1103, OPAL SQUARE, S. G. BARVE M ARG OPP. M IDC THAN E, WAG LE ESTATE THANE (WEST) 400 604. Land ine : 022 2081 3369 _associatesl@Yahoo.co.in FORM 1 ARCH ITECT'S CERTIFICATE Date: - 30 /06 /2024 To, M/s. Adhikarl Engineering PVT Ltd, 435, Avior, LBS Road, Opp Johnson & Johnson, :.. Mulund (W), Mumbai - 4OO Oa1. Subject:Certificate of Percentage of Cornpletion of Construction Work of proposed building Known as "Maharashtra Mandirrt cornprising of the project situated on the plot bearing C.T.S. No. 2314. (pt), 234,234(I to 14), 235, 235(1 to 61, 236, 236(I to 7), 1331, 1331 (1 to 10) of..Shree canpat Malt SRA CHSL" demarcated by its boundaries of North, adjoining slurn, Sorrth 13.4O rn wide existing road, Dast 27.45rn w.ide D.P. road, West adjoining Nalla, of Village Kanjur, .Taluka Kurla, Mttrnbai. Adrneasuring 1640.16 Sq. Mtrs. plot area being devcloped by M/s. Adhikari Engineerlng PVT Ltd. Sir, We, S. S. Associates have undertaken assignrnent as Architect of certifying Percentage of Completion of Construction Work of the proposed building Known as "Maharastrtra Mandir" Cornpositd building situated on the plot bearing, C.T.S. No. 231A (pt), 23a, 234(I to I4l, 235,235(1 to 61, 236,236(1 to 71, 1337, 1331 (1 to 10) of ..Strree Ganpat Malt SRA CHS" Village Kr:njur, Taluka Kr:rla, Mr.rrnbai. Adrneasuring 168O.16 Sq. Mtrs. plot area being developed by M/s. Adhikari Engineering p\/T Ltd, having registered office at M/s. Adhikari Engineering p\/T Ltd, 435, Awior, LBS Road, Opp JohnSon & Johnson, Mulund (V/), Murnbai - 400 080. Following technical professionals are appointed by Prornoter: - (i) S.S: Associates a-s Architect. (ii) M/s. Nexus Project Solution Pvt. Ltd. as Structlrral Consultant. (iii) M/s. Nexus Project Solution Pvt. I,td. as MEp consultant. (iv) M/s..Nexus Project Solution Flvt. Ltd. as Qualtity Surveyor. Based on Site lnspection, with respect to each o f the Building/Wing of the aJorcsaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for the building of the Real Estate Project is as per table A herein below. Ttre percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. - 1103, OPAL SQUARE, S. G. BARVE MARG OPP MIDC THANE, WAGLE ESTATE rHANE (WEST) - 400 604. Landline:022 20813369 _associatesl@Yahoo.co.in TABLE_A (Composite Brrilding) Sr. Taslis / Activity neretage of vork No. (2) done (1) /\ ]r (3) 1. Excavaticn IAO o/o 2. Plinth IOO o/o 3. Fodir:rrrs N.A +. 1 Stilt floor N.A" J. 23 nurnber of Slabs of Super -Structure LOO o/o 6. Internal Walls, Internal Plaster, Floorifrgs @Yo within Flats/Premises, Doors and Windows to eadr of th-e Flat /Prernises Sanitary Fittings- within the fJ"/o Flat /Prernises, Electrical Fittings within the Flat /Prernises. 8. Staircases, Lifts Wells and Lobbes at each 7OO o/o Floor level connecting Staircases anrd Lifts, l*rerhead and undergrorrnd Water Tanks 9.-------- The \ external plurnbing and external 75 o/o dgst er,\evatior! corrpletiorr of terraces witl. 'rvatbrorooflns of the Eh:ildinq /lr)lEne. 10. hstallaliqn of\ifts, water 1rtnrps, Fke FiehtinC ffio/o Fittir€s dqd 'Eeuiprnert as per CFO NOC, Eectrical fi\tings\..'' to Oornrrpn Areas, electro, rneftanical edqifr\nt" Oorrpliane to corrdi- tions of 'environrrsr\/Cs NOC, finishing errtrance .lobty/s, plinth\ prb, tectior, paving"toof areas errrn rrtenanf to Thrildlne' / Wne'- Cnrrrrrnrnd Wall ard all otlrer reqljrerherrts asi m€ry be reqrired to obtiin Occtmtiori / Cornrletion Certificate. A 1103, OPAL SQUARE, S, G. BARVE MARG OPP IMIDC THANE, WAGLE ESTATE THAN E (WEST) - 400 604. tandline : 022 2081 3369 e-mail : ss associatesl@yahoo.co.in TABLE - B fnternal and External Development Works in respect of the entire Registered Phase. Proposed Percentage Details Sr.No Common areas and Facilities (Yes/No) of work (1) Amenities (3) done (s) (21 ftl 1. Internal Roads & Footh- paths. No -\\ N.A N.A 2. Water Supplv Yes 5001 MCGM Sewerage (Chamber,lines,Septic Tanl, Yes LOYo MCGM STP) 4. Storm Water Drains Yes 4Oo/o Developer 5. Landscaping&Tree Plantins. No N.A N.A 6. Street Lislatins No N.A N.A Community Buildines No N.A N.A R Tieatment . and disposal of No N.A N.A sewage and sullage water. 9. Solid Waste management & No N,A N.A Disposal 10. Water conservation Rain water .Yes 2OVo Developer harvesting '.- 11. Enerqy managernent No N.A N.A 72. Fire protection and fire safety Yes 6OVo Developer reouirernents 13. Electrical 'meter room, sub- Yes 8Oo/o ' Developer station, receivine station. 14.-----..- Purnp Room Yes lOOo/o Developer t""^\:nt;u\ ,-."w\' s\ryl, NrnH\ FOR)g S. ASSOCT (cA/2oo3l31138) Agread And Accepl Z.r' "/ -4/n' S^tur" of Promr :- M/s. Adhl E+gin e e rltrg PVT Ltd ' Farrle Date :- 30/06/2O2t