Form 1 [See regulation 3] ARCHITECT’S CERTIFICATE To Newone Constructions Private Limited, S-14, 7th floor, Solitaire Corporate Park, Andheri-Ghatkopar Link Road, Chakala, Andheri East, Mumbai – 400 093 Subject: Certificate of Percentage of Completion of Construction Work for the Project Satellite Elegance [MahaRERA Registration Number– P51800021913 being developed by Newone Constructions Private Limited. Ref: Updates for Q.E. Sep 30, 2025. Sir, I, Kiran R Shirwatkar have undertaken assignment as Architect/Licensed Surveyor of certifying percentage of Completion of Construction Work of “Satellite Elegance” having MahaRERA Registration Number– P51800021913. Based on Site Inspection, with respect to each of the building/wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each building/wing of the Real Estate Project under MahaRERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire project is detailed in Table B. Table A Building Sr. No Tasks /Activity Percentage of work done 1. Excavation 100% 2. 1 number of basements and plinth 100% 3. 10 number of Podiums 100% 4. 1 Stilt Floor 100% 5. 23 number of Slabs of Super Structure (over and above plinth, 100% stilt and podium floor, 6. Internal walls, Internal Plaster, 76% Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 7. Sanitary Fittings within the Flat/Premises, - Electrical Fittings within the Flat/Premises 8. Staircases, Lifts Wells and Lobbies at each Floor level connecting 100% Staircases and Lifts, Overhead and Underground Water Tanks. 9. The external plumbing and external plaster, elevation, 50% completion of terraces with waterproofing of the Building/Wing. 10. Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common areas, electro, mechanical equipment, compliance to conditions of environment /CRZ NOC. 10% Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate. TABLE-B Common Area (Internal & External Development Works) in Respect of the entire Registered project Number: P51800021913. Common areas and Facilities, Proposed (Yes/No) Percentage Details Amenities of Work done 1. Internal Roads & Footpaths No N.A. 2. Water Supply Yes 0 3. Sewerage (chamber, lines, Yes 0 Septic Tank , STP) 4. Storm Water Drains Yes 0 5. Landscaping & Tree Planting Yes 0 6. Street Lighting No NA 7. Community Buildings No NA 8. Treatment and disposal of Yes 0 sewage and sullage water 9. Solid Waste management & Yes 0 Disposal 10. Water conservation, Rain water Yes 0 harvesting 11. Energy management Yes 0 12. Fire protection and fire safety Yes 0 requirements 13. Electrical meter room, sub- Yes 0 station, receiving station 14. Aggregate Area of recreational Yes 0 open space 15. Open parking No N.A 16. Children Play Area Yes 0 17. Entrance Foyer Yes 0 18. Gymnasium Yes 0 19. Landscape Garden Yes 0 20. Multipurpose Hall Yes 0 21. Security Cabin Yes 0 22. Security Office Yes 0 Agreed and accepted by Yours Faithfully Promotor Kiran R Shirwatkar For Newone Constructions Pvt. Ltd. Abhishek Jain (Authorised Signatory) Date: October 07, 2025 Place: Mumbai YASHWANT DATAR & ASSOCIATES ARCHITECT, PLANNER & CONSULTANTS