+91 7738750063 parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar Annexure A FORM 1 (See Regulation 3) ARCHITECT'S CERTIFICATE (As on 31/12/2023) To, Alag Property Constructions Pvt. Ltd., 6, Bps Plaza, Devidayal Road, Near Bus Depot, Mulund (WNest), Mumbai - 400080 Subject: Certificate of Percentage of Completion of Construction work as on 31/12/2023 of Alag Capital having MahaRERA Registration Number: P51800020773 being developed by Alag Property Constructions Pvt. Ltd. Sir. IWe PB Associates have undertaken assignment as Architects/Licensed Surveyor of certifying Percentage of Completion of Construction work of Alag Capital the building having MahaRERA Registration Number: P51800020773 being developed by Alag Property Constructions Pvt. Ltd. Based on Site Inspection, with respect to Layout/each of the Building Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building / wing of the Real Estate Project under MahaRERA is as registered as per Table - A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. +91 7738750063 parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar Table A Building 1A Sr.No Task/ActivityesbhPercentage of Work Done (31/12/2023) (1) (2) (3) 1. Excavation 100% 2. Number of Basement(s) NA 3. Number of Plinth 70% 4. Number of Podium 25% 5 Stilt Floor 55% 6 Slabs of Super Structure 0% 7. Internal walls, Internal Plaster Floorings, Doors and Windows within Flat/Premises 0% 8 Sanitary Fittings within the Flat/Premises. 0% Staircases, Lifts Wells and Lobbies at each Floor level 9 0% Overhead and Underground Water tanks. The external plumbing and external plaster, elevation, 10. completion of terraces with waterproofing of the 0% Building/Wing. Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, finishing to entrance lobby/s, 11. plinth protection, paving of areas appurtenant to 0% Building/Wing, Compound Wall protection and all other requirements as may be required to complete project as per specification in agreement of sale. Any other activities, +91 7738750063 E parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar Table A Building 1B Sr.No Task/Activity Percentage of Work Done (31/12/2023) (1) (2) (3) 1 Excavation 100% NA 2. Number of Basement(s) 3. Number of Plinth 70% 4 Number of Podium 25% 5 Stilt Floor 60% 6 Slabs of Super Structure 0% Internal walls, Internal Plaster Floorings, Doors and 7 Windows within Flat/Premises 0% 8 Sanitary Fittings within the Flat/Premises. 0% Staircases, Lifts Wells and Lobbies at each Floor level 0% 9 Overhead and Underground Water tanks. The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the 0% 10. Building/Wing. +91 7738750063 parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, finishing to entrance lobby/s, 11. plinth protection, paving of areas appurtenant to 0% BuildingWing, Compound Wall protection and allother requirements as may be required to complete project as per specification in agreement of sale. Any other activities. Table A Building1C Sr.No Task/Activity Percentage of Work Done (31/12/2023) (1) (2) (3) 1. Excavation 100% 2. Number of Basement(s) NA 3. Number of Plinth 55% 4. Number of Podium NA 5. Stilt Floor 100% 6 Slabs of Super Structure O65% 7. Internal walls, Internal Plaster Floorings, Doors and Windows within Flat/Premises 0% 8 Sanitary Fittings within the Flat/Premises. 0% 9 Staircases, Lifts Wells and Lobbies at each Floor level 0% Overhead and Underground Water tanks. The external plumbing and external plaster, elevation, 10. completion of terraces with waterproofing of the 0% Building/MWing. +917738750063 e parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar Installation of lifts,water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, finishing to entrance lobby/s, 11. plinth protection, paving of areas appurtenant to 0% Building/Wing,Compound Wall protection and all other requirements as may be required to complete project as per specification in agreement of sale. Any other activities. TABLE-B Common Area (Internal and External Development Works) for (Alag Capital) Sr. Common areas and Facilities, Proposed Percentage of No Work Done Details Amenities (Yes/No) (31/12/2023) (1) (2) (3) (4) (5) 1. Internal Roads &Footpaths No NA 2. Water Supply Yes 0% From M.C.G.M. 3 Sewerage (chamber, lines, Yes 0% From M.C.G.M. Septic Tank, STP) Yes 4. Storm Water Drains 0% As Per SWC NOC. Yes 5. Landscaping &Tree Planting As Per Tree NOC 6. Street Lighting No NA 7. Community Buildings No NA 8 Treatment and disposal of No NA sewage and sullage water. Yes 9. Solid Waste Management & 50% As Per SWC NOC Disposal Yes 10. Water Conversation &Rain 0% Water Harvesting +91 7738750063 parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar 11. Energy Management No NA Yes 12. Fire Protection and fire safety 0% Ás Per CFONOC |requirements Yes Electrical metre room, 13. 0% sub-station, receiving station. +91 7738750063 e parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar Yours Faithfully, Agreed and accepted by: PBAssociates Ar.ParnaviBangar C-101, Shreerang Society Thane West 400601 No.7738750063 parnavibassocialesgmail.eor AR. PARNAVIBANGAR Signature of Promoter (License No - CA/2023/1551 64) Alag Property Constructions Pvt. Ltd. Date: