Form 1 ARCHITECT'S CERTIFICATE Date: 11th October 2021 To, Shri Chirag M. Shah, M/s. Disha Construction 201, Square One, Gulmohar Road, Juhu, Mumbai - 400 049. Subject: Certificate of Percentage of Completion of Construction Work of residential Building comprising of 9 Wings (Wing A to Wing I) of the Project Proposed Redevelopment of Dattaramanand Co-op. Hsg. Soc. Ltd. registered under MahaRERA vide Registration No. P51800001236 situated on the C.T.S. No. 717 & 717/1 to 51 of Village Vile Parle at Hanuman Cross Road No. 2, Vile Parle (East), Mumbai, demarcated by its boundaries By C.T.S. No. 716 to the North, By C.T.S. No. 718 to the South, By C.T.S. No.s 707(Pt.), 708, 709, 710, 711 & 712 to the East, By C.T.S. No. 724/9, Existing Road, C.T.S. No.s 724, 725/13, 725 & 729(Pt.) to the West of Konkan Division, Village Vile Parle, Taluka Andheri, District Mumbai Suburban, PIN 400057, admeasuring 4474.00 Sq. Mts. area being developed by M/s. Disha Construction, Mumbai. Sir, I, Mr. Ashish R. Solanki, have undertaken assignment as Architect of certifying Percentage of Completion of Construction Work of Residential Building comprising of 9 Wings (Wing A to Wing I) of the project Proposed Redevelopment of Dattaramanand Co-op. Hsg. Soc. Ltd. situated on the plot bearing C.T.S. No. 717 & 717/1 to 51 of Konkan Division, Village Vile Parle, Taluka Andheri, District Mumbai Suburban, PIN 400057, admeasuring 4474.00 Sq. Mts. area being developed by M/s. Disha Construction, Mumbai. Now, Developer is proposing additional Flats on Ground Floor, so percentage of work completed is considered as per Revised work. Following technical professionals are appointed by Promoter:- (i) Mr. Premal K. Gogri as Architect; (ii) Mr. Sunil R. Shah as Structural Consultant; (iii) Mr. Hitesh R. Solanki as Site Supervisor Based on Site Inspection, with respect to the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the Wings of the Real Estate Project registered under MahaRERA vide Registration No. P51800001236 is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A (Wing A to Wing I) Sr. No. Tasks / Activity Percentage of work done 1 Excavation 100% 2 1 number of Basement(s) and Plinth 100% 3 Ground Floor 100% 4 6 number of Slabs of Super Structure 100% 5 Internal walls, internal Plaster, 100% Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 6 Sanitary Fittings within the Flat/Premises, 100% Electrical Fittings within the Flat/Premises 7 Stair cases, Lift Wells and Lobbies at each 100% Floor level connecting Stair cases and Lifts, Overhead and Underground Water Tanks 8 The external plumbing and external plaster, 100% Elevation, completion of terraces with water Proofing of the Building/ Wing, 9 Installation of lifts, water pumps, Fire Fighting 100% Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/ Wing, Compound Wall and all other requirements as may be required to Obtain Occupation / Completion Certificate TABLE B Internal & External Development Works in Respect of the entire project S. Common areas and Proposed Percentage of Details No. Facilities, Amenities ( Yes / No ) work done 1 Internal Roads & Footpaths No NA 2 Water Supply Yes 100% On completion of the building 3 Sewarage (chamber, lines, Yes 100% Internal Chambers SepticTank, STP) and lines proposed. No STP Proposed. 4 Strom water drains Yes 100% Will be connected to Municipal Storm Water Drain. 5 Landscaping & Tree Yes 100% As per Tree NOC. planting 6 Street Lighting No NA 7 Community Buildings No NA 8 Treatment and disposal of No NA sewage and sewage water 9 Solid waste management & Yes 100% Vermiculture Bin will disposal be provided as per requirement by MCGM. 10 Water conservation, Rain Yes 100% Recharge pit water harvesting proposed. 11 Energy Management No NA 12 Fire Protection and fire Yes 100% As per CFO NOC. safety requirements 13 Electrical meter room, sub Yes 100% As per requirement station by Reliance Energy. Yours Faithfully, For AASHISH SOLANKI a r c h i t e c t s Ashish Digitally signed by Ashish Ramniklal Solanki DN: c=IN, o=Personal, title=6402, pseudonym=fdd5b36b8123605b6663 Ramnikla ba56bda22dc06e7bc0a0153b7fadbb43 5284aa31985a, postalCode=400057, st=Maharashtra, serialNumber=9db82c5cd99a333ad65 l Solanki b652b476ba6df1c16ce7b0f3170528b2 ebe341207558f, cn=Ashish Ramniklal Solanki Date: 2021.10.11 13:15:29 +05'30' Ashish R. Solanki (CA/2000/26252)