+91 7738750063 e parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar Annexure A FORM 1 (See Regulation 3) ARCHITECT'S CERTIFICATE (As on 30/06/2023) To,oh Alag Property Constructions Pvt. Ltd., 6, Bps Plaza, Devidayal Road, Near Bus Depot, Mulund (West), Mumbai - 400080 Subject: Certificate of Percentage of Completion of Construction work as on 30/06/2023 of Alag Capital having MahaRERA Registration Number: P51800020773 being developed by Alag Property Constructions Pvt. Ltd. Sir, IWe PB Associates have undertaken assignment as Architects/Licensed Surveyor of certifying Percentage of Completion of Construction work of Alag Capital the building having MahaRERA Registration Number: P51800020773 being developed by Alag Property Constructions Pvt. Ltd. 0resuslRoidis Based on Site Inspection, with respect to Layoutleach of the Building Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building /wing of the Real Estate Project under MahaRERA is as registered as per Table - A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. +91 7738750063 e parnavibassociates@gmail.com PB ASSOCIATES Shreerang Society Thane Ar. Parnavi Bangar TableAHoRA Building 1A Sr.No Task/Activity Percentage of Work Done (30/06/2023) (1) (2) (3) 1. Excavation 100% 2. Number of Basement(s) 3 Number of Plinth 50% 4. Number of Podium 15% 5 Stilt Floor 30% 6 Slabs of Super Structure o e 0% 7. Internal walls, Internal Plaster Floorings, Doors andoarh pulA Windows within Flat/Premises 0% 8 Sanitary Fittings within the Flat/Premises. lee 0% 9 Staircases, Lifts VWells and Lobbies at each Floor level 0% Overhead and Underground Water tanks. The external plumbing and external plaster, elevation, 10. completion of terraces with waterproofing of the 0% Building/Wing. Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, finishing to entrance lobby/s, 11. plinth protection, paving of areas appurtenant to 0% Building/VWing, Compound Wall protection and all other requirements as may be required to complete project as per specification in agreement of sale. Any other activities. +91 7738750063 parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar Table A Building 1B Sr.No Task/Activity Percentage of Work Done (30/06/2023) (1) (2) (3) 1. Excavation 100% 2. Number of Basement(s) NA 3. Number of Plinth 45% 4. Number of Podium 15% 5. Stilt Floor 40% 6. Slabs of Super Structure 0% 7. Internal walls, Internal Plaster Floorings, Doors and Windows within Flat/Premises 0% 8 Sanitary Fittings within the Flat/Premises.0% Staircases, Lifts VWells and Lobbies at each Floor level 9. 0% Overhead and Underground Water tanks. The external plumbing and external plaster, elevation, 10. completion of terraces with waterproofing of the e 0% Building/Wing. Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanicalequipment, Compliance to conditions of environment /CRZ NOC, finishing to entrance lobby/s, 11. plinth protection, paving of areas appurtenant to 0% Building/Wing,Compound Wallprotection and all other requirements as may be required to complete project as per specification in agreement of sale. Any other activities, 491 7/3875063 parnavibasociates@grnail.corm Shreerang Society Thane G PB ASSOCIATES Ar. Parnavi Bangar Table A Building 1C Sr.No Task/Activity Percentage of Work Done (30/06/2023) (1) (2) (3) 1 Excavation 100% 2. Number of Basement(s) NA 3 Number of Plinth 40% 4. Number of Podium NA 5. Stilt Floor 100% 6. Slabs of Super Structure 50% 7. Internal walls, Internal Plaster Floorings, Doors and Windows within Flat/Premises 0% 8. Sanitary Fittings within the Flat/Premises. 0% 9. Staircases, Lifts Wells and Lobbies at each Floor level 0% Overhead and Underground Water tanks. The external plumbing and external plaster, elevation, 10. completion of terraces with waterproofing of the 0% Building/Wing. Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, finishing to entrance lobby/s, 11. plinth protection, paving of areas appurtenant to 0% Building/Wing, Compound Wallprotection and allother requirements as may be required to complete project as per specification in agreement of sale. Any other activities. +91 7738750063 parnavibassociates@gmail.com Shreerang Society Thane G PB ASSOCIATES Ar. Parnavi Bangar TABLE-B Common Area (Internal and External Development Works)for (Alag Capital) Propósed Percentage of Sr. Common areas and Facilities, Work Done Details No Amenities (Yes/No) (30/06/2023) (1) (2) (3)(4) (5) 1. Internal Roads & Footpaths No NA 2. Water Supply Yes From M.C.G.M. 3. |Sewerage (chamber, lines, Yes 0% From M.C.G.M. Septic Tank,STP) Yes 4. Storm Water Drains 0% As Per SWC NOC. Yes 5. Landscaping &Tree Planting 0 As Per Tree NOC 6. Street Lighting No NA 7. Community Buildings No NA Treatment and disposal of 8. No NA sewage and sullage water. Yes 9 Solid Waste Management & 50% As Per SWC NOC Disposal Yes Water Conversation & Rain 10. 0% Water Harvesting 11. Energy Management No NA Yes 12. Fire Protection and fire safety 0% As Per CFO NOC |requirements Yes 13. Electrical metre room, 0% sub-station, receiving station. +91 7738750063 E parnavibassociates@gmail.com Shreerang Society Thane PBASSOCIATES Ar. Parnavi Bangar Yours Faithfully, Agreed and accepted by: PBAssociates Ar.ParnaviBangar C-101, Shreerang Society ThaneWest400601 No.7738750063 parnavibassociatesgmail.eor AR. PARNAVIBANGAR Signature of Promoter (License No- CA/2023/155164) Alag Property Constructions Pvt. Ltd. Date: