Architect & Interior Designers S.S.Nadkarni & Associates Annexure A FORM 1 (See Regulation 31) ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and tier withdrawal of Money from Designated Account) To, Date: 25.02.2023 M/S. Radheya Construction Co. 118,Goyal Shopping Arcade, S.V. Road, Borivali West ,Mumbai 400092. Sir, Subject :-Certificate of completion of Construction Work of “Nalini Bhuvan Co.–Op. Housing Society Ltd.” having MahaRERA Registration No. P51800023013 , being developed by M/s. Radheya Construction Co. I, Mr. S. S. Nadkarni have undertaken assignment as Architect of certifying percentage of Completion of Construction Work of Nalini Bhuvan Co.Op.Hsg.Soc.Ltd. having MAHARERA Registration Number P51800023013 , being developed by M/s. Radheya Construction Co. Based on Site Inspection, with respect to Layout / each of the Building/Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MAHARERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. A-204, Shree Mangal, Jain Derasar Lane, Off Shmpoli Road, T.P.S. III, Borivali (W), Mumbai 400 092. Tel.: 2809 0785 Email: ssnadkarni_07@hotmail.com Architect & Interior Designers S.S.Nadkarni & Associates TABLE-A Nalini Bhuvan CHSL.(Single Building with only one wing) SR.NO TASK / ACTIVITY PERCENTAGE OF ACTUAL WORK DONE ( AS ON 25.02.2023) 1 Excavation. 100% 2 Basements (if any) N.A. 3 Podiums (if any) N.A. 4 Plinth. 100% 5 Stilt Floor. 100% 6 Slabs of Super Structure. 100% 7 Internal walls, Internal Plaster, Floorings, 100% Doors and windows within Flats/Premises. 8 Sanitary Fittings within the 100% Flat/Premises 9 Staircases, Lifts Wells and Lobbies at 100% each Floor level Overhead and Underground Water Tanks. 10 External plumbing and external plaster, 100% elevation, completion of terraces with waterproofing of the Building Wing. 11 Installation of Lifts, water pumps, Fire 100% Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all finishing work. A-204, Shree Mangal, Jain Derasar Lane, Off Shmpoli Road, T.P.S. III, Borivali (W), Mumbai 400 092. Tel.: 2809 0785 Email: ssnadkarni_07@hotmail.com Architect & Interior Designers S.S.Nadkarni & Associates TABLE-B Common Areas (Internal and External Development Works) in respect of the Registered Phase / Project Number P51800023013. SR.NO COMMON AREAS AND PROPOSED PERCENTAGE OF FACILITIES (YES / NO) WORK DONE AS ON 25.02.2023 ______________ 1 Internal Roads & Footpaths No N.A. 2 Water Supply Yes 100% 3 Sewerage (Chamber, lines, Yes 100% Septic Tank, SIP). 4 Storm Water Drains No N.A. 5 Landscaping & Tree Planting Yes 100% 6 Street Lighting No N.A. 7 Community Buildings No N.A. 8 Treatment and disposal of No N.A. sewage and sullage water. 9 Solid Waste No N.A. management & Disposal 10 Water conservation / Rain Yes 100% water harvesting 11 Energy management No N.A. 12 Fire protection and fire safety Yes 100% requirements 13 Electrical meter room. Yes 100% 14 Others (IF ANY) N.A. N.A. Yours Faithfully, Siddharth Digitally signed by Siddharth S. Nadkarni DN: cn=Siddharth S. Nadkarni, o, ou, S. Nadkarni email=ssnadkarni_07@hotmail.com, c=US Date: 2023.02.25 19:17:30 +05'30' Signature and name (IN BLOCK LETTERS) of Architect MR.S.S. NADKARNI. (Regn. No. CA-86/9718) Agreed and accepted by: Signature of Promoter Name: M/S. Radheya Construction Co. A-204, Shree Mangal, Jain Derasar Lane, Off Shmpoli Road, T.P.S. III, Borivali (W), Mumbai 400 092. Tel.: 2809 0785 Email: ssnadkarni_07@hotmail.com