1103, OPAL SQUARE, S. G. BARVE MARG OPP. MIDC THANE, WAGLE ESTATE THANE (WEST)· 400 604. Landline : 022 2081 3369 e-mail : ss_associatesl@yahoo.co.in FORM 1 ARCHITECT'S CERTIFICATE (As on 30/09/2023) To Shraddha Prime Projects Limited, Ground Floor+ 1 st Floor, Manisha Heights Commercial Building, Vaishali Nagar,Mulund West, Mumbai - 400080 Subject: Certificate of Percentage of Completion of Construction Work of Composite Building of "SHRADDHA PALACIOUS" having MahaRERA Registration Number 'P51800052241' of plot located at CTS No 396, 396/ 1 to 59 of Village Kanjur, Bhandup (W), Taluka Kurla, Mumbai Suburban District, Mumbai - 400078, Maharashtra. being developed by M/s Shraddha Prime Projects Limited. Sir I M·,s. Sheetal Nikhare of M/s S. S. Associates have undertaken assignment of Architect of certifying percentage of completion of construction work of project known as "SHRADDHA PALACIOUS" having MahaRERA Registration Number 'P51800052241' of plot located at CTS No 396, 396/ 1 to 59 of Village Kanjur, Bhandup (W), Taluka Kurla, Mumbai Suburban District, Mumbai - 400078, Maharashtra. being developed by M/s -----,= -- Shra tl -h Prime Projects Limited. spection, with respect to Layout / each of the Building / Wing of the p ·oject, I certify that as on the date of this certificate, the Percentage of Work done for .ach of the building/wing of the real estate project under MahaRERA is as per T�le A herein below. The percentage of the work executed with respect to each of the activit_· of t}ie entire phase is detailed in Table 8. TABLE A REHAB BUILDING (WING - A) Sr. Tasks / Activity % of No Work 1,--;-______________ Done 1. E xcavation - ___,__ 000 1_ _ _A_o_.J 2. No Basement Only � 0% __j ___ 3. 0 Number of Pod'6 0% -/----------------------- 4. Stilt Floor 1103, OPAL SQUARE, S. G. BARVE MARG OPP. MIDCTHANE, WAGLE ESTATE THANE (WEST) - 400 604 Landline:022 2081 3369 S. ASSOCIATES e-mail : ss_associates1@yahoo.co.in 5. Plinth 100% 6. 23 Number of Slabs of Super Structure (22 Habitable Floors) 100% 7. Internal Walls, Internal Plaster, Flooring with Flat / Premises, Doors and 100% Windows to each of the Flat / Premises 8. Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat 100% /Premises 9. Staircases, Lifts Wells and Lobbies at Each Floor Level connecting staircases 100% and lifts, Overhead and Underground Water Tanks 10. The external plumbing and external plaster, elevation, completion of terraces 100% with waterproofing of the Building / Wing 11. Installation of Lifts, Water Pumps, Fire Fighting Fittings and Equipment as 100% per CFO NOC, Electrical Fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of Environment / CRZ NOC, Finishing to Entrance Lobby, Plinth Protection, Paving of Areas appurtenant to Building | Wing, Compound Wall and all other requirements as may be required to obtain Occupation /Completion Certificate. Any other activities. REHAB BUILDING (WING B) Sr. Tasks /Activity % of No Work Done 1. Excavation 100% 2 NoBasement Only 1Number of Plinth 0% 3. 0 Number of Podiums 0% 4 Stilt Floor 0% 5 Plinth 100% 19 Number of Slabs of Super Structure (18 Habitable Floors) 0% 7. Internal Walls, Internal Plaster, Flooring with Flat / Premises, Doors and 0% Windows to each of the Flat / Premises 8 Sanitary Fittings within the Flat/ Premises, Electrical Fittings within the Flat 0% /Premises 9. Staircases, Lifts Wells and Lobbies at Each Ploor Level connecting staircases 0% and lifts, Overhead and Underground Water Tanks 10. "The external plumbing ánd external plaster, elevation, completion of terraces 0% with waterproofing of the Building / Wing ASS AATE 1103, OPAL SQUARE, S. G. BARVE MARG OPP. MIDC THANE, WAGLE ESTATE THANE (WEST) - 400 604. Landline:022 2081 3369 ASSOCIATES e-mail : ss_associates1@yahoo.co. in 11, Installation of Lifts, Water Pumps, Fire Fighting Pittings and Equipment as 0% per CFO NOC, Electrical Fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of Environment/ CRZ NOC, Finishing to Entrance Lobby, Plinth Protection, Paving of Areas appurtenant to Building /Wing, Compound Wall and all other requirements as may be required to obtain Occupation / Completion Certificate. Any other activities. SALE WING-A SHRADDHA PALACIOUS" Sr. Tasks / Activity % of No Work Done 1. Excavation 40% 2. No Basement Only 1 Number of Plinth 0% 3. 6 Numbers of Part Podiums 0% 4. Stilt Floor 0% 5. Plinth O% 6 29 Number of Slabs of Super Structure (22 Habitable Floors) above Podium 0 % 7. Internal Walls, Internal Plaster, Flooring with Flat|Premises, Doors and Windows to each of the Flat / Premises 8. Sanitary Fittings within the Flat / Premises, Electrical Fittings within the Flat 0 % /Premises 9. Staircases, Liis Wells and Lobbies at Each Floor Level connecting staircases 0% and lifts, Overheaàd and Underground Water Tanks 10. The external plumbing and external plaster, elevation, completion of terraces 0% with waterproofing of he Building / Wing 11. Installation of Lifts, Wuter Pumps, Fire Fighting Fittings and Equipment as 0 % per CFO NOC, Electrical Fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of Environment / CRZ NOC, Finishing to Entrance Lobby, Plinth1 Protection, Paving of Areas appurtenant to Building / Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Complçtion Certificate. Any other activities. ASSO 1103, OPAL SQUARE, S. G. BARVE MARG OPP. MIDCTHANE, WAGLE ESTATE THANE (WEST) - 400 604. Landline: 022 2081 3369 S. S. ASSOCIATES e-mail : 5s_associates1@yahoo.co.in SALE WING - B "SHRADDHA PALACIOUS" Sr. Tasks / Activity % of No Work Done 1. Excavation 40% 2. NoBasement Only 1Number of Plinth 0% 3 6 Numbers of Part Podiums 0% 4. Stilt Floor 0% 5. Plinth O% 6. 29 Number of Slabs of Super Structure (22 Habitable Floors) above Podium 0 % 7. Internal Walls, Internal Plaster, Flooring with Flat / Premises, Doors and 0 % Windows to each of the Flat / Premises 8 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat 0 % Premises 9 Staircases, Lifts Wells and Lobbies at Each Floor Level connecting staircases 0 % and lifts, Overhead and Underground Water Tanks 10. The external plumbing and external plaster, elevation, completion of terraces 0 % with waterproofing of the Building / Wing 11. Installation of Lifts, Water Pumps, Fire Fighting Fittings and Equipment as 0 % per CFO NOC, Electrical Fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of Environment / CRZ NOC, Finishing to Entrance Lobby, Plinth Protection, Paving of Areas appurtenant to Building / Wing, Compound Wall and all other requirements as may be required to obtain Occupation / Completion Certificate. Any other activities. The percentage of work executed with respect to each of the major activity of the Building /Wing and Overall Percentage of work done with respect to each of the Building / Wing is detailed in Table B. TABLE B Internal& External Development Works in Respect of the entire Registered Phase Sr. Common Areas and Proposed Percentage Details No Facilities, Ainenities (Yes / No) of Work Done 1 Internal Roads & Footpaths Yes 0% Yes DEVELOPER 1103,OPAL SQUARE, S. G. BARVE MARG OPP. MIDC THANE, WAGLE ESTATE THANE (WEST) - 400 604. Landline: 022 2081 3369 S. ASSOCIATES e-mail : ss_associates1@yahoo.co.in 2 Water Supply Yes 0% NOC From MCGM & Built by Developer 3. Sewerage (Chamber Lines, Yes 0% Chamber Lines Septic Tank, STP) 4. Storm Water Drains Yes 0% NOC From MCGM & Built by Developer 5. Landscape & Tree Planting Yes 0% NOC From MCGM & Built by Developer 6. Street Lighting No NA NA 7. Community Buildings No NA NA 8. Treatment and Disposal of No 0% NA sewage and sullage water 9 Solid Waste Management & Yes 0% Provision made by Disposal Developer 10. Water Conservation, Rain Yes 0% Rain Water Harvesting to Water Harvesting be built by Developer 11. Energy Management Yes 0% Provided by Developer 12. Fire Protection & Fire SafetyYes 0% NOC From MCGM & Built Requirements by Developer 13. Electrical Meter Room, Sub- Yes 0% Electric Meter Room Only station, receiving station /Sub-station if required Thanking You, Yours Faithfulßy, ShEEPL NIKHARE FOR S.S. ASSOCIATES (CA/2003/3 1138) Agred and accepted by WS. SHiRADDHA PRIME PROJECTS LTD. Signature of Promoter Directór Name: Sudhir Mehta (Partner of M/s Shraddha Prime Projects Limited) Date: 30-09-2023