+91 7738750063 parnavibassociates@gmail.com Shreerang Society hane PB ASSOCIATES Ar. Parnavi Bangar Annexure A FORM 1 (See Regulation 3) ARCHITECT'S CERTIFICATE (As on 31 /03/2023) To, Alag Property Constructions Pvt. Ltd.,A 6, Bps Plaza, Devidayal Road, Near Bus Depot, Mulund (WNest), Mumbai- 400080 Subject: Certificate of Percentage of Completion of Construction work as on 31/03/2023 of Alag Capital having MahaRERA Registration Number: P51800020773 being developed by Alag Property Constructions Pvt. Ltd. Sir, IWe PB Associates have undertaken assignment as Architects/Licensed Surveyor of certifying Percentage of Completion of Construction work of Alag Capital the building having MahaRERA Registration Number: P51800020773 being developed by Alag Property Constructions Pvt. Ltd. Based on Site Inspection, with respect to Layoutleach of the Building Wing of the aforesaid Real Estate Project, Icertify that as on the date of this certificate, the Percentage of Work done for each of the building / wing of the Real Estate Project under MahaRERA is as registered as per Table - A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. +91 7738750063 parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar Table A Building 1A Sr.No Task/Activity Percentage of Work Done (31/03/2023) (1) (2) (3) 1. Excavation 100% 2. Number of Basement(s) NA 3 Number of Plinth 40% 4 Number of Podium 10% 5. Stilt Floor 20% 6. Slabs of Super Structure o 0% 7 Internal walls, Internal Plaster Floorings, Doors and Windows within Flat/Premises 0% 8. Sanitary Fittings within the Flat/Premises. 0% Staircases, Lifts Wells and Lobbies at each Floor level 9. 0% Overhead and Underground Water tanks. The external plumbing and external plaster, elevation, 10. completion of terraces with waterproofing of the 0% Building/Wing. Installation of lifts,water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, finishing to entrance lobby/s, 11. plinth protection, paving of areas appurtenant to 0% Building/Wing, Compound Wallprotection and all other requirements as may be required to complete project as per specification in agreement of sale. Any other activities. +91 7738750063 parnavibassociates@gmail.com Shreerang Society Thane ( PB ASSOCIATES Ar. Parnavi Bangar Table A Building 1B Sr.No Task/Activity Percentage of Work Done (31/03/2023) (1) (2) (3) 1 Excavation 100% 2. Number of Basement(s) NA 3. Number of Plinth 40% 4. Number of Podium 10% 5. Stilt Floor 35% 6 Slabs of Super Structure 0% 7 Internal walls, Internal Plaster Floorings, Doors and Windows within Flat/Premises oa0% 8 Sanitary Fittings within the Flat/Premises. 0% 9 Staircases, Lifts Wells and Lobbies at each Floor level 0% Overhead and Underground VWater tanks. The external plumbing and external plaster, elevation,te 10. completion of terraces with waterproofing of the 0% Building/VWing.eo +91 7738750063 parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, finishing to entrance lobby/s, 11. plinth protection, paving of areas appurtenant to 0% BuildingWing, Compound Wallprotection and all other requirements as may be required to complete project as per specification in agreement of sale. Any other activities. Table A Building 1C Sr.No Task/Activity Percentage of Work Done (31/03/2023) (1) (2) (3) 1. Excavation 100% 2. Number of Basement(s) oon NA 3. Number of Plinth 35% 4. Number of Podium NA 5. Stilt Floor 100% 6. Slabs of Super Structurei 40% 7. Internal walls, Internal Plaster Floorings, Doors and Windows within Flat/Premises 0% 8 Sanitary Fittings within the Flat/Premises. 0% 9. Staircases, Lifts Wells and Lobbies at each Floor level 0% Overhead and Underground Water tanks. +91 7738750063 e parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar The external plumbing and external plaster, elevation, 10. completion of terraces with waterproofing of the 0% Building/Wing. Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, finishing to entrance lobby/s, 11. plinth protection, paving of areas appurtenant to 0% BuildingWing, Compound Wall protection and all other requirements as may be required to complete project as per specification in agreement of sale. Any other activities. TABLE-B Common Area (Internal and External Development Works) for (Alag Capital) Sr. Common areas and Facilities, Proposed Percentage of Work Done Details No Amenities (Yes/No) (31/03/2023) (1) (2) (3) (4) (5) 1 |InternalRoads &Footpaths No NA 2. Water Supply Yes 0% From M.C.G.M. 3. |Sewerage (chamber, lines, Yes 0% From M.C.G.M. Septic Tank, STP) Yes 4. Storm Water Drains 0% As Per SWC NOC. Yes 5. Landscaping &Tree Planting As Per Tree NOC 6 Street Lighting No NA 7. Community Buildings No NA 8 Treatment and disposal of No NA sewage and sullage water. +91 7738750063 parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar Yes Solid Waste Management & 50% As Per SWC NOC Disposal Yes 10. Water Conversation & Rain 0% Water Harvesting 11. Energy Management No NA Fire Protection and fire safety Yes 12. 0% As Per CFO NOC requirements Yes 13. Electrical metre room, 0% sub-station,receiving station. +91 7738750063 parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. ParnaviBangar Yours Faithfully, Agreed and accepted by: PBAssociates Ar.Parnavi Bangar Society C-101, Shreerang ThaneWest400601 No.7738750063 parnavibassociaesgmail.eon AR. PARNAVI BANGAR Signature of Promoter (License No - CA2023/1551 64) Alag Property Constructions Pvt. Ltd. Date: