Phase SR. NO. PARTICULARS AMOUNT (IN RS) Total Estimated Cost of the Internal and External Development Works including amenities and Facilities in the layout as on date of Registration is 2 Cost incurred as on date of certificate 3 Work done in Percentage (as Percentage of the cstimaAD: 103,PRINCE PALACE, (JAYANTILAL VAISHNAV XLANE), KHOT LANE, GHATKOPAR (W), MUMBA|-400 086. PARAS CONSULTANTS K. H.SHAH CONSULTING ENGINEERS B.E.(Civil) M.I.E. Regn. No. STRS/33 S/197 Mobile :98673 07061 / 62 E Mail: parasconsultants@yahoo.com Date - Ref. No. Agreed and accepted by Yours Faithfully, For Paras Consultant PARA K.H. SHAH BEMIE ARODIAWAGAR MUMBA CHARTCREDENGINEER Ltd M-19425 DhamC.HÐ Malhavir KH Shah Nogar Garodia sotay STR S/33 For AUTHORISED NOTE: MEMBER Restered Real Estate Project as per drawings approved 1. The scope of work is to complete from time to time and as per specifications mentioned in agreement of sale. independent 2. (*) Quantity survey can be done by office of Engineer or can be done by an Quantity Surveyor, whose certificate of quantity calculated can be relied upon by the Engineer. In case of independent quantity surveyor being appointed by Developer, the name has to be mentioned at the place marked (*) and in case quantity are being calculated by office of Engineer, the name of the person in the office of Engineer, who is responsible for the quantity calculated should he mentioned at the place marked (*). 3. (**)Balance Cost to be incurred (4) may vary from Difference between Total estimated Cost (1) and Actual Cost incurred (2) due to deviation in quantity required Iescalation of cost etc. As this is an estimated cost, any deviation in quantity required for development of the Real Estate Project will result in amendment of the cost incurred / to be incurred. 4. Allcomponents of work with specifications are indicative and not exhaustive. 5. Please specify if there are any deviations / qualifications. Example: Any deviations in input material used from specifications in agreement of sale. TABLE C List of Extra/Additional/Deleted Items considered in cost (which were not part of original Estimate of Total Cost) SR.NO LIST OF EXTRA/ADDITIONAL/DELETED ITEMS AMOUNT (IN RS) 1 ADD: 103,PRINCE PALACE, (JAYANTILAL VAIS HNAV XLANE), KHOT LANE, GHATKOPAR (W), MUMBAI-400 086.