A S.ASSOCIATES 1103, OPAL SQUARE, S. G. BARVE MARG OPP. MIDC THANE, WAGLE ESTATE THANE (WEST) - 400 604 Landline: 022 2081 3369 e-mail : $s associates 1(@yahoo.co.in FORM 1 ARCHITECT'S CERTIFICATE Date: 03/07/2023 To Shraddha Prime Projects Limited, Ground Floor + 1st Floor, Manisha Heights Commercial Building, Vaishali Nagar, Mulund West, Mumbai -400080 Construction Work of Composite Subject: Certificate of Percentage of Completion of MahaRERA Registration Number Building of "SHRADDHA PALACIOUS" having Village Kanjur, Bhandup P5180005224 1' of plot located at CTS No 396, 396/1 to 59 of Mumbai 400078, Maharashtra. being (W), Taluka Kurla, Mumbai Suburban District, developed by M/s Shraddha Primne Projects Limited. Sir have undertaken assignment of Architect IMrs. Sheetal Nikhare of M/s S. S. Associates as of certifying percentage of completion of construction work of project known Registration Number P51800052241 of «SHRADDHA PALACIOUS" having MahaRERA Kanjur, Bhandup (W), Taluka Kurla, plot located at CTS No 396, 396/1 to 59 of Village Maharashtra. being developed by M/s Mumbai Suburban District, Mumbai - 400078, Shraddha Prime Projects Limited. each of the Building / Wing of Based on the Site Inspection, with respect to Layout / as on the date of this certificate, the the aforesaid real estate project, I certify that the real estate project under Percentage of Work done for each of the building/wing of percentage of the work executed with MahaRERA is as per Table A herein below. The phase is detailed in Table B. respect to each of the activity of the entire TABLE A REHAB BUILDING (WING A) % of Sr. Tasks / Activity Work No Done 100% 1 Excavation 0% 2. No Basement Only 1 Nuánber of Plinth 0% 3. ONumber of Podiums 100% 4 Stilt Floor CIATE 1103, OPAL SOUARE, S. G. BARVE MARG OPP. MIDC THANE, WAGLE ESTATE THANE (WEST) - 400 604. Landline:022 2081 3369 ASSOCIATES e-mail : ss_associates1@yahoo.co.in 100% 5 Plinth 100% (22 Habitable Floors) 6. 23 Number of Slabs of Super Structure / Premises, Doors and 100% 7. Internal Walls, Internal Plaster, Flooring with Flat Windows to each of the Flat/Premises Fittings within the Flat 100% 8 Sanitary Fittings within the Flat/Premises, Electrical /Premises Level connecting staircases 100% 9. Staircases, Lifts Wells and Lobbies at Each Floor and lifts, Overhead and Underground Water Tanks completion of"terraces 100% 10. The external plumbing and external plaster, elevation, with waterproofing of the Building / Wing as 100% 11. Installation of Lifts, Water Pumps, Fire Fighting Fittings and Equipment Common Areas, electro, mechanical per CFO NOC, Electrical Fittings to CRZ NOC, Finishing equipment, Comnpliance to conditions of Environment / appurtenant to Building to Entrance Lobby, Plinth Protection, Paving of Areas be required to /Wing, Compound Wall and all other requirements as may activities. obtain Occupation/Completion Certificate. Any other REHAB BUILDING (WING B) % of Sr. Tasks / Activity Work No Done 100% 1. Excavation 0% 2. No Basement Only 1Number of Plinth 0% 3. 0 Number of Podiums 0% 4. Stilt Floor 100% 5 Plinth Floors) 0% 6. 19 Number of Slabs of Super Structure (18 Habitable Premises, Doors and 0% 7. Internal Walls, Internal Plaster, Flooring with Flat / Windows to each of the Flat / Premises 0% 8 Sanitary Fittingswithin the Flat / Premises, Electrical Fittings within the Flat /Premises Staircases, Lifts Wells and Lobbies at Each Floor Level connecting staircases 0% 9 and lifts, Overhead and Jndrground Water Tanks of terraces 0% 10. The external plåmbing and external plaster, elevation, completion with waterproofing of the Building/ Wing 1103, OPAL SQUARE, S. G., BARVE MARG OPP. MIDC THANE, WAGLE ESTATE THANE (WEST)- 400 604. Landline: 022 2081 3369 S. S. ASSOCIATES e-mail :ss_associates 1@yaho0.co.in Installation of Lifts, Water Pumps, Fire Fighting Fittings and Equipment as 0% 11. per CFO NOC, Electrical Fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of Environment / CRZ NOC, Finishing to Entrance Lobby, Plinth Protection, Paving of Areas appurtenant to Building /Wing, Compound Wall and all other requirements as may be required to obtain Occupation / Completion Certificate. Any other activities. SALE WING-A SHRADDHA PALACIOUS" % of. Sr. Tasks / Activity Work No Done Excavation 30% 1. No Basement Only 1 Number of Plinth 0% 2. 6 Numbers of Part Podiums 0% 3. 0% 4. Stilt Floor 5. Plinth O% 29 Number of Slabs of Super Structure (22 Habitable Floors) above Podium O% 6. 7. Internal Walls, Internal Plaster, Flooring with Flat / Premises, Doors and O% Windows to each of the Flat / Premises 8. Sanitary Fittings within the Flat /Premises, Electrical Fittings within the Flat 0 % /Premises Staircases, Lifls Wells and Lobbies at Each Floor Level connecting staircases 0 % 9. and lifts, Overhead and Underground Water Tanks 10. The external plumbing and external plaster, elevation, completion ofterraces O% with waterproofing of the Building / Wing Installation of Lifts, Water Pumps, Fire Fighting Fittings and Equipment as 0 % 11. per CFO NOC, Electrical Fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of Environment / CRZ NOC, Finishing to Entrance Lobby, Plinth Protection, Paving of Areas appurtenant to Building | Wing, Compound Wall and all other requirements as may be required to obtain Occupation / Completion Certificate. Any other activities. 1103, OPAL SQUARE, S. G. BARVE MARG OPP. MIDCTHANE, WAGLE ESTATE THANE (WEST) - 400 604. Landline :022 2081 3369 ASSOCIATES e-mail: Ss_associates1@yahoo.co.in SALE WING - B "SHRADDHA PALACIOUS" of Sr. Tasks / Activity Work No Done 30% 1 Excavation 0% 2. No Basement Only 1Number of Plinth 0% 3 6 Numbers of Part Podiums 0% 4 Stilt Floor 0% 5. Plinth above Podium O% 6 29 Number of Slabs of Super Structure (22 Habitable Floors) Internal Walls, Internal Plaster, Flooring with Flat / Premises, Doors and 0% 7. Windows to each of the Flat/Premises the Flat 0 % 8. Sanitary Fittings within the Flat / Premises, Electrical Fittings within /Premises Staircases, Lifts Wells and Lobbies at Each Floor Level connecting staircases 0 % 9. and lifts, Overhead and Underground Water Tanks The external plumbing and external plaster, elevation, completion of terraces 0 % 10. with waterproofing of the Building / Wing Installation of Lifts, Water Pumps, Fire Fighting Fittings and Equipment as O% 11. mechanical per CFO NOC, Electrical Fittngs to Common Areas, electro, equipment, Compliance to conditions of Environment/ CRZ NOC, Finishing to Entrance Lobby, Plinth Protection, Paving of Areas appurtenant to Building / Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate. Any other activities. The percentage of work executed with respect to cach of the major activity of the Building /Wing and Overall Percentage of work done with respect to each of the Building/ Wing is detailed in Table B. TABLEB Internal & External Development Works in Respect of the entire Registered Phase Sr. Common Arcas and Proposed Percentage Detalls No Facilities, Amenities (Yes / No) of Work Done Yes DEVELOPER 1 Internal Roads &Footpaths Yes 0% ASSO 1103, OPAL SQUARE, S. G. BARVE MARG OPP. MIDC THANE, WAGLE ESTATE THANE (WEST) -400 604. Landline: 022 2081 3369 S. S. ASSOCIATES e-mail : Ss_associates1@yahoo.co.in 2. Water Supply Yes 0% NOC From MCGM & Built by Developer 3. Sewerage (Chamber Lines, Yes 0% Chamber Lines Septic Tank, STP) 4. Storm Water Drains Yes 0% NOC From MCGM & Built by Developer 5. Landscape & Tree Planting Yes 0% NOC From MCGM & Built by Developer 6. Street Lighting No NA NA 7. Community Buildings No NA NA 8. Treatment and Disposal of No 0% NA sewage and sullage water 9. Solid Waste Management & Yes 0% Provision made by Disposal Developer 10. Water Conservation, Rain Yes 0% Rain Water Harvesting to Water Harvesting be built by Developer 11. Energy Management Yes 0% Provided by Developer 12. Fire Protection & Fire Safety Yes 0% NOC From MCGM & Built Requirements by Developer 13. Electrical Meter Room, Sub- Yes 0% Electric Meter Room Only station, receiving station /Séb-station if required Thanking You, Yours Faithfully, A NIKHRE FORS. ASSOCTES, (CA/2003/31 138) Agreed and accepted by MS. SHIRADDHA PRILE PROJECTS LTD. Signature of Promoter Director Name: Sudhir Mehta (Partne of M/sShraddha Prime Projects Limited) Date: 03-07-2023