Sandeep S. Shah Architect & Engineer G-6/C, Swapnalok Apt., Near Andheri Sub-way, Andheri (E), Mumbai – 400 069 Tel./Fax : 2834 7181 E-mail : ssaarch@rediffmail.com Annexure A FORM 1 [see Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: 21/04/2026 To, VISHAL CONSTRUCTION MUMBAI SUBURBAN, MAHARASHTRA, 400053 Subject : Certificate of percentage of Work of completion of construction work of BUILDING NO 2 AJMERA SHIKHAR having MahaRERA Registration Number P51800052488 (Only Applicable after project Registartion) being developed by VISHAL CONSTRUCTION Sir, I/We SANDEEP SHAH have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of completion of Construction Work of BUILDING NO 2 AJMERA SHIKHAR having MahaRERA Registration Number P51800052488 (Only Applicable after project Registration, being developed by VISHAL CONSTRUCTION ) Based on Site Inspection,with respect to Layout / each of the Building/Wing of the aforesaid Real Estate Project I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A Layout/Building/Wing Number: WING A/NA Sr. No. Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 0.00 2 Basements (if any) 0.00 3 Podiums (if any) 0.00 4 Plinth, 0.00 5 Stilt Floor 0.00 6 Slabs of Super Structure 0.00 7 Internal walls, Internal plaster, Floorings, Floors and windows within 0.00 Flats/Premises 8 Sanitary Fitting within the Flat/Premises 0.00 Sr. No. Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) 9 Staircases, lifts Wells and Lobbies at each Floor level Overhead and 0.00 Underground Water Tanks Page 1 of 3 Sandeep S. Shah Architect & Engineer G-6/C, Swapnalok Apt., Near Andheri Sub-way, Andheri (E), Mumbai – 400 069 Tel./Fax : 2834 7181 E-mail : ssaarch@rediffmail.com 10 External plumbing and external plaster, elevation, completion of terraces with 0.00 waterproofing of the Building/wing. 11 Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per 0.00 CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection,paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. Layout/Building/Wing Number: WING B/NA Sr. No. Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 0.00 2 Basements (if any) 0.00 3 Podiums (if any) 0.00 4 Plinth, 0.00 5 Stilt Floor 0.00 6 Slabs of Super Structure 0.00 7 Internal walls, Internal plaster, Floorings, Floors and windows within 0.00 Flats/Premises 8 Sanitary Fitting within the Flat/Premises 0.00 9 Staircases, lifts Wells and Lobbies at each Floor level Overhead and 0.00 Underground Water Tanks 10 External plumbing and external plaster, elevation, completion of terraces with 0.00 waterproofing of the Building/wing. 11 Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per 0.00 CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection,paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. Page 2 of 3 Sandeep S. Shah Architect & Engineer G-6/C, Swapnalok Apt., Near Andheri Sub-way, Andheri (E), Mumbai – 400 069 Tel./Fax : 2834 7181 E-mail : ssaarch@rediffmail.com Table B - Common Areas (Internal and External Development Works) in respect of Registered Phase / Project Number) Sr.No Common areas and facilities Is Available Percentage of Actual Details (Yes / No) Work Done (As on date of the Certificate) (1) (2) (3) (4) (5) 1 Internal Roads & Footpaths Yes 0.00 AS PER PLAN 2 Water Supply Yes 0.00 AS PER PLAN 3 Sewerage (Chamber, Lines, Septic Tank , STP) Yes 0.00 AS PER PLAN 4 Storm Water Drains Yes 0.00 AS PER PLAN 5 Landscaping & Tree Planting Yes 0.00 AS PER PLAN 6 Street Lighting Yes 0.00 AS PER PLAN 7 Community Buildings No 0.00 NA 8 Treatment And Disposal Of Sewage And Sullage Water Yes 0.00 AS PER PLAN 9 Solid Waste Management And Disposal Yes 0.00 AS PER PLAN 10 Water conservation /Rain water harvesting Yes 0.00 AS PER PLAN 11 Energy managemcnt Yes 0.00 AS PER PLAN 12 Fire protection and fire safety requirements Yes 0.00 AS PER PLAN 13 Electrical meter room, sub-station, receiving station Yes 0.00 AS PER PLAN 14 Aggregate area of recreational Open Space Yes 0.00 AS PER PLAN 15 Open Parking Yes 0.00 AS PER PLAN Yours Faithfully SANDEEP SHAH Signature & Name (IN BLOCK LETTERS) of L.S/ Architect ( License No: F-1173) Date of Certificate: Agreed and accepted by: Signature of Promoter Name: VISHAL CONSTRUCTION Date: Page 3 of 3