PRIYANK BHATT ^A,FTCHTTEGTS FORM 1 ARCHITECT'S CERTIFICATB Date: - 3l/05/2026 To IW s. Landmark Heights Private Limited Shop No. 06, Said Vaishali CHSL, Vaishali Nagar, Jogeshwari West, Mumbai-4OO 102. Subject: Certificate of Percentage of Completion of construction work of Building 8f nroject [Maha RERA Resistration nuniber-P518000242891 situated on the Plot bearing C.T.S. No. 169,169/ 1 to 4 of Village Majas, R.R. Thakur Road, Jogeshwari (E), Mumbai- 400060 and demarcated by its boundaries by 13.00 mt. Road to the North, C.T.S. No. 166 to the South, C.T.S. No. 168 to the East & C.T.S. No. 170 A l7l to the West of Village Majas, taluka Andheri, District Mumbai PIN - 400 060 admeasuring249o.49 sq. mts. Area being developed by M/ s. Landmark Heights Private Limited. Sir, I Mr. Priyank Bhatt have undertaken assignment as Architect of certifoing Percentage of Completion of Construction Work of the "Vraj Bhumi Heights" of the Project,situatedontheplotbearingC.T.S. No. 169,169/ I to4ofVillageMajas, R.R.Thakur Road, Jogeshwari (E), Mumbai - 400060 admeasuring 2490.49 sq. mts. Area being developec;I by [M/s. Landmark Heights'Private Limited] l. Following Technical Professionals are appointed by the Promoter: - (D MT. PRIYANK BHATT Architect (iD MT. FURKHAN PETTIWALA Structural Consultant (iii) Mr. FAZAL M. MOMIN Site Supervisor Based on Site Inspection, with respect to the building of the aforesaid Real Estate Project, I certiSr that as on the date of this certificate, the Percentage of Work done for the building of the Real Estate Project to be registered number P51800024289 under MahaRERA is as per. table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. o * pbO10416@9mait.com 2021A- Shiv Prisha CHSL, Junction of Gulmohar +91-22-26255400 Road priyangT8@gmail.com & Juhu Lane, JVpD Scheme, Vile parle (W), Mumbai_400049. PRIYANK BHATT AFTGHITECTS Table A Sr. No Tasks /Activity Percentage of work done (As of 31.o3-2021) I Excavation 350/, 2 Zero number of Basement(s) and One number of PIinth' Oo/o 3 NIL Number of Podiums N.A. 4 Stilt Floor N.A. 5 Zero numbers of Slabs of Super Structure 0% Internal walls, Internal Plaster within flats/ Premises, o Floorings, Doors and Windows to each of the Flat/Premises Oo/o 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings 0o/o within the Flat/Premises Staircases, Lifts Wells and Lobbies at each Floor level B connecting Staircase and Lifts, Overhead and Underground 0o/o Water Tanks External plumbing and external_ plaster, Elevation, 9 Completion of terraces with waterproofing of the 0% building Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, compliance to conditions of environment/CRz NOC, Finishing to entrance l0 lobby/ s, plinth protection, paving of areas appurtenant to the o% Building, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate. PVT 19 .t * J, {-1 2 pbO10a16@9mail.com 2O2lA- Shiv Prisha CHSL, Junction of Gulmohar Road +91-22-26255400 priyangTS@gmail.com & Juhu Lane, JVPD Scheme, Vile Parle (W), Mumbai-400049' TABLE-B PRIYANK BHATT ^A.FRGHITEGTS I Internal & External Develonment Works in Respect of the entire Resistered Phase Sr. Common areas Proposed Percentage Details No and Facilities, Amenities (Yes/No) of Work done (As of 31.O3.2021) 1 Internal Roads & Footpaths No 0u NA 2 Water Supply Yes 0% J Sewarage Yes 0? (chamber lines, Septic Tank, STP) 4. Storm Water Drains Yes 03 5. Landscaping & Tree Planting Yes 0? 6 Street Lighting No 08 NA l Community Buildings No 0? NA 8 Treatment and disposal of sewage No NA 0% and sullage water 9 Solid Waste management & Yes 0% Disposal 10. Water conservation, Rain water Yes 0? harvesting 11. Energy management No 0? NA 12. Fire protection and fire safety Yes 0? requirements 13. Electrical meter room, Yes 0? sub-station, receiving station t4 Others (Option to Add more) No The above Certificate is issued as per the approved concessions / plans for building under reference as per DCPR 2034 & is correct to the best of my knowledge as per the details provided by our client. Thanking You. For ndmark Ltd Yours Faithfully, Ar ank Bha tt (Lie.No. CAD 003/3 923) 3 pbO10416@gmait.com +e1-22-262ss4oo 2021A- Shiv Prisha CHSL, Junction of Gulmohar LI priyangTS@gmail.com Road & Juhu Lane, JVpD Scheme, Vile parle (W), Mumbai_400049.