CONSULTING ARCHITECT’S CERTIFICATE Date: 31-12-2023 To, MR. DHRUVA MAHENDRA RATHOD AUM CREATORS. Rustomjee Elanza, A/3301, 33rd floor, Chincholi Bundar Road, Next to Inorbit Mall, Malad (west), Mumbai-400064. Subject: Certificate of Percentage of Completion of Construction work of SHRISHTI Residential Building Project [ MAHA RERA No –P51800023092] situated on the Plot bearing, Plot No. 358/A & CTS No. 370E at 14th Road, Khar (west) of village Bandra, Mumbai- 400052, demarcated by its boundaries NORTH-WEST N19 O 04’09.17851”(lat.) E72 O 49’58.72437”(long.) , NORTH-EAST N19 O04’09.15411”(lat.) O O O E72 49’59.69995”(long.) , SOUTH-EAST N19 04’08.54848”(lat.) E72 49’59.62793”(long.) SOUTH-WEST N19 O 04’08.57740(lat.). E72O 49’58.70240” (long.). Admeasuring 548.40 sq.mts. Area being developed by AUM CREATORS. Sir, I UDAY KANADIA have undertaken assignment of Architect of certifying Percentage of Completion of Construction Work of SHRISHTI Building Project, situated on the plot bearing Plot No. 358/A & C.T.S No. 370E at 14th Road, Khar (west) of village Bandra, Mumbai- 400052, Admeasuring 548.40 sq.mts Area being developed by AUM CREATORS. Following technical professionals are appointed by Owner/ Promoter i. Shri UDAY KANADIA as Consulting Architect ii. Shri JAYANT INAMDAR as Structural Consultant iii. Shri S A R F A R A Z AMBROISA DESIGN as MEP Consultant iv. Shri AMIT NAIK as Site Supervisor Based on Site Inspection, with respect to each of the Building/Wing of the aforesaid Real Estate Project, I certify that as on the date this certificate, the Percentage of Work done for each of the building/ Wing of the Real Estate Project as registered vide number [applied for Maha RERA number] under Maha RERA is as per table A herein below. The percentage of the work executed with respected to each of the activity of the entire phase is detailed in Table B. Table A Sr. No. Tasks/Activity Percentage of work done 1 Excavation 100% Completed 2 1 number of Basement(s) and Plinth 100% Completed 3 0 number of Podiums --------- 4 Stilt Floor 100% Completed 5 13 number of Slabs of Super Structure 80% Completed 6 Internal walls, Internal Plaster, Floorings within 80% Completed Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, 0% Completed Electrical Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each 10% Completed Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, Elevation, 0% Completed completion of terraces with waterproofing of the Building/Wing, 10 Installation of lifts, water pumps, Fire Fighting Fittings 0% Completed and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment/ CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas Appurtenant to Building/Wing, Compound Wall and all other Requirements as may be required to Obtain Occupation/Completion Certificate. Table –B Internal & External Development Works in respect of the entire Registered Phase S.NO Common areas and Facilities, Proposed Percentage of Details Amenities (Yes/No) work done 1. Internal Roads & Footpaths NO N.A Single Building adjacent to Municipal Road 2. Water Supply YES 0% Building Under Construction 3. Sewerage (chamber, lines, YES 0% Building Under Septic Tank, STP) Construction 4. Storm Water Drains YES 0% Building Under Construction 5. Landscaping & Tree Planting YES 0% Building Under Construction 6. Street Lighting YES 0% Building Under Construction 7. Community Buildings NO NIL NIL 8. Treatment and disposal of NO NIL NIL sewage and sullage water 9. Solid Waste management & NO NIL NIL Disposal 10. Water conservation, Rain YES 0% Building Under water harvesting Construction 11. Energy Management NO NIL NIL 12. Fire protection and fire safety YES 0% Building Under requirements Construction 13. Electrical meter room, YES 0% Building Under Construction 14. Others (Option to Add more) NO NIL NIL Yours Faithfully, UDAY KANADIA (KRATAARTH ARCHITECTS) CA/2005/35347