FORM 1 ARCHITECT’S CERTIFICATE Date: 15.10.2025 To, Shri. Arshad A. Lashkaria, Lashkaria Housing and Infrastructure Private Limited Lashkaria Anurag, 1st floor, J P. Road, Model Town, Four Bungalow, Near Versova Metro Station, Andheri (West), Mumbai 400 053. Sub :- Certificate of Percentage of Completion of Construction Work of Proposed Building on Property being developed by Lashkaria Housing and Infrastructure Private Limited (Developer) bearing all that piece and parcel of land bearing Plot bearing C.T.S No. 831/14 admeasuring 3187 square meters together with building standing thereon known as “INDRASUKH CHS LTD” situated at Village Ambivali, Taluka Andheri in the Registration District and Sub-District of Mumbai Suburban. Ref: - MCGM File No: CHE/WS/1745/K/W/337(NEW) Maha Rera Registration Number P51800052471. Sir, I, Kedar A Pathare (Proprietor of Ms. Envisions), have undertaken the assignment as Architect for certifying the Percentage of Completion of Construction Work of the Indrasukh CHS LTD building of the project bearing CTS No. 831/14 of Village Ambivali and (West), Mumbai in K/West Ward. Admeasuring 3187.00 Sq. mtrs together with the building standing thereon known as “INDRASUKH CHS LTD” situated at Revenue Village Andheri, Taluka Andheri in the Registration District and Sub-District of Mumbai Suburban, being developed by Lashkaria Housing and Infrastructure Private Limited. 12/13, GROUND FLOOR, ABHISHEK, OPP. SAB TV, OFF NEW LINK ROAD, ANDHERI (W), MUMBAI – 400 053. 1. Following technical professionals are appointed by Owner/Developer:–– (i) Kedar A Pathare (Proprietor of Ms. Envisions) as L.S. / Architect (ii) Mr. Furkan. M/s Frames as Structural Consultant (iii) Mr. Kamlesh Rajak, M/s Eco MEP as MEP Consultant Based on Site Inspection, with respect to each of the Building/Wing of the aforesaid Real Estate Project , I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project as registered vide number P51800052471 under Maha RERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in: TABLE - A Sr. Tasks/Activity Percentage no. of Work 1 Excavation 100% 2 Plinth 100% 3 Stilt Floor 90% 4 Ground floor shopping 100% 5 1st floor Shopping Unit 100% 6 3 No. of Podiums 90% 7 1 No. of the Amenity podium 50% 8 15 numbers of Slabs of Super Structure 90% 9 Internal Walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flats/Premises. Internal walls 90% Internal plaster 70% Flooring 50% Doors and Windows 60% 10 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 50% 11 Staircases, Lifts, Wells, and Lobbies at each Floor level connecting Staircases and 90% Lifts, Overhead and Underground Water Tanks. 12 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing. 13 External Plumbing 30% External Plaster 60% Elevation 40% Terraces with waterproofing 0% 14 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO 20% NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation / Completion Certificate. 12/13, GROUND FLOOR, ABHISHEK, OPP. SAB TV, OFF NEW LINK ROAD, ANDHERI (W), MUMBAI – 400 053. TABLE – B Internal and External Development Works in respect of the entire Registered Phase. Sr. Common areas and facilities Proposed Percentage of Details No. amenities (YES/NO) work done 1 Internal Roads & Footpaths N.A 2 Water Supply YES Will be provided as per norms. 3 Sewerage (chamber, YES Will be provided as Lines. per norms. 4 Stormwater Drains YES Will be provided as per norms. 5 Landscaping& YES Will be provided as Tree Planting. per norms. 6 Street Lighting N.A 7 Community Buildings N.A 8 Treatment and disposal of YES Will be provided as sewage and sullage water. per norms. 9 Solid Waste Management & YES Will be provided as Disposal. per norms. 10 Water conservation, Rainwater YES Will be provided as harvesting. per norms. 11 Energy management N.A 12 Fire protection and fire safety YES Will be provided as requirements. per norms. 13 Electrical meter room, sub- YES Will be provided as station, receiving station. per norms. 14 Others (Option to Add more). NIL Yours faithfully, Ar. Kedar A Pathare (PROPRIETOR M/S Envisions) (LICENSE NO CA/96/20562) 12/13, GROUND FLOOR, ABHISHEK, OPP. SAB TV, OFF NEW LINK ROAD, ANDHERI (W), MUMBAI – 400 053.