Annexure A FORM 1 (See Regulation 3) ARCHITECT'S CERTIFICATE (As on 31-03-2025) To, Neeleshwar Developers, H 602, Krishnavasant, Sagar Complex Village, Kandivali East, Borivali – 400101 Subject: Certificate of Percentage of Completion of Construction work as on 31-03-2025 of Satellite Heights having MahaRERA Registration Number: P51800021643 being developed by Neeleshwar Developers. Sir, I/We PB Associates have undertaken assignment as Architects/Licensed Surveyor of certifying Percentage of Completion of Construction work of Satellite Heights the building having MahaRERA Registration Number: P51800021643 being developed by Neeleshwar Developers. Based on Site Inspection, with respect to Layout/each of the Building /Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building / wing of the Real Estate Project under MahaRERA is as registered as per Table - A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A Layout/Building/Wing Number_____ Sr.No Task/Activity Percentage of Work Done (As of date of the Certificate) (1) (2) (3) 1. Excavation 100% 2. Number of Basement(s) NA 3. Number of Plinth 100% 4. Number of Podium 0% 5. Stilt Floor 100% 6. Slabs of Super Structure 85% Internal walls, Internal Plaster Floorings, Doors and 7. 78% Windows within Flat/Premises 8. Sanitary Fittings within the Flat/Premises. 64% Staircases, Lifts Wells and Lobbies at each Floor level 9. 59% Overhead and Underground Water tanks. The external plumbing and external plaster, elevation, 10. completion of terraces with waterproofing of the 40% Building/Wing. Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, finishing to entrance lobby/s, plinth protection, 11. 40% paving of areas appurtenant to Building/Wing, Compound Wall protection and all other requirements as may be required to complete project as per specification in agreement of sale. Any other activities. TABLE-B Common Area (Internal and External Development Works) for (Project Name) Percentage of Work Sr. Common areas and Proposed Done Details No Facilities, Amenities (Yes/No) (As on date of the Certified) (1) (2) (3) (4) (5) 1. Internal Roads & Footpaths No - ----NA---- 2. Water Supply Yes 35% ----NA---- 40% 3. Sewerage (chamber, lines, Yes ----NA---- Septic Tank, STP) 4. Storm Water Drains Yes 40% ----NA---- 5. Landscaping & Tree Planting Yes 40% ----NA---- 6. Street Lighting Yes 35% ---NA--- 7. Community Buildings No - ---NA--- No - 8. Treatment and disposal of ---NA--- sewage and sullage water. Solid Waste Management & No - 9. ---NA--- Disposal Water Conversation & Rain No - 10. ---NA--- Water Harvesting 11. Energy Management No - ---NA--- Fire Protection and fire 40% 12. Yes ---NA--- safety requirements Electrical metre room, 40% 13. sub-station, receiving Yes ----NA---- station. 14. Others (options to add more) No - ----NA---- +91 7738750063 11 parnavibassociates@gmail.com IBI Shreerang Society Thane 9 PB ASSOCIATES Ar. Parnavi Bangor Yours faithfully, Agreed and Accepted by: Signature & Name of L.S/Architect Signature of Promoter AR. PARNAVI BANGAR (License No - CA/2023/155164) Date: