FORM-1 ARCHITECT'S CERTIFICATE Date: 30/06/2023 To, Shri. Bhupesh J Govani Director of Shubhjivan Builders Private Limited CA to Owner, 302 Goyal Shopping Arcade, S.V. Road. Borivali(W), Mumbai.400092 Subject: Certificate of percentage of co mpletion of Construction work of Development of “SIANNA HEIGHTS” for Construction of ONE Building of the SINGLE Phase Having Rera Registration Number P51800052192 situated on the Land bearing CTS. NO. 913/A&B, 914/A&B, 915/A&B, 917 demarcated by its bounda ries (latitude and longitude of the end points) 19. 25054,72.84913 to the North 19.25013,72.84901 to the South 19.25032,72.84926 to the East 19. 25042,72. 84888 to the West of T.P.S.III, Village Eksar, Borivali (W), Mumbai. Admeasuring about 2265.20 Sq. Mtrs. Area being developed by Shri. Bhupesh J Govani Director of Shubhjivan Builders Private Limited CA to Owner Sir, We Arch. Sarita S. Manjunath of M/S. Ashok Gandhi consultants LLP have undertaken assignment as Licensed Architect of certifying Percentage of Completion of Construction Work of the Project “ SIANNA HEIGHTS ” situated on the Land bearing CTS.NO. 913/A&B, 914/A&B, 915/A&B, 917 demarc ated by its boundaries ( latitude an d longitude of the end points) 19.25054,72.84913 to the North 19.25013,72.84901 to the South 19.25032,72.84926 to the East 19.25042,72. 84888 to the West of Village Eksar, I.C. Colony, Borivali(W), Mumbai, admeasuring about 2265.20 Sq. Mtrs. Area being developed by Shri. Bhupesh J Govani Director of Shubhjivan Builders Private Limited CA to Owner Following technical professionals as informed are appointed by Owner/Promoter: - i. Arch. Sarita S. Manjunath of M/S. Ashok Gandhi Consultants LLP as Licensed Architect ii. Shri Kaivant C. Shah. Consultants as Structural Consultant iii. M/s. / Shri / Smt. -- N. A, -- MEP Consultant iv. Shri Mangesh S. Deorukhakar as Site Supervisor on site. 1 Based on Site Inspection, with respect to the Building of the aforesaid Real Estate Project, I certify that as on 30/06/2023 of this certificate, the percentage of work done for the building of the Real Estate Project to be registered valid Rera registration Number P51800052192 applied for as “ SIANNA HEIGHTS ” under Maha RERA is as per 'Table A' herein below. The percentage of the work executed with respect to each o f the activity of the entire phase is detailed in the 'Table B'. Table A Building – (Project / Building Name) Sr. Task/Activity Percentage of No. work done 1. Excavation 100 % 2. Plinth 100 % 3. 3 Nos of Number of Podiums 20 % 4. Stilt on Ground Floor 20 % 5. 23 Number of Slabs of Super structure 30 % including podium slabs and terrace 6. Internal Walls, Internal Plaster, Flooring within Flats / Premises, Doors and Window 0 % to each of the Flat / Premises 7. Sanitary Fitting within t he Flat/Premises, 0 % Electrical Fitting within the Flat/Premises 8. Staircase, Lifts Wells and Lobbies at each Floor level connecting staircases and Lifts, 0 % overhead and underground water tanks 9. The External Plumbing and external plaster, elevation, completion of terraces with 0 % water proofing of the Building/wing, 10. Installation of Lifts, water pumps, Fire fighting fitting and Equipment as per CFO 0% NOC, Electrical fitting to common areas, electro, Mechanical Equipment, compliance to conditions of environment/CRZ NOC, Finishing to entrance Lobby/s Plinth Protection, paving of areas appurtenant to Building/Wing Compound Wall and all other requirement as may be required to obtain Occupation/Completion certificate. Note: Percentage of work done stated is a s per approved amended plan dated 02/02/2023 2 TABLE – B Internal & External Develop ment work in respect of the entire Registered Phase Percent S. Common areas and Proposed age of Details No. Facilities, Amenities (Yes/No) Work done Internal Roads and 0% 1. NO Footpaths 2. Water Supply YES 0% FROM MCGM Sewerage 0% 3. (chamber, lines, YES septic Tank, STP) 4. Storm Water Drains YES 0% AS PER REMARKS Landscaping and 0% 5. YES AS PER REMARKS Tree Planting 6. Street Ligh ting NO 0% 7. Community Buildings NO 0% Treatment and 0% 8. disposal of sewage NO and sullage water Solid Waste 0% 9. management & YES Disposal Water conservation, 0% 10. Rain water YES AS PER REMARKS harvesting 11. Energy Management NO 0% Fire protection a nd 0% AS PER CFO 12. fire safety YES REMARKS requirements Electrical meter 0% 13. room, sub-station, YES receiving station Others (option to 0% 14. add more) Note: Percentage of work done stated is as per approved amended plan dated 02/02/2023 Yours Sincerely, SARITA Digitally signed by SARITA SATISH SATISH MANJUNATH Date: 2023.08.09 MANJUNATH 14:28:48 +05'30' For, SARITA S. MANJUNATH, ASHOK GANDHI CONSULTANT LLP 3