SKYLINE _______________________________________________________________________ Annexure A FORM 1 ARCHITECT’S CERTIFICATE For a period of 01.03.25 to 31.03.25 To, Date: 21.04.2025. Shri Tarun R. Dave, Proprietor of M/s. Om Constructions. Gr. Floor, Hardik, 120’ Link Road, Kandar Pada, Dahisar (W), Mumbai – 68. Subject: Certificate of Percentage of Completion of Construction Work for development of Maruti Residency having MahaRERA Registration Number P51800052504 being developed by M/s. Om Constrcutions. Sir, I, Divyesh H. Parekh, have undertaken assignment as Licensed Surveyor of certifying Percentage of Completion of Construction Work of Maruti Residency having MahaRERA Registration Number P51800052504 being developed by M/s. Om Constrcutions. Based on Site Inspection, with respect to Layout / each of the Building/Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. TABLE-A Layout / Building / Wing Number (single building is proposed) Sr. Tasks / Activity Percentage of Actual Work Done No. (2) (As on 31.03.2025) (1) (3) 1. Excavation 100% Completed 2. Basements (if any) NA 3. Podiums (1) NA 4. Plinth 100% Completed _______________________________________________________________________________ 1105, SOLITAIRE BUSINESS CENTER, GULMOHAR ROAD, BORIVALI (W), MUMBAI - 92. EMAIL: DIVSPAREKH@GMAIL.COM PHONE: 98693 56657 5. Stilt Floor 100% Completed 6. Slabs of Super Structure 100% Completed 7. Internal walls, Internal Plaster, Floorings, 75% Completed Door and windows within Flats/Premises 8. Sanitary Fittings within the Flat/Premises 25% Completed 9. Staircases, Lifts Wells and Lobbies at each 100% Completed Floor level, Overhead and Underground Water Tanks 10. External plumbing and external plaster, 75% Completed elevation, completion of terraces with waterproofing of the Building/Wing. 11. Installation of Lifts, water pumps, Fire Fighting 25% Completed Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. TABLE-B Common Areas (Internal and External Development Works) in respect of the entire RegisteredPhase / Project Number Sr. Common areas andFacilities Proposed Percentage of Actual Details No (2) (Yes / No) Work Done (As on (5) (1) (3) 31.03.2025) (4) 1. Internal Roads & Footpaths. No --- 2. Water Supply Yes 25% Completed 3. Sewerage (Chamber, lines, No --- Septic Tank, STP). 4. Storm Water Drains Yes 0% Completed 5. Landscaping & Tree Planting No --- 6. Street Lighting No --- 7. Community Buildings No --- 8. Treatment and disposal of No --- sewage and sullage water. 9. Solid Waste management Yes 25% Completed and Disposal 10. Water conservation / Rain Yes 0% Completed water harvesting 11. Energy Management No --- 12. Fire protection and Fire Safety Yes 50% Completed requirements 13. Electrical meter room, sub No --- - station, receiving station. 14. Others (Option to Add No --- more). Yours faithfully, DIVYESH HARESH PAREKH 2025.04.21 12:15:43 +05'30' _________________________ Licensed Surveyor (DIVYESH H. PAREKH), (P/444/LS) Agreed and Accepted by: _________________________________ Shri Tarun R. Dave, Proprietor of M/s. Om Constructions. Date: 21.04.2025