trENtrRETE ENGINEERS/PROJECT MANAGEMENT trtrNtrEPTEi CDNSULTANTS 233, NEw lsLAMpuRA, BAR| EoMPouNo, BHrwANor, DrsTRrtrT THANE - 42'l 3rl2. E-MArL: concreteconcepts@rediffmail.com Job No.467 Date: 16 June2026 Annexure - C FORM-2A [see MahaRERA order no.S of 2018] ENGINEER'S CERTIFICATE FOR QUALITY ASSURANCE ' (Site Supervisor's Certificate) (Certificate No.4 for the year ending 2023-2024) To, M/s. Landmark Heights Pvt. Ltd. Shop No.6, B-17, SaiVaishali CHS. Ltd., Vaishali Nagar, Jogeshwari (W), Mumbai -400102 Subject: Certificate of Approximate of Completion of Construction work of of Project [Maha RERA Registration Number P51800024289 situated on the Plot bearing C.T.S. No. 169,169/1 to 4 of Village Majas, R.R. Thakur Road, Jogeshwari (E), Mumbai- 400060 and demarcated by its boundaries by 13.00 mt. Road to the North, C.T.S. No. 166 to the South, C.T.S. No. 168 to the East & C.T.S. No. 170 & 171 to the West of Village Majas, taluka Andheri, District Mumbai PIN - 400 060 admeasuring2490.49 sq. mts. Area being developed by M/s. Landmark Heights Private Limited. I, the undersigned FAZAL M. MOMIN, site licensed supervisor of above project request you for a Architect Certificate. The work completed on site is as below, Table A Percentage o work done Sr. No Tasks /Activity 1 Excavation 100% 2 Zero nwmber of Basement(s) and One number of Plinth' 1000/, 3 NIL Number of Podiums N.A 4 Stilt Floor N.A 5 5 numbers of Slabs of Super Structure 20% 6 Internal walls, Internal Plaster within flats/premises, Flo Doors and Windows to each of the Flat/premises 7.00% 7 Sani tary Fittings within the Flat/premises, Electrical Fittings within the Flat/Premises 0.00 % Staircases, Lifts Wells and tobbies at each Floor level connecti Staircase and Lifts, Overhead and Underground Water Tanks 8 6 00% Extemal plumbing and external plaster, Elevation, Completior terraces with waterproofing ofthe Building 9 0.00% Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical flttings to Common Ar< electro, mechanical equipment, compliance to conditions of environment/CRz NOC, Finishing to entrance tobby/s, plint protection, paving of areas appurtenant to the Building, 10 Compound Wall and all other requirements as may be requirer 0.00 % Obtain Occupation / Completion Ceftiflcate. TABLE.B Internal & External Development Works in Respect of the entire Reeistered phase Percentage o Sr. Nc Common areas Proposed Work done Details ald Facilities, Amenities (Yes/No) 1 Internal Roads & Footpaths No O%o NA 2 Water Supply Yes o.k Sewarage Yes o% (chamber lines, Septic Tank , STP) 4 Storm Water Drains Yes ooh 5 Landscaping & Tree Planting Yes OYo 6 Street Lighting No OYo NA 7 Community Buildings No oo NA Treatment and disposal of 8. sewage No OYo NA Solid Waste management & 9 Yes ov. Disposal Water conservation, Rain wa1 10. harvesting Yes ov. 11. Enerry management No O"/o NA Fire protection and flre safetJ t2. requirements Yes Oo/" Electrical meter room, sub- ,|? Yes OYo station, receiving station 74. Others (Option to Add more) No o t 5 ( 7 0. z o c. JH Thanking You Yours Faithfully, For, CONCRETE CONCEPTS Fazal oigirarryrgned by raza Mushtaque #,'j'j,1T#:T- Momin r2io:as+o5ro FAZAL M. MOMIN Licence No. M/388/SS-II + tvai|,nll- 3 t\ Pvt. Ltd for I