+91 7738750063 e parnavibassociates@gmail.com Shreerang Society Thane G PB ASSOCIATES Ar. Parnavi Bangar Annexure A FORM 1 (See Regulation 3) ARCHITECT'S CERTIFICATE (As on 31/03/2024) To, Alag Property Constructions Pvt. Ltd..Was 6, Bps Plaza, Devidayal Road, Near Bus Depot, Mulund (West), Mumbai - 400080 Subject: Certificate of Percentage of Completion of Construction work as on 31/03/2024 of Alag Capital having MahaRERA Registration Number: P51800020773 being developed by Alag Property Constructions Pvt. Ltd. Sir, IWe PB Associates have undertaken assignment as Architects/Licensed Surveyor of certifying Percentage of Completion of Construction work of Alag Capital the building having MahaRERA Registration Number: P51800020773 being developed by Alag Property Constructions Pvt. Ltd. Based on Site Inspection, with respect to Layout/each of the Building Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building / wing of the Real Estate Project under MahaRERA is as registered as per Table - A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. +91 7738750063 e parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar Table A Building1A Sr.No Task/Activityeoioute Percentage of Work Done (31/03/2024) (1) (2 (3) 1. Excavation 100% 2. Number of Basement(s) NA 3. Number of Plinth 80% 4. Number of Podium 35% 5. Stilt Floor Bpo 70% 6. Slabs of Super Structure Bo 0% Internal walls, Internal Plaster Floorings, Doors and 7. 0% Windows within Flat/Premises 8 Sanitary Fittings within the FlatPremises. 0% Staircases, Lifts Wells and Lobbies at each Floor level a 0% 9. Overhead and Underground Water tanks. The external plumbing and external plaster, elevation, 10. completion of terraces with waterproofing of the 0% Building/VWing. Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanicalequipment, Compliance to conitions of environment /CRZ NOC, finishing to entrance lobby/s, 11. plinth protection, paving of areas appurtenant to 0% Building/Wing,Compound Wall protection and all other requirements as may be required to complete project as per specification in agreement of sale. Any other activities. +91 7738750063 e parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar ote e b TableA u Building 1B Sr.No Task/Activity Percentage of Work Done (31/03/2024) (1) (2) (3) 1. Excavation 100% 2. Number of Basement(s) NA 3 Number of Plinth 80% 4. Number of Podium 35% 5. Stilt Floor 70% 6 Slabs of Super Structure 0% 7. Internal walls, Internal Plaster Floorings, Doors and Windows within Flat/Premises 0% 8. Sanitary Fittings within the Flat/Premises. 0% 9. Staircases, Lifts Wells and Lobbies at each Floor level on 0% Overhead and Underground VWater tanks. The external plumbing and external plaster, elevation, 10. completionof terraces with waterproofing oftheou2 0% Building/Wing. +91 7738750063 2 parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, finishing to entrance lobby/s, 11. plinth protection, paving of areas appurtenant to 0% BuildingWing, Compound Wall protection and all other requirements as may be required to complete project as per specification in agreement of sale. Any other activities. Table A Building 1C Sr.No Task/Activity Percentage of Work Done (31/03/2024) (1) (2) de (3) 1. Excavation 100% 2. Number of Basement(s) NA 3. Number of Plinth 70% 4. Number of Podium NA 5. Stilt Floor 100% 6. Slabs of Super Structure 80% 7. Internal walls, Internal Plaster Floorings, Doors and Windows within Flat/Premises 0% 8. Sanitary Fittings within the Flat/Premises. 0% 9. Staircases, Lifts Wells and Lobbies at each Floor level 0% Overhead and Underground Water tanks. +91 7738750063 parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar The external plumbing and external plaster, elevation, 10. completion of terraces with waterproofingof the 0% Building/MWing. Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, finishing to entrance lobby/s, 11. plinth protection, paving of areas appurtenant to 0% BuildingWing, Compound Wall protection and all other requirements as may be required to complete project as per specification in agreement of sale. Any other activities. TABLE-B Common Area (Internal and External Development Works) for (Alag Capital) Percentage of Sr. Common areas and Facilities, Proposed Work Done Details No Amenities (Yes/No) (31/03/2024) (1) (2) (3) (4) (5) 1 |Internal Roads &Footpaths No NA 2. Water Supply Yes 0% From M.C.G.M. 3. Sewerage (chamber, lines, Yes 0% From M.C.G.M. Septic Tank, STP) Yes 4. Storm Water Drains 0% As Per SWC NOC. Yes As Per Tree NOC 5. Landscaping &Tree Planting 6. Street Lighting No NA 7. Community Buildings No NA 8. Treatment and disposal of No NA sewage and sullage water. Yes 9 Solid Waste Management & 50% As Per SWC NOC Disposal +91 7738750063 e parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar Yes 10. Water Conversation &Rain 0% |Water Harvesting 11. Energy Management No NA Fire Protection and fire safety Yes 12. 0% As Per CFO NOC requirements Yes 13. Electrical metre room, 0% sub-station, receiving station. +91 7738750063 e parnavibassociates@gmail.com Shreerang Society Thane PB ASSOCIATES Ar. Parnavi Bangar Yours Faithfully, Agreed arnd accepted by: PBAssociates Ar.ParnaviBangar C-101, Shreerang Society ThaneWest400601 No.7738750063 parnavibassocintes(bgmail.eor AR. PARNAVI BANGAR Signature of Promoter (License No - CA/2023/1551 64) Alag Property Constructions Pvt. Ltd. Date: